The use of sandbags is a centuries old, tried
and true method for flood fighting.
See procedures and safety tips inside on
efficient bagging operations.
s:
Sandbag
a steadfast tool for flood fighting
andbagging is one of the most versatile
of flood fighting tools and is a simple,
effective way to prevent or reduce flood
water damage.
Although sandbags do not guarantee a
watertight seal, they are a proven deterrent to
costly water damage.
Sandbags have been used to:
• prevent overtopping of levees.
• direct a river's current flow to specific areas.
• construct ring dikes around boils on levee
back slopes, levee toes or behind levees.
• use as weight on back slopes of saturated
levees.
• weigh down visquine and straw bales.
• build buttresses on back slopes and the toes
of saturated levees.
• reduce seepage at closure structures.
Read this brochure to learn proper filling and
placement methods aimed at increasing
productivity of sandbagging operations. Included
are hints, safety tips and correct procedures
which will minimize work-related injuries and
strain and will maximize essential time.
THE FIRST LINE OF DEFENSE
Sandbag construction is a centuries old
technique that has changed little. Bags are made
from different materials including treated burlap
and plastic. They measure approximately 14
inches wide and 24 inches long.
Sandbags filled one-half to two-thirds full
should generally be left untied. Tied bags, filled
slightly fuller, have specific purposes: filling holes,
holding visquine or straw bales in place, or
forming barriers backed by supportive planks or
aluminum sheet piles.
If access to the flood site is limited to boat,
tractor or helicopter, then pallets and forklifts
may be needed to load and off-load sandbags.
Unused empty bags can be stockpiled for emer-
gency and will be serviceable for years if kept
dry and properly stored.
FILL MATERIALS
Sand is by far the easiest material for filling
and shaping sandbags and becomes heavier
when saturated from rain or moisture.
In emergencies, other materials such as silt,
clay, gravel or a mixture of these may be used,
but none work as well as sand.
When vehicle access is cut off to the flood site,
and you have no other choice, use the back side
of the levee or an adjacent field to find whatever
material is available to fill sandbags.
Here are pros and cons on use of other
materials:
Silty soils get soft when wet and are more
difficult to shape, and finer particles leak
through the weave in the material.
Clay materials are difficult to shape and to
bag.
Coarse-grained gravels are pervious and
are also difficult to shape but can be used
for redirecting the main stream flow while
allowing seepage through bags.
ALTERNATIVES
Other methods and remedies for flood fighting
are as follows:
• Readily available, straw bales are an
economical alternative. They range in size
from 18 inches high by 30 inches long to 4
by 4 by 8 foot long blocks. Secure the bales
by driving 4 to 10 foot stakes (or rebar)
through the straw into the levee top, and
weight down with filled sandbags. Water
swells the straw, making the bales heavier
and watertight.
• Concrete Jersey Barriers or Ecology Blocks
can be used to divert water and can be cost
effective solutions.
• Plastic sheeting can be used effectively by
placing sand along a fold.
• Overtopping
• Downed trees on
levee slope
• Gopher holes
• Seepage through
pervious levee material
• Saturated levee
embankments
• Seepage following
tree root paths
Flood Level
P ----q
iOM2
Downed ...._
CORRECT FILLING PROCEDURES
Filling sandbags is normally a two or three
person operation. One member of the team,
while crouching with feet apart
and arms extended, should place
the bottom of the empty bag on
the ground.
The opening of the bag is
folded outward about 1-1/2
inches to form a collar and held
open to allow the second team
member to empty a fully
rounded No. 2 shovel of material
into the open end of the bag.
Don't hurry. Haste can result
in undue spillage and added
work. The third team member
stockpiles or stacks the open
sacks. The three team members
should rotate duties often to reduce job -specific
muscle fatigue.
Untied bags should be filled approximately
one-half to two-thirds full. Tied
bags can be filled slightly more,
but with enough room left at
the top to tie the bag off
properly.
Always use gloves to protect
your hands during the filling
operation. After handling
treated bags, avoid contact with
your eyes and mouth.
Dress appropriately and layer
clothing. Safety goggles should
be used on dry and windy days.
Sandbag filling operations are
done either near the actual
placement site or at centrally
located filling sites such as fire
3
This two -member team uses correct
positions for sandbag filling.
stations, diking districts or sand pits.
If the bags are filled at a distant location,
vehicle transportation and access to the flood
site are primary planning considerations.
For large scale operations, a variety of
specialized filling equipment - such as funnels on
the back of dump trucks - is commercially available.
Such equipment is not always available during
an emergency and may be best suited for a
staging area where bags can be filled and then
delivered to the site.
PROPER PLACEMENT
Remove any debris from the areas where bags
are to be placed. Place the bags lengthwise and
parallel to the direction of flow. Fill the low
spots first before placing bags the full length
of the area to be raised.
Start at approximately 1 foot landward from
the river or levee's edge. Fold the open end of
the bag under the filled portion. Folded end of
bag should face upstream. Place succeeding
Veteran flood engineer Ernie Sabo demonstrates that
the sandbag should be two-thirds full, folded at the top.
4
bags with the
bottom of the
bag tightly and
partially
overlapping the
previous bag.
Offset adjacent
rows or layers by
one-half bag
length to avoid
continuous
joints.
To eliminate
voids and form a
tight seal,
compact and
shape each bag by
walking on it and
continue the
Place each succeeding bag tightly
against and parially overlapping the
previous one. Compact and shape each
bag by walking on it.
process as each layer is placed.
This flattens the top of the bag and prevents
slippage between succeeding layers.
SINGLE
STACK
PLACEMENT
Sandbags
stacked in a single
row work well in
flood areas where
there is no
streamflow
velocity or danger
from floating
debris, such as
logs and tree
stumps, or from
wave action which Single stack placement
could topple the bags.
Although generally not recommended to be above
three courses or layers in height (approximately 1
foot), higher single stack placement can be effectively
used as a barricade to protect structures from
impending water damage as shown in the photo.
PYRAMID PLACEMENT METHOD
Use pyramid placement to increase the height of
sandbag protection; however, use caution when
rasing the levee height. Determine the height of
the sandbag raise by using the best available
forecasts of flood conditions.
An example: When the water level is currently 1
foot below the top of the levee and is predicted to
rise 3 more feet, construct a 2-1/2 foot sandbag
operation which includes one-half foot of height
4 ft
3 ft
2 ft
1 ft
0 ft
as a safety factor.
It's important to compact each bag in place by
walking on it, butting the ends of the sacks toether,
maintaining a staggered joint placement and
folding under all loose ends.
Watch for flooding elsewhere, and watch for
boils on the landward side of the levee due to the
increased water elevation.
Bags Required Per 100
Linear Feet of Levee
Height of
Bags
Sandbag Levee
Required
1 foot
600*
2 feet
2100
3 feet
4500
4 feet
7800
* Single width course 1 foot high
requires 300 bags per 100 linear feet.
0 ft 2.5 ft 5 ft 7.5 ft loft
1 ft Width of Sandbag Pyramid Base
Minimum
The pyramid placement method issued to increase
the height of sandbag protection.
Use this rule of thumb in determining dimensions
of the pyramid:
• 1 bag in length equals about 1 foot
• 3 bags in width equals about 2-1/2 feet.
• 3 bags in height equals about 1 foot.
Place the sandbags by laying an equal number
of horizontal rows on the bottom as there are
vertical layers.
It's important to compact each bag in place by
walking on it, butting the ends of the sacks together,
maintaining a staggered joint placement and
folding under loose ends.
Minimum 2 ft. radius from
center of boil to edge of
ring dike.
• Tie into levee if boil is near
toe of levee
Build half-moon shaped ring
dike if boil is on levee slope.
RINGING SAND BOIL METHOD
A sand boil is created by water seepage
through the levee foundation or embankment.
When that seepage transports dirty water, the
levee's integrity is threatened.
Corps employees demonstrate building a ring dike.
SIDE VIEW
2 ft Minimum
It's generally not necessary to build a ring dike
around a boil that is not transporting soils but
monitor the boil for any change in condition.
Don't attempt to place sandbags directly on
the boil. Pressure applied to plug the boil will
cause water seeping through the levee to seek
other avenues to follow and could cause levee
failure.
As a minimum, there should be a 2 to 3 foot
radius from the center of the boil to the inside
edge of the ring dike. Take care to contain the
entire area experiencing boils within the ring
dike.
Build a spillway section in the dike so water
runs out in a controlled manner. This diverts the
overflow water away from the dike and reduces
erosion on the levee slope. Once the spillway
water runs clear, and is not transporting soils,
then the ring dike is completed.
U.S. ARMY CORPS OF ENGINEERS
The U.S. Army Corps of Engineers is the nation's
oldest engineering organization and one of its
oldest military branches. It dates back to the
Revolutionary War when, in 1775, George
Washington appointed Col. Richard Gridley as Chief
Engineer of the Continental Army.
The Corps' water resource program began in
1824 when Congress appropriated money for
Tip# 1: Use proper lifting techniques to avoid
injury and fatigue. Lift with your legs and
bend at the knees to save your back.
Tip #2: Sandbags are treated to prevent
deterioration when stored. Use work gloves
and avoid contact with your eyes and mouth.
Tip #3: Stay in eye contact with heavy equipment
operators and keep alert for truck backup
alarms.
Tip#4: Flood waters can be polluted. Use rubber
gloves and appropriate clothing if contact with
water is unavoidable.
Tip#5: Wear adequate clothing in layers and
watertight boots. Reflective material on outer
clothing is essential for night work.
Tip#6: Rotate team members frequently to
avoid fatigue.
Starting at the top, going clockwise:
Watch for trucks and other heavy equipment
frequently at flood sites; boots, clothing and other
items are necessary for flood fighting; and heavy
gloves are protection from treated burlap bags.
improving river navigation. In the following decade,
the involvement in civil works mushroomed,
including new roads, railroads and bridges, and
assistance to local communities during flood
disasters.
Annually Congress sets aside funds for disaster
response flood work. This gives the Corps the ability
0
This classic shot shows conditions frequently are not even close to perfect. In the early `50s, flood fighters moved fast and
furious to contain the swollen Snohomish River at Ebey island - a major flood event.
THE CORPS (continued from page 7)
to provide preparation, response and recovery
The Army Corps of Engineers conducts flood
measures concerned with flood fighting.
fight training every year which includes
Public Law 84-99 today authorizes the Corps
sandbagging techniques. The Corps' districts
to engage in flood fighting and rescue operations
maintain a limited supply of sandbags and other
if the emergency is beyond local and state
flood fighting materials intended to augment
capabilities. The Corps is there to perform a basic
the stocks of state and local jurisdictions during
mandate as set down by the Corps' forefathers.
actual flood emergency situations.
During a flood the corps has the authority to:
Local jurisdictions should first use their supplies
• inspect and, if necessary, strengthen flood
and then request additional sandbags from the
control structures,
state.
• make temporary levee raises,
If the state supplies become depleted, then
• provide supplies and 24-hour technical assis-
the Corps supplies are available for use when
tance, and
requested by state or local officials.
• assist in the evacuation of people and
livestock.