HomeMy WebLinkAbout3139MINNESOTA DEPARTMENT LICENSE NUMBER #uwAn12479
OF NATURAL RESOURCES COMPANY PROJECT NO. BA-21-1
LICENSE FOR UTILITY TO CROSS PUBLIC WATERS
This license is issued by the State of Minnesota, acting by and through its commissioner of natural resources, and
hereafter called the "State", under authority and subject to Minnesota Statutes, section 84.415, and Minnesota Rules
Chapter 6135 and other applicable law, to the Licensee as named and for the fee and term as specified below.
Name and Address of Licensee: City of Edina
7450 Metro Boulevard
Edina, Minnesota 55439
License Fee: Two Hundred Thirty Seven Dollars and no/100 ($237.00)
Term (years): 50
Effective Date: June 15, 2021
Expiration Date: June 14, 2071
Purpose of License: Construction, maintenance and operation of a liquids pipeline under water under the covenants and
agreements of the Licensee to use the following described waters:
That part of the NE1/4 NW1/4 in Section 20, Township 28 North, Range 24 West in Hennepin County as shown on the
attached application and map, all of which are made a part hereof by reference.
This license is granted subject to the following provisions:
1. Use of premises.
A. This license is subject to the provisions of Minnesota Statutes, section 84.415 and Minnesota Rules Chapter
6135. All standards of Chapter 6135 are incorporated as terms and conditions of this license, except such
variations as are identified and approved by the State in the license applications, plans and specifications which
are attached and made part of the terms and conditions of this license. The Licensee is bound by the crossing
location and installation method as detailed in the application and approved by the State. The Licensee shall not
deviate from the terms and conditions of this license or the application as approved by the State unless it has first
obtained written permission from the State.
B. When the installation occurs more than six months after the issuance of the license, the Licensee shall contact the
State 20 days prior to installation.
C. No merchantable timber shall be cut, used, removed or destroyed without first paying the State the timber value
in the sum stated above as determined by the State. Slash material on state water crossings must be disposed of
within 30 days of clearing activities.
D. For overhead crossings of state waters, lines shall have a minimum clearance of 25 feet above the water, unless
otherwise approved by the State.
E. When directed by the State as a condition of the license, flight diverters shall be placed on overhead utility lines.
F. Any cable or conduit located at a shoreline shall be sufficiently buried so that it does not become exposed.
G. When directed by the State as a condition of the license, underwater crossings shall be marked by permanent
signs on the banks at the points where the line enters and leaves the public waters.
H. To protect fish spawning activities, the State may prohibit work in the public water or within a specified distance
of the public water during the spawning season.
2. State's rights and reservations. The use of these waters by the Licensee in constructing or maintaining the lines for
which this license is granted shall be subject to the use, sale, or leasing for mineral or other legal purposes. The
Licensee will not cause any unnecessary hindrance to the activities of the State and shall allow access across the
license area by the State when needed.
3. Erosion and Revegetation.
A. Erosion control measures shall be adequately designed for site characteristics. They shall be installed prior to
commencement of construction and maintained for as long as needed. All erosion control measures installed next
to a water body shall run parallel to the contours.
B. All disturbed areas shall be restored to original contours and elevations and stabilized as soon as possible
following construction. Areas of subsidence and crowing shall be repaired. Topsoil shall be reserved on site and
used to re-dress disturbed areas.
C. All disturbed areas shall be revegetated using state approved seed mixes. All seed and plant materials shall be
certified weed-free. Weed-free straw or hay shall be used for mulching and erosion control. Native species
plants should be used, whenever possible, to revegetate disturbed areas. This revegetation should occur as early
in the season as possible to permit adequate regrowth.
D. The Licensee shall monitor revegetation at state water crossings until the site is stabilized and the vegetation is
self-sustaining. Where severe or repeated damage is occurring or where measures have not been successful,
preventative and corrective actions shall be taken by the Licensee, including construction of appropriate barriers,
installation of warning signs, and other methods in consultation with the State.
E. The Licensee shall routinely inspect for erosion that may develop during the term of the license. Areas of erosion
shall be stabilized by the Licensee.
F. If a disturbed area cannot be stabilized with vegetation before September 15 in the year that the utility was
installed, the Licensee shall submit a written site stabilization plan to the State for approval. This plan shall
describe erosion control, mulching, dormant seeding and monitoring. Seeding shall occur as soon as soil
conditions are suitable.
G. Excavated materials shall not be deposited or stored alongside public water in a manner where the materials can
be redeposited into the public water by reasonably expected high water or storm run-off.
4. Herbicides and Pesticides.
A. The Licensee must request and obtain written permission to apply herbicides or pesticides to state waters t'rom
the State prior to treatment. This request shall consist of (1) a map identifying proposed treatment areas and (2) a
description of the proposed treatment plan, including target species, herbicide or pesticide name, rate of
application, a description of application method, and beginning and end dates. All applications must be
according to label regulations and as otherwise specified by the State. The Licensee shall not apply pesticides
that are restricted for use on certified state forest land administered by the State.
B. The Licensee must submit annual reports detailing herbicide or pesticide application on areas covered under the
license. The report must include the dates, acres, location expressed as quarter-quarter section, township and
range, herbicide or pesticide used, target species, and such other information as may be reasonably required by
the State for the purpose of verifying herbicide or pesticide use.
C. The Licensee shall post all places commonly used by the public for access along the utility corridors treated with
herbicides or pesticides.
5. Invasive Species.
A. The Licensee shall inspect all state water crossings for the presence of invasive species and noxious weeds prior
to commencing clearing activities and take action to prevent their spread. For installation of the utility line, the
State will identify on a map the known infested sites to be avoided. For maintenance and operation, the Licensee
is responsible for obtaining updated information on known infested sites.
B. If the State or the Licensee discover additional invasive species infestation areas on state water crossings during
construction, the Licensee shall immediately take action to prevent spread from the newly discovered infested
area and then consult with the State on a resolution.
C. The Licensee shall prevent invasive species from entering into or spreading within state water crossing by
cleaning equipment and clothing prior to arriving at the license area. The Licensee shall legally dispose of
material cleaned from equipment and clothing at a location offsite and the materials must be secured prior to
transport to avoid dispersal.
D. Whenever possible, parking, staging areas and travel routes shall not be within known infested sites. Where there
are multiple state water crossings and at least one contains invasive species, the Licensee shall to the extent
practicable start work at the site with the fewest number of invasive plants, leaving the most heavily infested sites
to last. The Licensee shall make every effort to schedule operations and site visits to avoid the spread of weed
seed.
2
E. The Licensee shall continue to control invasive species on state water crossings for the terms of the license using
methods approved by the State.
6. Crossing of State Trail.
A. The location of any crossing of a state trail must be approved in advance by the State. The State may provide
written instructions as to specific construction standards to be followed for the crossing of the state trail.
B. Utility installation and maintenance activities shall be conducted in a manner so as to minimize disturbance of
state trail use and to separate the public from work areas. The Licensee must provide signs to warn state trail
users of construction hazards.
C. The Licensee is responsible for repairing any damage to the state trail in a manner satisfactory to the State.
D. For maintenance and operations, prior approval must be obtained from the State for the cutting or trimming of
trees within the state trail right-of-way.
E. The Licensee may not close the state trail right-of-way without the prior written approval of the State.
7. Maintenance, operations and repairs.
A. The Licensee must keep the premises in a neat and orderly condition, and shall remove all refuse and debris that
may accumulate thereon.
B. After initial installation, no merchantable timber shall be cut, used, removed or destroyed by the Licensee without
first contacting the State at least 60 days in advance to determine if a timber payment is needed. Slash material
on state water crossings must be disposed of within 30 days of maintenance activities.
C. Emergency repairs and replacements may be made without prior notification to the State by the Licensee
according to conditions and standards prescribed by Minnesota Rules, Chapter 6135 and the method of
installation identified in this license. The Licensee shall notify the State of this activity as soon as practicable.
D. The Licensee shall employ appropriate erosion and sedimentation measures at the site during any emergency
repairs. The State must approve plans for restoration of the site after the emergency repairs are conducted.
E. Other than the herbicide or pesticide application reporting as provided in paragraph 4, the Licensee shall notify the
State of the extent and method of any routine maintenance and the proposed schedule. The notification must be in
writing and must be provided either annually or at least 20 days prior to commencing any routine maintenance work
on state water crossings subject to this license, The Licensee shall include a specific description of the proposed
maintenance activities including location, clearing methods, erosion and sedimentation control measures, removal of
merchantable timber, revegetation plans, and plans for preventing the spread of invasive species. The Licensee may
commence any routine maintenance work unless notified to the contrary by the State within 20 days after the State's
receipt of the maintenance plan. The State may require the Licensee to adjust its maintenance plans due to natural
resource management concerns.
8. State inspection. The project hereunder shall at all times during and after construction is subject to inspection by the
State and for that purpose the Licensee shall grant access to the premises at all reasonable times.
9. Compliance with laws. The Licensee shall comply with all federal, state and local laws and regulations, including
municipal ordinances, affecting said lands or the area in which they are situated.
10. Taxes and assessments. The Licensee will pay when due all taxes and assessments levied against said waters or any
improvements owned, used, or controlled by the Licensee, provided that the taxes or assessments are imposed due to
this license.
11. Enforcement. No delay by the State in enforcing any of the conditions of this license shall operate as a waiver of
any of its rights.
12. Liability. This license is permissive only. No liability shall be imposed upon or incurred by the State of Minnesota
or any of its officers, agents, or employees, officially or personally, on account of the granting of the license or on
account of any damage to any person or property resulting from any act or omission of the Licensee or any of its
agents, employees, or contractors relating to any license matter. This license shall not be construed as estopping or
limiting any legal claims or right of action of any person against the Licensee, its agents, employees, or contractors
for any damage or injury resulting from any such act or omission, or as estopping or limiting any legal claim or right
of action of the State against the Licensee, its agents, employees, or contractors, for violation of or failure to comply
with the provisions of the license or applicable provisions of law. The Licensee shall indemnify and hold harmless
3
Title
By
Title cv•Ant.r.
Date I
CITY OF EDINA
Licensee(s)
By
WLEDGED ACCEPTED AND
the State from all claims arising out of the Licensee's use of the above described lands whether such claims are
asserted by civil action or otherwise.
13. Termination and cancellation.
A. At the end of the license period and if both parties wish to renew, the renewal fee will be determined by the State.
B. This license shall be cancelable upon reasonable notice by the State for violation of any of its terms, or if at any
time its continuance will conflict with a public use of the land over or upon which it is granted, or for any other
reason. Licensee shall ensure that Licensee's employees, agents and contractors have received and thoroughly
understand all conditions of this license.
C. Unless otherwise authorized by the State, upon the surrender, expiration or cancellation of this license, the
Licensee shall remove from the above described lands all the utility lines and related structures owned by it. If
Licensee does not remove such lines or related structures, all such lines or structures remaining shall become the
property of the State, to be used or disposed of as the State elects. If the State requires the Licensee to remove
utility lines and related structures and Licensee fails to do so, the Licensee agrees to pay the State for the costs of
removing and disposing of such lines or structures.
14. Assignment or transfer. The Licensee shall not without the State's prior written consent: a) assign, convey or
otherwise transfer this license or any interest under it; b) sublet the license corridor or any part thereof; or c) permit
the use or occupancy of the license corridor or any part thereof by anyone other than the Licensee. This license shall
extend to, and bind the successors, heirs, legal representatives and assigns of the Licensee, if any. The State may
require a party who has requested to sublet, use or occupy the license corridor to obtain a separate license from the
State prior to occupying or using the license corridor.
15. Reports. The Licensee must submit reports on herbicide and pesticide use as provided in paragraph 4 and
maintenance and repair work as provided in paragraph 7.
16. Contacts. The contact for the State is the Regional Lands and Minerals Operations Supervisor, who is Joey Rokala
at (218) 328-8923. Any questions about this license shall be directed to the Regional Lands and Minerals Operations
Supervisor. The'regional Lands and Minerals Operations Supervisor may direct the Licensee to contact additional
State staff for revie s and approvals.
17. Special provisi his license is subject to the SPECIAL PROVISIONS attached hereto (if none, state none). None
STATE OF MINNESOTA
DEPARTMENT OF NATURAL RESOURCES
By
Regional Lands and Minerals Operations Supervisor
Date
4