HomeMy WebLinkAboutResolution No. 2012-028 Approving Site Plan 7401 Metro Boulevard o� e � RESOLUTION NO.2012-28
o APPROVING A SITE PLAN
.,� FOR 7401 METRO BOULEVARD
City of Edina
BE IT RESOLVED by the City Council of the City of Edina, Minnesota, as follows:
Section 1. BACKGROUND.
1.01 Children s Design Group is requesting a Site Plan review for 7401 Metro Boulevard.
1.02 The applicant is proposing to build a Primrose Day Care Center on the newly created lot at
7401 Metro Boulevard.
1.03 The subject property is legally described as follows:
Lot 1, Block 1,One Corporate Center 2nd Addition
1.04 On January 11,2012, the Planning Commission unanimously recommended approval of the
project.
Section 2. FINDINGS
2.01 The proposal would meet the required standards and ordinances for a Site Plan.
2.02 Spack Consulting conducted a traffic impact and parking study,and concluded that the
existing roadway system could support the proposed project,and there would be more than
enough parking.
Section 3. APPROVAL
NOW THEREFORE,it is hereby resolved by the City Council of the City of Edina,approves
the Site Plan at 7401 Metro Boulevard for Children's Design Group.
Approval of the Site Plan is subject to the following conditions:
1. Subject to staff approval,the site must be developed and maintained in substantial
conformance with the following plans,unless modified by the conditions below:
• Site plan date stamped November 28,2011.
• Grading plan date stamped November 28, 2011.
• Landscaping plans date stamped November 28,2011 and January 5,2012.
• Building elevations date stamped November 28,2011 and January 6,2012.
• Building materials board including colors as presented at the Planning Commission
and City Council meeting.
City Hall 952-927-8861
4801 WEST 50TH STREET FAX 952-826-0390
EDINA,MINNESOTA,55424-1394 www.CityofEdina.com TTY 952-826-0379
} RESOLUTION NO. 2012-28
Page Two
2. Prior the issuance of a building permit, a final landscape plan must be submitted, subject
to staff approval. Additionally,a performance bond,letter-of-credit, or cash deposit must
be submitted for one and one-half times the cost amount for completing the required
landscaping, screening,or erosion control measures.
3. Before issuance of a building permit,a shared parking arrangement with the southern lot
must be executed.
4. The property owner is responsible for replacing any required landscaping that dies.
5. Submit a copy of the Nine Mile Creek Watershed District permit. The City may require
revisions to the approved plans to meet the district's requirements.
6. A construction management plan will be required for the construction of the new building.
7. Compliance with the conditions required by the city engineer in his memo dated January
5,2012.
Adopted by the city council of the City of Edina,Minnesota, n ry 11,2012.
ATTEST: Pad" - —
Debra A. Mangen,CAy C(Jrk James B. Hovland,Mayor
STATE OF MINNESOTA )
COUNTY OF HENNEPIN )SS
CITY OF EDINA )
CERTIFICATE OF CITY CLERK
I, the undersigned duly appointed and acting City Clerk for the City of Edina do hereby certify that
the attached and foregoing Resolution was duly adopted by the Edina City Council at its Regular
Meeting of January 11,2012, and as recorded in the Minutes of said Regular Meeting.
WITNESS my hand and seal of said City this day of 2012.
City Clerk