PROJECT CONTACTS
Business Liaison – Addison Lewis 612‐209‐3006
Project Inspector – George Bender 612‐360‐1321
Project Manager – Andrew Plowman 763‐287‐7149
March 26, 2014
France Avenue Pedestrian Improvement Project
Preliminary Schedule
DRAFT: SUBJECT TO CHANGE
Stage 1
Hazelton Drive to 69th Street
April 7 – June 15
Stage 2
69th Street to 66th Street
June 1 – August 23
Stage 3
76th Street to Gallagher
Drive
August 23 – October 15