HomeMy WebLinkAbout2025-2030 Capital Improvement PlanCity of Edina, Minnesota
Capital Improvement Plan
2025-2030
(Adopted December 17th, 2024)
Edina City Council
Mayor James Hovland
Council Member Kate Agnew
Council Member Carolyn Jackson
Council Member James Pierce
Council Member Julie Risser
City of Edina Staff
City Manager Scott Neal
Assistant City Manager Ari Lenz
Finance Director Pa Thao
Assistant Finance Director Nelly Chick-Brewer
Contributing Staff
Financial Analyst Mallory Jensvold
City Management Fellow Zoe Johnson
Table of Contents
Introduction 4-23
Overview 4
Organization 5
Vision Edina 6
Budget & Work Plan Process 7
Budget Goals 8
CIP Introduction 9
CIP Process 9-16
Funding Sources & Financing 17-23
Funded Project Data 24-298
Funded Projects by Funding Source 24-36
Funded Projects in Detail Sorted by Department 37-298
Appendices 299-351
Funding TBD Projects by Department 299-301
Funding TBD Projects in Detail Sorted by Department 302-351
3
Introduction
The City of Edina has over $550 million invested in capital assets that either need to be maintained
or replaced. This number includes things such as land, buildings, roads, water and sewer lines,
vehicles and equipment. The Capital Improvement Plan (CIP) is one of several ways that the City
supports Vision Edina, the long-term strategic framework of the City.
The 2025-2030 Capital Improvements Plan is a six-year, $547 million plan. This is an increase
from the 2023-2028 funded $300 million plan. The increase is due to several large capital projects,
including improvements to France Avenue Crossing Gallagher & 72nd ($16 million) and Citywide
Roof Replacements ($12.5 million), construction of Fire Station 3 ($50 million), Braemar Golf
Course Clubhouse ($27 million), Neighborhood Reconstruction projects ($63 million), Storm
Water projects ($71 million), Water Utility projects ($68 million), and Sewer projects ($35
million).
This plan includes 256 funded projects, a significant increase from 162 projects in the 2023-2028
CIP. This growth can be attributed to a structural change made in the 2023-2028 CIP where only
projects with identified funding sources were included in the plan. This is contrasted by previous
years’ CIPs where both funded and unfunded projects were included. While unfunded projects
are tracked internally for future consideration, the rising number of funded initiatives underscores
the growing need to address equipment maintenance, repairs, and expansion of community
services. These efforts are critical to ensuring the City's infrastructure and amenities meet the
evolving demands of residents.
Approximately $280 million is planned for infrastructure
projects, $28 million for parks projects, another $32
million is planned for vehicle and equipment replacement,
over $188 million for building improvements, $12 million
for land improvements, and $7 million for technology.
Additionally, The American Rescue Plan Act (ARPA)
funding project is nearing the final phase. These federal and
state-distributed funds were allocated to provide economic
relief in response to the COVID-19 pandemic. The City has
primarily directed these resources toward enhancing public
amenities and infrastructure at Centennial Lakes Park.
Additionally, the Local Option Sales Tax (LOST), approved by voters in November 2022,
generates revenue through a half-cent sales tax. This funding supports the implementation of the
improvements detailed in the Fred Richards Park Master Plan and the Braemar Park Master Plan.
Buildings
35%
Equipment & Vehicles
6%Parks
5%Technology
1%
Land
2%
Infrastructure
51%
2025-2030 CIP Project Costs by Type
4
Organization
The City of Edina operates under the Council-Manager form of government. Policy-making and
legislative authority are vested in a City Council (Council) consisting of the Mayor and four other
members, all elected on a non-partisan basis. The Council is responsible for, among other things,
adopting the budget, approving ordinances, appointing committees and hiring the City Manager.
Council members serve four-year terms, with two Council members elected every two years.
The Mayor also serves a four-year term. The Council and Mayor are elected at large.
The City Manager is responsible for carrying out the policies and ordinances of the Council and
overseeing the day-to-day operations of the city government. Edina has six “operating”
departments which primarily serve the community and four “supporting” departments which
primarily work within the City serving operating departments, in addition to the Administration
Department which includes the City Manager and Assistant City Manager.
RESIDENTS
Operating Departments
5
Vision Edina
Vision Edina is a long-term strategic framework that aids in community understanding and
guidance in important decision making that will impact Edina’s future. The Vision Edina work and
publications have been developed through a broad based and inclusive community visioning
process conducted in 2014. This framework lays out the City’s vision, and mission.
Vision: Edina holds a well-earned reputation as a city of choice. It is the model of a successful,
mature, and progressive urban community, that strives to lead in a modern and evolving world.
We maintain our heritage and attractiveness, and afford our residents the highest quality of life,
while actively embracing the future. The features that define our future community include:
Inclusive and Connected
Built-to-Scale Development
Sustainable Environment
Community of Learning
Future-Oriented
Mission: To provide effective and valued public services, maintain a sound public infrastructure,
offer premier public facilities and guide the development and redevelopment of lands, all in a
manner that sustains and improves the health and uncommonly high quality of life enjoyed by our
residents and businesses.
Eight key strategic focus areas have emerged through the Vision Edina process. This framework
lays out the key issues identified by our community, which we need to focus our attention and
resources on over the coming years.
Residential Redevelopment Mix
Transportation Options
Commercial Development Mix
Live and Work
Educational Focus
Population Mix
Environmental Stewardship
Regional Leadership
6
Budget & Work Plan Process
In the City of Edina, the Capital Improvement Plan is part of a comprehensive approach to
performance management supporting Vision Edina.
The City Council and staff develop a two-year Budget Work Plan that coincides with the
operating budget. The operating budget and Capital Improvement Plan processes occur on
alternating years. While both the operating budget and CIP will be reviewed every year, much
of the planning, focus and effort will occur on a biennial basis. The process begins with identifying
the goals, objectives, and actions that will put the City in the best position to achieve the
outcomes identified in the City’s strategic plans.
Vision Edina
(Twenty-year)
Comprehensive
Plan
(Ten-year)
Capital
Improvement
Plan
(Five-year)
Strategic
Policy
Budget Work Plan (Two-year)
Operating Budget (Two-year)
Department Work Plans (Annual)
Implementation
7
The following Budget Pillars & Values were identified by the City’s Leadership Team and City
Council for the 2024-2025 operating budget cycle:
Pillars
Budget pillars are two-year broad outcomes to be achieved by the budget.
Strong Foundation
City infrastructure, facilities, technology, and equipment meets
community needs now and in the future.
Reliable Service
City services enhance the safety, wellbeing, and quality of life
experienced in Edina.
Livable City
City planning fosters healthy, connected, sustainable
development that enriches the lives of current and future
residents.
Better Together
City government fosters an inclusive, informed, and engaged
community.
Values
Budget values are beliefs that guide decision making. The values should be considered when
making recommendations and asking for council action.
Stewardship:
We make wise
investments that focus
on the best long-term
value for residents
Health:
We use Health-in-All
Policies to promote and
protect the physical,
mental, and social wellbeing
of all people who live,
work, or visit Edina
Equity:
We provide equitable
opportunities for people
to participate in their city
government and access
City institutions, facilities,
and services
Sustainability:
We ensure that our
policies, decisions, and
plans have a positive
impact on people and the
planet now and for future
generations
8
Capital Improvement Plan
Introduction
The CIP represents a framework for planning the preservation and expansion of infrastructure,
facilities, equipment, and technology while at the same time advancing towards our long-term
vision. The CIP serves as a form of policy document that outlines both needs and an expectation
that projects will be reprioritized according to timing, changing needs and finances available. The
CIP is the first step towards estimating schedules, costs, and sources of revenues to pay for higher
priority projects.
• The City’s threshold for projects or equipment to be included in the CIP is $20,000. Projects
or equipment expected to be under the threshold are instead included in the operating
budget.
• In the CIP, the definition of a capital asset differs from GAAP financial accounting. The main
difference being that the CIP can include maintenance expenditures that do not meet the
GAAP definition of a capital asset.
• The preparation of a long-range plan requires City staff to make material estimates of project
scope, costs of labor and materials, anticipated interest rates, and other items. Many times,
these estimates come from staff experience, outsourced published projections, vendor
estimates, or a combination of resources. Generally, estimates for earlier years are more
precise than later years. Actual results can differ significantly from such estimates.
Process
For both the CIP and the operating budget, it is the responsibility of City staff to gather
information and develop a recommendation for the City Council to consider. City Council’s role
is to guide City staff through the process and to formally adopt a CIP near the end of every even-
numbered year. After adoption of the Capital Improvement Plan, staff will develop additional
recommendations on how to proceed with specific projects.
The process includes numerous instances of City Council oversight, including a kickoff meeting
to review the process of developing the CIP, multiple reviews of draft CIPs and final approval of
the 2025-2030 CIP. The calendar on page 16 provides a more detailed view of the full-year
process.
9
Originally launched with the 2021-2026 CIP, the City implemented a formal departmental scoring
process that standardizes priorities and functions across departments. The departmental scoring
is high, medium, low, defined as:
Additionally, a prioritization committee comprised of select staff from all departments provides
another level of review and scoring with the criteria outlined below. The asset preservation
project created to address immediate facility repair needs also receives semi-annual review and
scoring using this criterion.
Criteria I – Justification
Project justification looks at three different asset categories, which most often coincide with
project urgency. Projects are assigned one or multiple categories if applicable.
• Health, Safety & Regulatory Compliance: Asset does not meet health and safety
standards, has existing code violations, and/or displays safety hazards or structural
defects.
• Asset Functionality: Asset is no longer functioning properly or is expected to no longer
function properly soon.
• Expansion and/or Level of Service: Asset improvement or addition will directly impact
level of access and/or service output.
The projects summarized on the following page were identified as projects that have the most
significant justification for funding.
10
Aquatic Center Filter Room
Health, Safety & Regulatory Compliance: Aspects of the pool filtration equipment no longer
meet the Minnesota state Building Code. Expansion of surge tanks and upgrades to
equipment are required. Pathways and maintenance spaces would also be designed for
current pool, building, and health codes.
Asset Functionality: An assessment was initiated in 2022 after an electrical failure closed the
facility during peak season. Critical repairs were made to keep functionality and safety of the
pool, but it was determined that additional repairs to existing equipment were not fiscally
responsible due to existing conditions that have drastically accelerated wear and degradation
of equipment. The pump room structure dates back to 1958 and while additions have been
made since then, much of the equipment remains dependent on the original building and
piping. It was determined that a new equipment room was needed to ensure sustainability of
future investments and replacements.
Expansion and/or Level of Service: The new structure allows for not only mechanical and
electrical spaces but also the enhancement and increase of square footage above the
structure on the pool deck apron. This will provide an opportunity to increase both services
and seating areas.
Public Works Building Emergency Services Radio Repeater
Health, Safety & Regulatory Compliance: As of April of 2020, Minnesota State Statue
7511.7900 Appendix P requires all commercial buildings to have working emergency
responder radio coverage within a building. The radio repeater in the Public Works building
functions but has some “dead” spots throughout the building that pose reliability concerns.
If an emergency was to occur within the space, the city would rely on a functioning unit to
ensure public safety needs are met. Replacing the system will ensure that we are able to
provide this critical function at a time of crisis.
Edinborough Park Pool HVAC Unit
Asset Functionality: Over the past 5 years the HVAC unit that supplies cooling to the pool
and track area has broken down on four different occasions, most often during winter
months. These repairs have cost tens of thousands of dollars and generally require
emergency repairs and down-time of the pool and track which significantly and negatively
impacts the services and amenities provided to users.
11
Criteria II - Values
Our budget values guide decision-making. Each project identifies how it meets our budget values,
understanding these core values guide what projects received funding. The projects summarized
below were identified as projects that best represent our values regardless of funding status.
Stewardship
We make wise investments that focus on the best long-term value for residents.
Aquatic Center Filter Room
The Edina Aquatic Center has operated in its current state since the early 2000’s and has
been added onto a number of times. Its current configuration no longer meets today’s pool
standards and requirements and as a result must be expanded to do so. The city has
researched various options and scenarios that include both complete replacement and
refurbishment and determined a hybrid of replacement and refurbished equipment was the
most cost-effective approach to this project.
Edinborough Park Pool Filter Replacement
Replacement of filters that assist with keeping water chemistry levels in safe alignment helps
to minimize the need for chemical treatment of pools and other aquatic facilities. These
chemicals, while needed for the operation of the pools, can also wreak havoc on pool
equipment and structures, therefore, it is crucial to maintain the filters. Regular maintenance
and replacement will extend the life of the filters and cut down on the cost of chemical
treatments which will intern extend the life of the surrounding and supporting equipment.
Edinborough Park Replace Camus Boiler
Planned replacement of boilers and mechanical equipment eliminates costly emergency
repairs and replacements. When planned correctly, these replacements can be addressed
during off-seasons, further reducing the cost and impact on amenity users.
Health-In-All Policies
We use Health-in-All Policies to promote and protect the physical, mental, and social wellbeing
of all people who live, work, or visit Edina.
Pedestrian And Bicycle Master Plan Update
Walking and biking are important activities that can improve and maintain physical health.
Well planned walking and biking routes can also encourage social interaction and improve
access to healthy food and activities. An update of the pedestrian and bicycle master plan on
a regular basis will evaluate the existing system and make future recommendations that adjust
to new construction, land use, and changes in how and where people move.
12
Rosland Park Master Plan
Access to green space for physical activity, mental health, and social connection is an integral
part of one’s well-being. Park planning will review the current state of Rosland Park and plan
for necessary adjustments to improve access to park facilities, equipment, programming and
green space. As demographics and density of the population changes, the Rosland Park
Master Plan should assess immediate and future needs of park users. These needs may
include easier ways to access the park, accessibility of park features and equipment, and
updated programming.
Edinborough Park Pool Filter Replacement
Edinborough Park swimming pool provides access to swimming and aquatic activities for both
physical fitness and entertainment. Safe water in the pool is a critically necessary part of
operations, and requires daily testing, maintenance and adjustments. Pool filters lose efficacy
over time and must be replaced to keep water safe for swimmers and to reduce the time
spent by pool operations staff on manually changing the chemistry of the water to ensure
safety. Replacement of the existing filters will provide a more consistent and safer experience
for swimmers while reducing dedicated amount of staff time spent on water chemistry.
Equity
We provide equitable opportunities for people to participate in their city government and access
City institutions, facilities, and services.
Parks Accessibility Improvements
Public accessibility improvements, including City of Edina facilities, aligns with the city's equity
value by expanding accessibility of programs and services for all to use. All public facilities
should be available for all users to access regardless of ability. This project aligns with the
ADA Transition Plan and already has CIP funding allocated to address facility needs,
grievances, and right of way. Examples of improvements to park accessibility include
resurfacing trails, adaptive equipment and new programming to further meet the needs of a
diverse and growing community.
Rosland Park Master Plan
The Rosland Park Master Plan is the first large study to identify overall park and facility needs.
Rosland Park has notably aged since inception while daily users continue to increase.
Attractions like the Edina Aquatic Center contribute to Rosland Park’s diverse population of
daily visitors. As a new pedestrian bridge and aquatic center renovations are being planned,
this study would allow for and encourage community engagement in a holistic analysis of the
park for new programming, services, and/or facility needs that aim to maximize both
recreational and natural resource potential.
13
Centennial Lakes Park Public Wi-Fi
The Centennial Lakes Public Wi-Fi project continues efforts to increase accessibility to Wi-
Fi throughout the City of Edina. In the 2022 American Community Survey, 36.3% of those
with a household income of less than $20,000 reported having no internet subscription, while
13.7% of those with household incomes ranging between $20,000-74,999 also reported no
internet subscription. By comparison, 9.7% of Edina residents reported a household income
of less than $25,000. In the 2023 Quality of Life Survey provided to Edina residents, 39% of
residents rated fiber/home internet connectivity less than good or excellent, a number that
increases above 50% for Hispanic and other race groups, and residents 18-54 years old.
Reliable public Wi-Fi throughout the city helps Edina community members stay connected
to public services, programming, and information, as needed.
Sustainability
We ensure that our policies, decisions, and plans have a positive impact on people and the planet
now and for future generations.
Public Works Fleet Bio Diesel Storage Tanks
Biodiesel is a low carbon, cost-effective fuel option to reduce emissions from diesel-powered
petroleum vehicles. To meet our Climate Action Plan goals to decarbonize municipal fleet
vehicles, biodiesel is a cost-effective option for medium- and heavy-duty fleet. This project
will allow the City to install a new dedicated biodiesel tank to deliver 100% biodiesel to its
existing heavy-duty fleet. It’s anticipated that a 100% biodiesel powered vehicle reduces
emissions by almost 75% compared to petroleum diesel.
DC Fast Charger
To meet the City’s carbon emission reduction goals, we are transitioning light- and medium-
duty fleets to battery and plug-in hybrid battery electric vehicles. To fuel these electric
vehicles, the City has installed Level 2 charging stations at different City buildings, including
dedicated Level 2 chargers for fleet at its Public Works facility. A Level 2 charger often takes
multiple hours to fully charge an electric vehicle, whereas a Level 3 charger can provide up
to 40 miles of range in about 10 minutes. A dedicated Level 3 charger for fleet vehicles will
reduce the downtime for electric fleet vehicles, including public safety vehicles that run 24-
hour operations.
Edinborough Park Replace Camus Boiler
Aging mechanical equipment is inefficient and often costly to maintain and operate; and
wasting energy results in higher greenhouse gas emissions which negatively impacts our
ability to meet our climate goals. Edinborough Park is one of the City’s highest energy users
and replacing its boiler with a more energy-efficient model will result in reduced energy costs
and a more comfortable environment for residents and visitors who use the park.
14
Community Engagement
We foster an inclusive, informed and engaged community.
Rosland Park Master Plan
Rosland Park is a destination park which offers pathways for walking, an inclusive playground
and a large gathering space. Annually, the picnic shelter has as many as 300 reservations for
birthday parties, graduation celebrations and other gatherings. An investment in a master
plan could enhance the current positive attributes and plan for future opportunities to be
welcoming and engaging for all.
Parks Accessibility Improvements
Accessibility improvements support overall access to city parks and positively impact
recreational programming. As demographics change, conforming to ADA requirements and
assessing the needs of the community will provide broader programming and more inclusive
city parks.
Edina Art Center Design
The Edina Art Center opened in 1977 at its current location out of a home built in 1948.
For years, the art center has offered programming, an art gallery and gift store. The current
facility needs structural work and is not accessible. The city’s potential partnership and design
opportunity with the Hennepin County Library will allow the city to offer services in the
southeast quadrant while also emphasizing improvements to accessibility and creating a
welcoming space.
The 2025-2030 CIP is designed to be a financially viable plan for specific infrastructure projects,
based on existing and proposed funding availability and policy guidance provided by the City
Council. Implementation of this plan occurs when City Council takes action to initiate an
individual project. By adopting the CIP, the City Council is providing overall policy guidance on a
long-term community investment plan. Implementation of this plan occurs when individual project
details are presented to City Council for formal approval and initiation.
In addition to consideration of the overall project plan, the CIP serves as a mechanism to
highlight policy issues that could significantly impact future capital project funding. These issues
are presented as an opportunity for the City Council to provide additional guidance to staff if
appropriate.
15
20th
Public hearing held for
2025-2030 CIP & 2025
Operating Budget
CIP Prioritization
Committee Final Review
& Recommendations
City Council adopts
2025-2030 CIP & 2025
Operating Budget
6th
DECEMBER 2023
MAY 2024
CIP staff kickoff
JULY 2024
APRIL 2024
JUNE 2024
CIP community
engagement begins
AUGUST 2024
SEPTEMBER 2024
DECEMBER 2024
19th 2024 – 2025 Budget &
Work Plan approved by
City Council
10th
17th
29th
20th
17th
3rd
Departments submit
CIP requests
City leaders discuss
CIP project
prioritization
City Council adopts
preliminary 2025 levy
Draft 2025-2030 CIP
presented to City
Council during
Work Session
CIP goal setting during
City Council Retreat
17th
18th City Manager final
CIP draft review
25th
21st
MARCH 2024
31st CIP Prioritization
Committee begins
project review
CIP Prioritization Committee
& City Council Site Tours
2024-2025 Capital Improvement Plan Roadmap
16
Funding Sources and Financing
Planning for capital improvements requires sound and economic financing. The City of Edina has
many options for funding sources and financing. The identified funding method for each
improvement is based on the City’s general policies, past practices, and legal and practical
considerations. The final selection and scheduling of proposed capital improvements is then based
on the ability of the City to draw upon various funds. Many of the funding sources the City uses
to pay for CIP projects are restricted to use. Each of these funding sources is examined in more
detail in this section.
For many of the above funding sources, the City and/or the HRA may decide to sell bonds to pay
the upfront costs of a project when cash flows from the project funding sources are not
immediately available. For other projects without a dedicated funding source (utility revenues,
franchise fees, etc.), one of the few options available to pay for this type of project is a tax levy.
Shown below is a strategy whereby an increase in the CIP levy is offset by expiring debt service
levies (in green) for City Hall and the Gymnasium.
Utility Funds
32%
Other
Funds
4%
HRA Funds, 3%
PACS Fund
3%
Construction Fund
58%
2025-2030 CIP by Funding Source
17
Debt Service Fund and Construction Fund Levies
The strategy of increasing the CIP Levy as other levies expire allows the city to prioritize
maintaining physical assets and infrastructure, as is emphasized in City Goal 1: Strong
Foundation. In 2018, the City completed a three-year review process of 117 buildings to create
a master replacement schedule for physical buildings, plumbing, HVAC and other mechanical
systems, components, fixtures and equipment to optimize long-term financial resources and meet
sustainability goals. Building improvement projects submitted for the 2023-2028 CIP include
maintenance identified through new data collected.
The City’s 2025 annual comprehensive budget is approximately $212 million. Much of that budget
is spent on operating costs to provide community services. Part of the annual budget also pays
for debt service on debt that has already been issued to pay for past projects. The final part of
the budget is for capital improvements, which is the focus of this CIP plan. The graphic below is
a conceptual diagram of the City’s budget, split between governmental activities and enterprise
activities. The areas highlighted in yellow are those that typically have CIP needs.
18
The following tables outline the 2025-2030 CIP expenses by funding source for all planned years.
Construction Funds
The construction fund contains several revenue streams including levies, special assessments,
grants, franchise fees, and bonds, as well as several sub-funds.
Edina Consolidated Budget $212M
Governmental Funds
$128M
General Fund
$66M
Construction Fund
$22M
Debt Service Fund
$25M
Special Revenue Funds, including HRA
$15M
Enterprise Funds
$75M
Utility Fund
$42M
Liquor Fund
$16M
Park Enterprises
$17M
Internal Service Funds $9M
Risk Management
$3M
Equip. Operations
$2M
IT
$3M
Facilities
$1M
19
• Bridge Maintenance: Funds from the Public Works budget set aside to be used for bridge
maintenance and retaining wall repairs.
• Capital Improvement Plan Bonds: In general, bonds are a written promise to pay a specified
sum of money at a specified future date along with periodic interest paid at a specified percentage
(interest rate). Bonds are typically used for long-term debt. These Capital Improvements Bonds,
or general obligation (GO) bonds, are issued to pay for the construction of the Community
Health and Safety Center, including Fire Station 2 and Public Health.
• Capital Improvement Plan Levy: A plan developed to prioritize expenditures for significant
projects and match financing to pay the project costs. The City of Edina prepares a five-year CIP
every two years.
• Equipment Levy: The Equipment Levy is designed to provide funding for replacing all equipment
used for governmental purposes. This levy is projected to increase five percent each year to
cover the escalating costs of replacing the general fund equipment, including police cars,
snowplows and ambulances.
• Grants & Donations: Funding received from a variety of sources, including state and federal,
to be used for public infrastructure projects.
• Local Option Sales Tax (LOST): A local tax levied on the sale of goods and services to be
used for specific purposes by local government. This funding stream was approved by referendum
in 2022 to pay for improvements in the Fred Richards Master Plan and the Braemar Arena Master
Plan.
Cash Reserves
0.2%
Bridge Maintenance
0.3%
PEG Comcast Fees
0.3%
Special Park
Improvement Levy
1%
Grant/Donation
3%MSA
5%
Equipment
Replacement Levy
7%
CIP
Levy
7%
Special Street Levy
7%
Special
Assessment
8%
LOST
20%
CIP Bonds
42%
2025-2030 Construction Funds by Funding Source
20
• Municipal State Aid (MSA): A city designated street that becomes part of a broader state
transportation system. This designation allows the city to receive resources to assist with the
construction and maintenance of the street.
• PEG Comcast Fees: Fees collected for public, educational & government access channels, used
for communications and broadcasting technology.
• Special Assessments: The City places a financial lien against a property to recoup the cost of
certain improvements or services provided to a property, such as a street or utility improvement
or unpaid utility services.
• Special Park Improvement Levy: Established in 2023, this levy funds playground equipment
replacement and park and recreation facility improvements.
• Special Street Levy: Established in 2022, this levy is designed to offset some of the costs
associated with street reconstruction, which were previously entirely assessed to property
owners. This levy is expected to increase an average of five percent in each of the next 14 years.
Utility Enterprise Funds
Each utility enterprise fund collects revenue from
customers of the specific service. The revenue
can be spent on operational, capital and debt
service costs of providing the service. Rates are
studied and set to ensure revenue meets
operating and capital costs into the future.
In addition to the funds outlined above, a utility
fund collects revenue from all three funds to
finance capital infrastructure and equipment
replacement for each utility. The total of this
fund, for 2025-2030, is $2,735,000.
21
Pedestrian And Cyclist Safety (PACS) Fund
This special revenue fund was established in 2013 to account for funds received from gas and
electric franchise fees, which the City Council intends to use for pedestrian and cyclist
improvements (e.g. sidewalks, paths and trails) included in future street reconstruction projects.
Housing And Redevelopment Authority Fund
This fund accounts for the activities of the Housing and Redevelopment Authority. In tax
increment finance (TIF) districts, property owners pay ad valorem taxes at the full rate levied by
the units of local government within the taxing jurisdiction.
The HRA is an entity legally separate from the City. However, for financial reporting purposes,
the HRA is reported in a special revenue fund as if it were part of the City’s operations. This is
done because the members of the City Council serve as HRA commissioners, and its activity is
confined to the same geographic borders as the City of Edina.
Other Funds
These funds have over $21 million in projects in the 2025-2030 CIP, including $7M in the Golf
Course Fund and $6.9M in the CAS Fund.
22
• American Rescue Plan Act (ARPA) Fund: A fund set up to track state and local revenue
received as a part of the economic stimulus package established to speed up the country’s
recovery from the economic and health effects of the COVID-19 pandemic.
• Braemar Field Fund: This fund was created in 2013 to account for the revenues and
expenses for Braemar Field which was built in 2014.
• Conservation and Sustainability (CAS) Fund: This special revenue fund was established
in 2015 to account for funds received from gas and electric franchise fees beginning in 2016.
The City will use these funds to provide a dedicated funding source for new conservation and
sustainability functionality and programs.
• E911 (Police Special Revenue) Fund: This special revenue fund was established to account
for funds received for specific purposes within the Police Department, including E-911 and
forfeiture funds.
• Edinborough Park Fund: Edinborough Park’s finances were combined with Centennial
Lakes Park in one fund through 2011. A separate fund for each facility was created in budget
year 2012.
• General Fund: This is the City’s primary operating fund. It records most of the City’s
revenues and expenditures from core City operations like Administration, Police, Fire, Parks
and Recreation, etc. Any activities that are not specifically reported in a different fund can be
found in the General Fund. The General Fund is not used for debt service or capital projects.
• Golf Course Fund: This fund was established to account for the City’s golf business when
the 18-hole Braemar Golf Couse opened in 1964. Today, the City operates Braemar Golf
Course (18-hole championship course), a 9-hole executive course and driving range, an indoor
golf dome, and banquet room.
• Liquor Fund: This fund accounts for the City’s off-sale liquor business, which Edina first
started around 1948. Today, there are three municipally owned liquor stores in Edina. Profits
are generally transferred into other City funds.
• Public Safety Aid Fund: Fund created in 2023. The 2023 omnibus tax bill included $210
million in onetime public safety aid to cities across the state. This aid cannot be used for must
be used to provide public safety. The City received $2,344,327 on December 26,2023.
23
FUNDED PROJECTS
BY FUNDING SOURCE
24
Capital Improvement Plan - FUNDED
City of Edina, Minnesota
PROJECTS BY FUNDING SOURCE
2025 2030thru
Total20252026202720282029Source2030Project #
Braemar Field Fund
P&R25125Braemar Field Turf & Shell Replacement 2,300,0002,300,000
P&R25126Braemar Field Heater 200,000200,000
P&R25127Braemar Field Stormwater Design 75,00075,000
Braemar Field Fund Total 2,575,00075,000 200,000 2,300,000
Bridge Maintenance
ENG210616520 Belmore Lane Multi-Tiered
Retaining Wall
400,000400,000
ENG250186932 Valley View Road Multi-Tiered
Retaining Wall
360,000360,000
ENG25020Dewey Hill Road CP Rail Crossing 35,00035,000
Bridge Maintenance Total 795,000395,000 400,000
CAS Fund: Utility Franchise Fees
ENG21062Facility Efficiency Upgrades 3,000,000500,000 500,000 500,000 500,000 500,000 500,000
ENG25001DC Fast Charger 150,000150,000
ENG25079Electric Vehicle Infrastructure & Vehicle
Upgrades
600,000100,000 100,000 100,000 100,000 100,000 100,000
FAC25126Photovoltaic & EV Charger Installation 2,225,000575,000 50,000 500,000 1,100,000
FAC25127Fire Station #1 Energy Management
Study
500,000500,000
PWK25104Public Works Fleet - Bio Diesel Storage
Tanks
375,000375,000
CAS Fund: Utility Franchise Fees Total 6,850,0001,625,000 1,175,000 600,000 650,000 1,100,000 1,700,000
CIP Bonds
ENG23041TH Tight Diamond Interchange 4,000,0004,000,000
FAC25103City Wide Roof Replacement 12,500,000800,000 700,000 2,000,000 5,000,000 4,000,000
FAC2510550th & France Streetscapes
Improvements
7,400,000400,000 3,000,000 3,000,000 1,000,000
FAC25113Public Works Cold Storage Building
Replacement
2,300,0002,300,000
FAC25123Edinborough Park Pool HVAC Unit 350,000350,000
FIR21008Community Health & Safety Center 26,000,00026,000,000
FIR21009Fire Station #3 50,000,00050,000,000
P&R25117Aquatic Center Pool Paint, Equip & Signage Rplcmnt 558,100172,100 286,000 100,000
P&R25119Aquatic Center Filter Room 4,000,0004,000,000
P&R25157Edinborough Park Replace Camus Boiler 70,00070,000
P&R25163New Golf Course Clubhouse 27,000,00027,000,000
CIP Bonds Total 134,178,10035,792,100 6,286,000 55,000,000 6,100,000 31,000,000
25
Total20252026202720282029Source2030Project #
Construction Fund: Cable PEG
COM25100Replacement of Council Chambers
Cameras
40,00040,000
COM25101Cable TV Broadcast Server Replacement 70,00070,000
COM25102Video Production Studio Space 350,000350,000
COM25200Communications Equipment Replacement 70,00070,000
FAC25118Senior Center AV Equipment 55,00055,000
FAC25122City Hall Council Chambers Studio
Lighting
300,000300,000
Construction Fund: Cable PEG Total 885,000355,000 140,000 350,000 40,000
Construction Fund: CIP Levy
15-048Normandale Park Shelter Building
Replacement
1,040,00040,000 1,000,000
ENG21045City Wide ADA Facility Improvements
Level 3&4
1,336,0001,336,000
ENG21051Pamela Park Facility Maintenance 210,000210,000
ENG25021Grandview Parking Ramp ADA Access Route 200,000200,000
ENG25022Grandview Parking Ramp ADA Access
Route to Gus Yng
2,000,0002,000,000
FAC23109Arneson Acres Park Facility Improvements 700,000700,000
FAC25101City Wide Card Reader & Fire Alarm
Updates
100,000100,000
FAC25114Public Works Space Reconfiguration 850,00075,000 775,000
FAC25115Public Works Access Gates 300,000300,000
FAC25117Public Works BAS & Lighting Upgrades 825,000125,000 700,000
FAC25125City Hall HVAC Equipment Replacement 500,000500,000
FAC25128City Wide ADA Facility Improvements
Level 2
300,00050,000 100,000 50,000 100,000
FAC25129Fire Station #1 Living Quarters 500,000500,000
FAC25200Asset Preservation Funding 4,450,000800,000 700,000 700,000 700,000 750,000 800,000
ITS25100CLP Maintenance Fiber 30,00030,000
ITS25101Increase Fiber Capacity to SLP 60,00060,000
P&R21001General Park Asset Equipment
Replacement
50,00050,000
P&R21006Athletic Field Improvements 1,050,000350,000 350,000 350,000
P&R21046Normandale Park Playground Equipment 200,000200,000
P&R21047Heights Park Playground Equipment 175,000175,000
P&R25102Highlands Park Shelter Replacement 1,250,0001,250,000
P&R25103Yorktown Park Master Plan 790,00040,000 750,000
P&R25104Chowen Park Playground Improvement 350,000350,000
P&R25105Countryside Playground Replacement 315,000315,000
P&R25106Park Pathways and Parking Project
Improvements
525,00025,000 100,000 100,000 100,000 100,000 100,000
P&R25107Parks Accessibility Improvements 525,00025,000 100,000 100,000 100,000 100,000 100,000
P&R25108Utley Park Shelter Replacement 60,00060,000
P&R25110Arneson Park Shelter Replacement 75,00075,000
P&R25111Rosland Park Master Plan 100,000100,000
P&R25130Centennial Lakes Park Public Wi-Fi 40,00040,000
P&R25145Centennial Lakes Entrance Fountain
Repair
150,000150,000
P&R25147Centennial Lakes Improvements 800,000800,000
26
Total2026202720282029Source2030Project # 2025
PW22002Annual Deferred Retaining Wall
Replacements
750,00050,000 100,000 200,000 200,000 200,000
Construction Fund: CIP Levy Total 20,606,0001,000,000 2,205,000 2,995,000 3,990,000 5,116,000 5,300,000
Construction Fund: Equipment Levy
17-028Braemar Arena Zamboni 400,000200,000 200,000
17-039Centennial Lakes Vehicle Replacement 40,00040,000
ADM25200Administration Equipment Replacement 325,00030,000 85,000 210,000
COM25200Communications Equipment Replacement 40,00040,000
DEV25200Development Equipment Replacement 97,00097,000
ENG25200Engineering Equipment Replacement 631,331150,000 102,631 191,500 64,700 92,500 30,000
FAC25110Facility Asset Maintenance Software 1,044,000300,000 135,000 142,000 150,000 155,000 162,000
FIR25200Fire Equipment Replacement 6,300,292515,300 1,044,845 1,258,995 1,403,395 1,112,350 965,407
ITS25200IT Equipment Replacement 2,340,000440,000 95,000 633,000 500,000 294,000 378,000
P&R21001General Park Asset Equipment
Replacement
200,00050,000 50,000 50,000 50,000
P&R23120Park Maintenance Equip Replacement -
Vehicles
1,693,750329,300 411,700 234,250 223,500 191,000 304,000
POL25101Patrol Squad Car Addition 60,00060,000
POL25200Police Equipment Replacement 3,052,300330,000 358,000 867,800 588,000 690,000 218,500
PWK23200Public Works Equipment Replacement 4,214,107583,500 830,000 23,000 767,684 1,089,000 920,923
Construction Fund: Equipment Levy
Total
20,437,7802,678,100 3,102,176 3,810,545 3,847,279 3,873,850 3,125,830
Construction Fund: Grants/Donations
19-301Wooddale Ave Bridge Historic Rehab 1,500,0001,500,000
ENG23041TH Tight Diamond Interchange 700,000700,000
ENG25001DC Fast Charger 150,000150,000
ENG25026Rosland Park Pedestrian Bridge 6,000,0006,000,000
P&R25126Braemar Field Heater 200,000200,000
Construction Fund: Grants/Donations
Total
8,550,000850,000 7,700,000
Construction Fund: MSA
17-01169th Street Roundabout 450,000450,000
19-301Wooddale Ave Bridge Historic Rehab 400,000400,000
ENG23004Benton Avenue A Reconstruction 1,475,2971,475,297
ENG23041TH Tight Diamond Interchange 5,007,4045,007,404
ENG23101Hilary Lane Reconstruction 3,387,9783,387,978
ENG25002Parklawn Avenue A Reconstruction 524,385524,385
ENG25003W 77th Street D Reconstruction 987,078987,078
ENG25023Valley View Rd Fence Replace Sdale
Neighborhood
100,000100,000
ENG25028Traffic Signal at Halifax and 50th St 400,000400,000
ENG2502950th over Minnehaha Creek North
Retaining Wall 275,000275,000
ENG25030Benton Avenue Over CP Rail Beam Painting 250,000250,000
ENG25031Valley View Road Bridge over CP Rail
Beam Painting
250,000250,000
ENG25064West 76th Street A Reconstruction 968,276968,276
27
Total20252026202720282029Source2030Project #
Construction Fund: MSA Total 14,475,4185,007,404 400,000 500,000 3,662,978 2,929,739 1,975,297
Construction Fund: Reserves
DEV25107City Zoning Ordinance Update 250,000250,000
FAC25113Public Works Cold Storage Building
Replacement
300,000300,000
Construction Fund: Reserves Total 550,000550,000
Construction Fund: Special Assess
19-308Prospect Knolls C Reconstruction 1,091,2681,091,268
19-309Prospect Knolls D Reconstruction 332,125332,125
19-310Presidents B Reconstruction 1,129,5461,129,546
19-314Indian Trails A Reconstruction 671,785671,785
DEV25103France Avenue Branding/Lighting 2,000,0002,000,000
DEV25110HRA Grandview Maintenance District 545,000300,000 40,000 45,000 50,000 55,000 55,000
ENG23001Prospect Knolls A Reconstruction 1,632,1581,632,158
ENG23002Countryside E Reconstruction 782,328782,328
ENG23003Todd Park B Reconstruction 523,709523,709
ENG23004Benton Avenue A Reconstruction 108,997108,997
ENG23101Hilary Lane Reconstruction 302,453302,453
ENG25002Parklawn Avenue A Reconstruction 48,27048,270
ENG25003W 77th Street D Reconstruction 90,86190,861
ENG25005Chowen Park C Reconstruction 1,414,9911,414,991
ENG25006Chowen Park E Reconstruction 878,270878,270
ENG25009Minnehaha Woods B Reconstruction 618,632618,632
ENG25010Pamela Park B (Peacdale Avenue) Reconstruction 250,399250,399
ENG25011Pamela Park C (Halifax Avenue)
Reconstruction
191,481191,481
ENG25012Braemar Hills E (Washington Avenue)
Reconstruction
172,485172,485
ENG25013The Heights A Reconstruction 1,127,0301,127,030
ENG25014The Heights C Reconstruction 939,192939,192
ENG25064West 76th Street A Reconstruction 200,919200,919
ENG25074Parklawn (Parklawn Ct) Reconstruction 87,30187,301
ENG25075Rolling Green Reconstruction 2,505,0502,505,050
ENG25076Minnehaha Woods D Reconstruction 456,609456,609
ENG25077South Cornelia B Reconstruction 3,447,2973,447,297
ENG25078South Cornelia D Reconstruction 3,182,3943,182,394
ENG25100Presidents A Reconstruction 1,946,4511,946,451
Construction Fund: Special Assess Total 26,677,0015,375,997 3,182,852 6,669,132 3,169,423 1,912,171 6,367,426
E911
POL21005Dispatch E911 Call Handling System 550,000550,000
POL25200Police Equipment Replacement 1,053,000475,000 550,000 28,000
E911 Total 1,603,000475,000 550,000 578,000
Edinborough Fund
15-069Edinborough Park Track Air Conditioning 81,00081,000
28
Total20252026202720282029Source2030Project #
P&R21012Edinborough Park Fitness Equipment
Replacement
26,00026,000
P&R25148Edinborough Park Track Surface
Replacement
90,00090,000
P&R25149Edinborough Park Replace Exterior
Landscaping
75,00075,000
P&R25150Edinborough Park Loading Dock 50,00050,000
P&R25151Edinborough Park Concession
Replacement
24,00024,000
P&R25152Edinborough Park Amphitheater Upgrades 23,50023,500
P&R25153Edinborough Park SE Entry Concrete
Replacement
27,00027,000
P&R25154Edinborough Park Locker Replacement 31,00031,000
P&R25155Edinborough Park Truck Replacement 50,00050,000
P&R25156Edinborough Park Pool Filter
Replacement
70,00070,000
Edinborough Fund Total 547,500332,500 215,000
Federal ARPA
P&R23100CLP & EP Interior and Exterior Public
Furniture
40,00040,000
Federal ARPA Total 40,00040,000
General Fund
DEV25107City Zoning Ordinance Update 250,000250,000
DEV251092050 Comprehensive Plan 600,000250,000 250,000 100,000
General Fund Total 850,000500,000 250,000 100,000
Golf Course Fund
17-031Braemar Golf Clubhouse Lower Level 100,000100,000
FAC25120Golf Course Audio Visual Replacement 250,000250,000
FAC25124Golf Course Restroom Front 9 400,000400,000
P&R21028Toro 300 Gal Sprayer 85,00085,000
P&R21036Dome Electrical Update 25,00025,000
P&R21043Cart Path Addition Hole #6 & #11 150,000150,000
P&R25160Golf Dome Netting Repairs 250,000100,000 150,000
P&R25162Golf Course Tractor & Mower
Replacements 705,000100,000 295,000 160,000 50,000 100,000
P&R25164Golf Course Irrigation Upgrade 225,000225,000
P&R25166Club Car Utility Carts 78,00026,000 26,000 26,000
P&R25167Golf Maintenance Facility Lift Table 20,00020,000
P&R25168Golf Course Restroom Renovation 40,00040,000
P&R25169Golf Course Cold Storage Insulation 60,00060,000
P&R25170Update Well House #2 on Hole #13 75,00075,000
P&R25171Practice Green Enlargement / Academy 9
Pavilion 75,00075,000
P&R25172Driving Range Safety Netting 200,000200,000
P&R25175Golf Course Additional Native Areas 65,00065,000
P&R25176Golf Course New Nursery Green 100,000100,000
P&R25178Cart Path Addition Academy 9 150,000150,000
P&R25180Academy Training Facility 500,000500,000
P&R25182Golf Course Drainage Upgrade 40,00040,000
29
Total2026202720282029Source2030Project # 2025
P&R25183Academy 9 Re-Grass & Irrigation 40,00040,000
P&R25184Green Renovation/Relocation Hole #8 500,000500,000
P&R25185Golf Dome Building Expansion 3,000,0003,000,000
Golf Course Fund Total 7,133,0001,581,000 571,000 1,151,000 3,630,000 100,000 100,000
HRA Fund: 72nd and France TIF
DEV25102France Avenue Pedestrian/Bike Crossing 500,000500,000
HRA Fund: 72nd and France TIF Total 500,000500,000
HRA Fund: Centennial Lakes TIF
15-189Gateway Signs 150,00050,000 50,000 50,000
15-225HRA - Promenade Phase V 500,000500,000
17-01169th Street Roundabout 450,000450,000
17-018Valley View Rd Bicycle Facility
Improvements
350,000350,000
DEV25100HRA Cahill Business District Branding 300,000300,000
DEV25101HRA City Entrance Markers 100,000100,000
ENG23041TH Tight Diamond Interchange 250,000250,000
ENG25025France Avenue Crossing Gallagher &
72nd
16,000,000500,000 1,500,000 7,000,000 7,000,000
HRA Fund: Centennial Lakes TIF Total 18,100,0001,200,000 2,050,000 7,050,000 7,000,000 450,000 350,000
Liquor Fund
FAC23110Liquor Stores Facility Improvements 901,600297,600 324,000 280,000
Liquor Fund Total 901,600297,600 324,000 280,000
Local Option Sales Tax
P&R25100Fred Richards Park 16,255,0005,500,000 9,250,000 805,000 700,000
P&R25101Braemar Park & Arena 47,140,00011,850,000 17,320,000 15,820,000 2,150,000
P&R25181Golf Course Parking Lot Upgrade 1,000,0001,000,000
Local Option Sales Tax Total 64,395,00017,350,000 26,570,000 17,625,000 2,850,000
PACS Fund: Utility Franchise Fees
17-072Hwy 169 Frontage Rd/Braemar Blvd
Shared-Use Paths
658,420658,420
19-301Wooddale Ave Bridge Historic Rehab 200,000200,000
19-308Prospect Knolls C Reconstruction 319,200319,200
19-334Olinger Boulevard Sidewalk 883,500418,800 464,700
ENG21030McCauley Trail Shared-Use Path Phase 2 392,731392,731
ENG23004Benton Avenue A Reconstruction 109,800109,800
ENG23041TH Tight Diamond Interchange 400,000400,000
ENG23101Hilary Lane Reconstruction 190,400190,400
ENG25002Parklawn Avenue A Reconstruction 172,400172,400
ENG25003W 77th Street D Reconstruction 172,400172,400
ENG25005Chowen Park C Reconstruction 50,00050,000
ENG25006Chowen Park E Reconstruction 158,000158,000
ENG25013The Heights A Reconstruction 295,200295,200
ENG25014The Heights C Reconstruction 295,200295,200
30
Total20252026202720282029Source2030Project #
ENG25050Sidewalk Inspection Program 300,00050,000 50,000 50,000 50,000 50,000 50,000
ENG25051Drive 25 Improvements 120,00020,000 20,000 20,000 20,000 20,000 20,000
ENG25052Normandale Road/Viking Drive Bike
Lanes
28,20028,200
ENG25053Pedestrian and Bicycle Master Plan
Update
100,000100,000
ENG25054Wooddale Avenue Bike Lanes 111,10091,600 19,500
ENG25055McCauley Trail Shared-Use Path 503,000503,000
ENG2505669th Street Bike Lanes 24,40024,400
ENG25057West Shore Drive Bike Boulevard 35,10035,100
ENG25058W 44th St Bike Lanes 18,10018,100
ENG25059Metro Boulevard Bike Lanes 60,90060,900
ENG25060Minnehaha Creek Pedestrian Bridge 1,200,0001,200,000
ENG25061Edina Industrial Boulevard Sidewalk 297,500297,500
ENG25062W 66th Street Sidewalk 476,000476,000
ENG25063Valley View Road Bike Lane Design 50,00050,000
ENG25064West 76th Street A Reconstruction 41,15041,150
ENG25065France Avenue Shared-Use Paths 1,541,300762,900 778,400
ENG25066Lincoln Drive/7th Street/Malibu Drive Sidewalks 419,600419,600
ENG25067West 60th Street Sidewalk 710,500710,500
ENG25068West 77th Street Sidewalk 483,100483,100
ENG25069Benton Avenue Shared-Use Path 730,400730,400
ENG25070West 64th Street Shared-Use Path 422,654422,654
ENG25071Valley View Road Sidewalk 109,100109,100
ENG25072Amundson Avenue Sidewalk 156,100156,100
ENG25073Interlachen Boulevard Shared-Use Path 381,600381,600
ENG25074Parklawn (Parklawn Ct) Reconstruction 27,90027,900
ENG25076Minnehaha Woods D Reconstruction 288,600288,600
ENG25077South Cornelia B Reconstruction 444,150444,150
ENG25100Presidents A Reconstruction 233,000233,000
PACS Fund: Utility Franchise Fees Total 13,610,7051,594,100 2,404,831 3,220,650 2,085,700 1,537,550 2,767,874
Public Safety Aid
FAC25121PW Building Emergency Services Radio
Repeater
250,000250,000
FIR25200Fire Equipment Replacement 375,200375,200
POL25101Patrol Squad Car Addition 70,00070,000
POL25103Rifle-Rated Ballistic Shields 40,00040,000
POL25107PS Radio Bi-Directional Amplifier (BDA)
Rplcmt
25,00025,000
POL25200Police Equipment Replacement 110,000110,000
Public Safety Aid Total 870,200845,200 25,000
Special Park Improvement Levy
17-143Creek Valley Irrigation 50,00050,000
19-763Tingdale Park Playground Replacement 155,000155,000
P&R21003Outdoor Athletic Field Lighting 900,000180,000 180,000 180,000 180,000 180,000
P&R21039Strachauer Park Master Plan Phase II 1,100,0001,100,000
P&R21048Sherwood Park Playground Equipment 150,000150,000
P&R21049Kojetin Park Playground Equipment 165,000165,000
31
Total2026202720282029Source2030Project # 2025
P&R23212York Park Playground Replacement 175,000175,000
P&R25113Fox Meadow Shelter Replacement 55,00055,000
P&R25114Alden Park Playground Replacement 185,000185,000
P&R25118McGuire Park Playground Equipment
Replacement.
250,000250,000
P&R25123Off Leash Dog Park Investments 10,00010,000
P&R25134Pamela Park Playground Equipment
Replacement
300,000300,000
Special Park Improvement Levy Total 3,495,000405,000 305,000 1,940,000 485,000 180,000 180,000
Special Street Levy
19-308Prospect Knolls C Reconstruction 983,386983,386
19-309Prospect Knolls D Reconstruction 299,292299,292
19-310Presidents B Reconstruction 822,660822,660
19-314Indian Trails A Reconstruction 747,279747,279
ENG23001Prospect Knolls A Reconstruction 1,470,8041,470,804
ENG23002Countryside E Reconstruction 870,245870,245
ENG23003Todd Park B Reconstruction 720,847720,847
ENG23004Benton Avenue A Reconstruction 150,027150,027
ENG23101Hilary Lane Reconstruction 336,442336,442
ENG25002Parklawn Avenue A Reconstruction 82,82782,827
ENG25003W 77th Street D Reconstruction 155,909155,909
ENG25005Chowen Park C Reconstruction 1,947,6301,947,630
ENG25006Chowen Park E Reconstruction 1,208,8741,208,874
ENG25009Minnehaha Woods B Reconstruction 1,061,5191,061,519
ENG25010Pamela Park B (Peacdale Avenue)
Reconstruction
429,663429,663
ENG25011Pamela Park C (Halifax Avenue)
Reconstruction 328,566328,566
ENG25012Braemar Hills E (Washington Avenue) Reconstruction 374,045374,045
ENG25013The Heights A Reconstruction 2,444,0412,444,041
ENG25014The Heights C Reconstruction 2,036,7012,036,701
ENG25074Parklawn (Parklawn Ct) Reconstruction 78,67178,671
ENG25075Rolling Green Reconstruction 2,786,5642,786,564
ENG25076Minnehaha Woods D Reconstruction 783,502783,502
ENG25100Presidents A Reconstruction 1,417,6191,417,619
Special Street Levy Total 21,537,1132,240,279 2,832,153 3,533,843 4,213,793 2,841,986 5,875,059
Utility Fund
PWK23201Utilities Equipment Replacement 2,735,000355,000 200,000 677,000 297,000 642,000 564,000
Utility Fund Total 2,735,000355,000 200,000 677,000 297,000 642,000 564,000
Utility Fund: Sewer
15-173Asset Management Software and
Equipment
40,00010,000 10,000 10,000 10,000
19-308Prospect Knolls C Reconstruction 573,550573,550
19-309Prospect Knolls D Reconstruction 174,559174,559
19-310Presidents B Reconstruction 998,443998,443
19-314Indian Trails A Reconstruction 392,308392,308
19-335Sanitary Trunk Capacity Expansion York 3,800,0003,800,000
32
Total2026202720282029Source2030Project # 2025
Segs 2-3
19-336Sanitary Trunk Capacity Exp York Seg 4 & Fairview 4,700,0004,700,000
19-340Sanitary Targeted Inflow Reduction
Project
130,000130,000
ENG2105572nd Street Sewer Line Upsize 1,600,0001,600,000
ENG23001Prospect Knolls A Reconstruction 686,265686,265
ENG23002Countryside E Reconstruction 391,999391,999
ENG23003Todd Park B Reconstruction 299,187299,187
ENG23004Benton Avenue A Reconstruction 186,198186,198
ENG23009Hilary Lane Sanitary Sewer Lining 300,000300,000
ENG23033Sanitary Trunk Capacity Exp York Avenue Hazelton 8,900,000200,000 2,000,000 500,000 5,000,000 1,200,000
ENG23034Sanitary Trunk Capacity Exp York
Avenue 69th St W
1,400,0001,400,000
ENG23041TH Tight Diamond Interchange 300,000300,000
ENG23101Hilary Lane Reconstruction 303,883303,883
ENG25002Parklawn Avenue A Reconstruction 103,924103,924
ENG25003W 77th Street D Reconstruction 195,622195,622
ENG25005Chowen Park C Reconstruction 929,616929,616
ENG25006Chowen Park E Reconstruction 577,003577,003
ENG25009Minnehaha Woods B Reconstruction 464,487464,487
ENG25010Pamela Park B (Peacdale Avenue)
Reconstruction
188,007188,007
ENG25011Pamela Park C (Halifax Avenue)
Reconstruction
143,770143,770
ENG25012Braemar Hills E (Washington Avenue)
Reconstruction 34,33934,339
ENG25013The Heights A Reconstruction 858,472858,472
ENG25014The Heights C Reconstruction 715,394715,394
ENG25033Nine Mile Village Sanitary Sewer Lining 175,000175,000
ENG25034Olinger Road Sanitary Sewer
Replacement
100,000100,000
ENG25064West 76th Street A Reconstruction 165,248165,248
ENG25074Parklawn (Parklawn Ct) Reconstruction 39,89939,899
ENG25075Rolling Green Reconstruction 281,326281,326
ENG25076Minnehaha Woods D Reconstruction 342,836342,836
ENG25077South Cornelia B Reconstruction 1,071,9041,071,904
ENG25078South Cornelia D Reconstruction 957,073957,073
ENG25100Presidents A Reconstruction 1,720,5301,720,530
PWK23010Nine Mile Village Sewer Lining 175,000175,000
PWK23011Olinger Road Dip Replacement: 130 LF +
Road Repair
80,00080,000
PWK25105Lift Station Pump and VFD Renewal 180,00030,000 30,000 30,000 30,000 30,000 30,000
Utility Fund: Sewer Total 34,675,8427,708,973 3,694,273 8,585,538 7,149,689 4,233,894 3,303,475
Utility Fund: Storm
15-173Asset Management Software and
Equipment
60,00015,000 15,000 15,000 15,000
17-01169th Street Roundabout 100,000100,000
19-301Wooddale Ave Bridge Historic Rehab 400,000400,000
19-308Prospect Knolls C Reconstruction 1,386,9361,386,936
19-309Prospect Knolls D Reconstruction 422,111422,111
33
Total2026202720282029Source2030Project # 2025
19-310Presidents B Reconstruction 1,305,0781,305,078
19-314Indian Trails A Reconstruction 1,038,4751,038,475
19-346CWRMP Model Update 200,000200,000
ENG23001Prospect Knolls A Reconstruction 1,583,4181,583,418
ENG23002Countryside E Reconstruction 850,851850,851
ENG23003Todd Park B Reconstruction 826,220826,220
ENG23004Benton Avenue A Reconstruction 434,318434,318
ENG23010Concord Flood Infrastrucure Project #2
area
10,650,000200,000 950,000 9,500,000
ENG23011Arden & 50th Flood Infrastructure Project
#3 Area
650,000200,000 450,000
ENG23012Lake Cornelia and Normandale Park
Flood Infras 16,000,00016,000,000
ENG23013France Avenue Crossing (Minnehaha Creek)800,000200,000 600,000
ENG23014Adaptive Level Management Project Ph 2
Minnehaha
2,700,000200,000 2,500,000
ENG23015Adaptive Level Management Project Nine
Mile Creek
2,500,0002,500,000
ENG23016Minor Pipe and Grading Project (Citywide)2,500,0002,500,000
ENG23017Chowen and 60th Flood Project 1,100,0001,100,000
ENG23041TH Tight Diamond Interchange 300,000300,000
ENG23101Hilary Lane Reconstruction 1,009,2451,009,245
ENG25002Parklawn Avenue A Reconstruction 226,673226,673
ENG25003W 77th Street D Reconstruction 426,678426,678
ENG25005Chowen Park C Reconstruction 2,460,7762,460,776
ENG25006Chowen Park E Reconstruction 1,527,3781,527,378
ENG25009Minnehaha Woods B Reconstruction 1,282,7071,282,707
ENG25010Pamela Park B (Peacdale Avenue)
Reconstruction
454,631454,631
ENG25011Pamela Park C (Halifax Avenue)
Reconstruction
347,659347,659
ENG25012Braemar Hills E (Washington Avenue)
Reconstruction
332,148332,148
ENG25013The Heights A Reconstruction 2,370,7172,370,717
ENG25014The Heights C Reconstruction 1,729,9361,729,936
ENG2502750th St Concrete Curb and Gutter
Replacement 55,00055,000
ENG25036CWS 1 - Lake & Pond Sediment Phosphorus Sequest 550,00050,000 100,000 100,000 100,000 100,000 100,000
ENG25037CWS 2 - Targeted Intensive Street
Sweeping
100,00010,000 20,000 70,000
ENG25038CWS 3 - Assurance, Monitoring,
Lakegrades
215,00040,000 35,000 35,000 35,000 35,000 35,000
ENG25039CWS 4 - Rough Fish Management 190,00030,000 40,000 40,000 40,000 40,000
ENG25040CWS 5 - New Clean Water Infrastructure 150,000150,000
ENG25064West 76th Street A Reconstruction 385,207385,207
ENG25074Parklawn (Parklawn Ct) Reconstruction 110,184110,184
ENG25075Rolling Green Reconstruction 4,009,2434,009,243
ENG25076Minnehaha Woods D Reconstruction 946,760946,760
ENG25077South Cornelia B Reconstruction 2,049,8752,049,875
ENG25078South Cornelia D Reconstruction 1,830,2771,830,277
ENG25100Presidents A Reconstruction 2,248,9282,248,928
Utility Fund: Storm Total 70,816,4296,669,006 6,982,649 11,212,593 16,563,619 20,565,315 8,823,247
34
Total2026202720282029Source2030Project # 2025
Utility Fund: Water
15-162New Water Treatment Plant 5 - Southdale 18,000,00018,000,000
15-173Asset Management Software and
Equipment
40,00010,000 10,000 10,000 10,000
19-308Prospect Knolls C Reconstruction 854,577854,577
19-309Prospect Knolls D Reconstruction 260,088260,088
19-310Presidents B Reconstruction 1,413,4941,413,494
19-314Indian Trails A Reconstruction 584,530584,530
19-351Water Main Condition Assessment 955,000150,000 160,000 160,000 165,000 160,000 160,000
19-913Well #7 Rehabilitation 300,000180,000 120,000
19-915Well #11 Rehabilitation and Facility
Improvements
240,000120,000 120,000
19-918Well #20 Rehabilitation 180,000180,000
ENG21058Water Supply Grandview Area PH 3 2,500,0002,500,000
ENG21059Water Supply 50th and France 2,000,0002,000,000
ENG21060Water Supply Pentagon Park 1,000,0001,000,000
ENG23001Prospect Knolls A Reconstruction 1,278,1481,278,148
ENG23002Countryside E Reconstruction 584,093584,093
ENG23003Todd Park B Reconstruction 783,583783,583
ENG23004Benton Avenue A Reconstruction 369,875369,875
ENG23035Watermain Rehabilitation (Citywide)1,400,0001,400,000
ENG23036Grandview Area Watermain
Improvements PH 2 240,000240,000
ENG23041TH Tight Diamond Interchange 300,000300,000
ENG23101Hilary Lane Reconstruction 786,652786,652
ENG25002Parklawn Avenue A Reconstruction 201,768201,768
ENG25003W 77th Street D Reconstruction 379,800379,800
ENG25005Chowen Park C Reconstruction 2,434,7052,434,705
ENG25006Chowen Park E Reconstruction 1,511,1961,511,196
ENG25009Minnehaha Woods B Reconstruction 692,075692,075
ENG25010Pamela Park B (Peacdale Avenue)
Reconstruction
492,398492,398
ENG25011Pamela Park C (Halifax Avenue)
Reconstruction
376,540376,540
ENG25012Braemar Hills E (Washington Avenue)
Reconstruction
51,16451,164
ENG25013The Heights A Reconstruction 2,248,3762,248,376
ENG25014The Heights C Reconstruction 1,873,6471,873,647
ENG25043Chapel Drive Watermain Rehabilitation 300,000300,000
ENG25044Maloney Ave Watermain Rehabilitation 1,000,0001,000,000
ENG25045Watermain Replacement under NMC at
5901 Lincoln Dr
50,00050,000
ENG25046Watermain Replcmnt LB Tr/Shannon
Dr/Coventry Way
225,000225,000
ENG25047Heights Neighborhood Watermain
Rehabilitation 6,250,0006,250,000
ENG25064West 76th Street A Reconstruction 247,724247,724
ENG25074Parklawn (Parklawn Ct) Reconstruction 59,44959,449
ENG25075Rolling Green Reconstruction 1,676,6781,676,678
ENG25076Minnehaha Woods D Reconstruction 897,902897,902
ENG25077South Cornelia B Reconstruction 1,530,6691,530,669
ENG25078South Cornelia D Reconstruction 2,343,5492,343,549
ENG25100Presidents A Reconstruction 2,435,7532,435,753
35
Total2026202720282029Source2030Project # 2025
FAC25109Fire Station #2 York Ave. Building Demo 500,000500,000
PW23002Well #15 Rehabilitation and Facility
Improvements
140,000140,000
PW23004Well #10 Rehabilitation and Facility Improvements 120,000120,000
PW23005Well #12 Rehabilitation and Facility Improvements 180,000180,000
PW23006Well #13 Rehabilitation and Facility
Improvements
180,000180,000
PW23007Well #2 Rehabilitation and Facility
Improvements
170,000170,000
PW23008Well #6 Rehabilitation and Facility
Improvements
180,000180,000
PWK25101Water Meter Radio Receivers 4,970,0001,300,000 880,000 900,000 930,000 960,000
PWK25102Filter Media Replacement 450,000450,000
PWK25103Fiber Installation, Van Valkenburg Tower 160,000160,000
Utility Fund: Water Total 68,398,4337,319,247 5,407,262 5,041,877 27,891,136 11,728,207 11,010,704
GRAND TOTAL 546,788,121102,141,506 77,347,196 131,042,178 90,503,617 63,310,712 82,442,912
36
FUNDED PROJECTS IN DETAIL
SORTED BY DEPARTMENT
37
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Sharon Allison
2025 2030thru Department Administration
Description
Replacement of equipment according to the equipment replacement schedule. This includes essential equipment such as furniture and election
equiment, among other items.
2025:
Furniture - Voter Registration
2026:
Furniture - Administration
2027:
Furniture - Planning & Assessing
Furniture - General
Project #ADM23200
Justification
As outlined in Vision Edina, it is the mission of the City Council to provide effective and valued public services and maintain a sound public
infrastructure. Regular replacement of furniture and election equipment allows the city to maintain a high level of quality service provided to the
residents of the City of Edina.
Useful LifeProject Name Administration Equipment Replacement Category Equipment and Vehicles
Type Replace or repair
Total Project Cost:$325,000
Total2025 2026 2027 2028 2029Expenditures 2030
325,00030,000 85,000 210,000Vehicles and Equipment
30,000 85,000 210,000 325,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
325,00030,000 85,000 210,000Construction Fund: Equipment
Levy
30,000 85,000 210,000 325,000Total
38
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Bill Neuendorf
2025 2030thru Department Comm. Dev. and HRA
Description
The Edina Promenade, a dedicated route for pedestrians and bicyclists on public right-of-way currently terminates at 70th Street. It is intended to
be extended incrementally when individual properties are redeveloped. Ultimately, the North Extension will create a non-motorized route from
70th Street to Highway 62. It may be necessary to acquire public easements on some private properties to complete this project.
ENVIRONMENTAL CONSIDERATIONS:
The purpose of the Promenade and the North Extension is to provide a safe and convenient route for bicyclists and pedestrians. The route can be
used for both recreational and commuting purposes as a healthier and cleaner alternative than driving.
Project #15-225
Justification
The Edina Promenade pathway originated in the 2007 Promenade Urban Design Plan. The North Extension supports Objective #2 (Transportation
Options) in Vision Edina.
This project will provide new alternatives to better connect the residential neighborhoods and employment center located north of 66th Street and
north of Highway 62 to commercial businesses in the Greater Southdale area.
Useful LifeProject Name HRA - Promenade Phase V Category Land
Type Expand or enhance
Total Project Cost:$500,000
Total2025 2026 2027 2028 2029Expenditures 2030
500,000500,000Construction
500,000 500,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
500,000500,000HRA Fund: Centennial Lakes
TIF
500,000 500,000Total
39
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Cary Teague
2025 2030thru Department Comm. Dev. and HRA
Description
Replacement of equipment according to the equipment replacement schedule. This includes essential departmental vehicles and other miscellanous
equipment.
2030:
2010 Focus
2020 Chevrolet Bolt
2018 Toyota Prius II
Project #DEV23100
Justification
As outlined in Vision Edina, it is the mission of the City Council to provide effective and valued public services and maintain a sound public
infrastructure. Regular replacement of department vehicles and other equipment allows the city to maintain a high level of quality service provided
to the residents of the City of Edina. Timely replacement of equipment also ensures equipment reliability while keeping maintenance costs low.
Useful LifeProject Name Development Equipment Replacement Category Equipment and Vehicles
Type Replace or repair
Total Project Cost:$97,000
Total2025 2026 2027 2028 2029Expenditures 2030
97,000Vehicles and Equipment 97,000
97,000Total97,000
Total2025 2026 2027 2028 2029Funding Sources 2030
97,000Construction Fund: Equipment
Levy 97,000
97,000Total97,000
40
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Bill Neuendorf
2025 2030thru Department Comm. Dev. and HRA
Description
Develop a brand for the district. Borders of the district would be 70th on the north, Cahill Road on the west, the City border on the south and
Highway 100 on the east.
Project #DEV25100
Justification
Asset Functionality
Community Engagement: Would involve businesses within the district.
Useful LifeProject Name HRA Cahill Business District Branding Category Land
Type New
Total Project Cost:$300,000
Total2025 2026 2027 2028 2029Expenditures 2030
300,000300,000Construction
300,000 300,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
300,000300,000HRA Fund: Centennial Lakes
TIF
300,000 300,000Total
41
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Bill Neuendorf
2025 2030thru Department Comm. Dev. and HRA
Description
Install entrance markers at key entrances to the City.
Project #DEV25101
Justification
Asset Functionality
Useful LifeProject Name HRA City Entrance Markers Category Land
Type Expand or enhance
Total Project Cost:$100,000
Total2025 2026 2027 2028 2029Expenditures 2030
100,000100,000Construction
100,000 100,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
100,000100,000HRA Fund: Centennial Lakes
TIF
100,000 100,000Total
42
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Bill Neuendorf
2025 2030thru Department Comm. Dev. and HRA
Description
Provide a safe pedestrian crossing either under or above France Avenue in the 7200 Block of France.
Project #DEV25102
Justification
Health, Safety & Regulatory Compliance
Stewardship, Race & Equity: Provides a safe crossing across France Avenue.
Community Engagement: Better together
Useful LifeProject Name France Avenue Pedestrian/Bike Crossing Category Infrastructure
Type New
Total Project Cost:$500,000
Total2025 2026 2027 2028 2029Expenditures 2030
500,000500,000Construction
500,000 500,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
500,000500,000HRA Fund: 72nd and France
TIF
500,000 500,000Total
43
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Bill Neuendorf
2025 2030thru Department Comm. Dev. and HRA
Description
Work with the business to develop branding along France Avenue.
Project #DEV25103
Justification
Justification - Asset Functionality
Community Engagement - Work with businesses and property owners that will fund the project.
Health in All Policies - Create a more walkable France Avenue.
Stewardship - Creates a more walkable area in the future. Contributes to the economic viability in the area.
Budget Impact/Other
Useful LifeProject Name France Avenue Branding/Lighting Category Infrastructure
Type New
Total Project Cost:$2,000,000
Total2025 2026 2027 2028 2029Expenditures 2030
2,000,0002,000,000Construction
2,000,000 2,000,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
2,000,0002,000,000Construction Fund: Special
Assess
2,000,000 2,000,000Total
44
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Cary Teague
2025 2030thru Department Comm. Dev. and HRA
Description
Update the City' Zoning Ordinance based on recommendations from the Zoning Audit, Planning Commission and City Council.
Project #DEV25107
Justification
Health, Safety & Regulatory Compliance
Sustainability - Provides clarity of zoning regulations for residents, staff, land owners and developers. Zoning regulations influence the built
environment.
Community Engagement - Community Engagement would be important for this project. Public processes for land use regulation is housed in the
zoning ordinance.
Race and Equity - Review ordinance through the lens of race and equity.
Budget Impact/Other
Useful LifeProject Name City Zoning Ordinance Update Category Land
Type New
Total Project Cost:$500,000
Total20252026202720282029Expenditures2030
500,000250,000 250,000Planning and Design
250,000 250,000 500,000Total
Total20252026202720282029Funding Sources 2030
250,000250,000General Fund
250,000250,000Construction Fund: Reserves
250,000 250,000 500,000Total
45
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Addison Lewis
2025 2030thru Department Comm. Dev. and HRA
Description
Comprehensive Plan Update. Required every 10 years.
Project #DEV25109
Justification
"Health, Safety & Regulatory Compliance
Sustainability - Sets a guide for the City for the next 10 years
Community Engagement - Yes. Community Engagement is extensive with Comprehensive Plan updates. Including resident and business owner
working group(s), numerous public meetings and ending with two public hearings. Entire process takes 2-3 years and every Edina Commission is
involved.
Health in all policies - Provides a guide for the built environment in Edina for the next 20 years.
Race & Equity - Public process is to be determined. Staff, consultants and working group will seek inclusion from all of Edina. Including targeting
of groups and areas in City that have no previously participated in comprehensive planning.
Stewardship - The Comprehensive Plan should assist in future decision making for the next 10 years. This project includes all of the City's
commissions."
Useful LifeProject Name 2050 Comprehensive Plan Category Land
Type New
Total Project Cost:$600,000
Total2025 2026 2027 2028 2029Expenditures 2030
600,000250,000 250,000 100,000Planning and Design
250,000 250,000 100,000 600,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
600,000250,000 250,000 100,000General Fund
250,000 250,000 100,000 600,000Total
46
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Bill Neuendorf
2025 2030thru Department Comm. Dev. and HRA
Description
Improvements and ongoing maintenance of landscaping areas in the Grandview District. Cost assessed to property owners.
Project #DEV25110
Justification
Asset Functionality
Budget Impact/Other
Useful LifeProject Name HRA Grandview Maintenance District Category Buildings
Type Expand or enhance
Total Project Cost:$545,000
Total2025 2026 2027 2028 2029Expenditures 2030
545,000300,000 40,000 45,000 50,000 55,000Construction 55,000
300,000 40,000 45,000 50,000 55,000 545,000Total55,000
Total2025 2026 2027 2028 2029Funding Sources 2030
545,000300,000 40,000 45,000 50,000 55,000Construction Fund: Special
Assess
55,000
300,000 40,000 45,000 50,000 55,000 545,000Total55,000
47
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Scott Denfeld
2025 2030thru Department Communications
Description
Replacement of equipment according to the equipment replacement schedule. This includes essential equipment such as cameras, broadcasting
equipment, and graphics systems, among other items.
2026:
Tightrope Server
2028:
Council Chamber Cameras - Sony HD PTZ
Replacement Chambers Cameras - 2 Sony HD PTZ
Project #COM23100
Justification
As outlined in Vision Edina, it is the mission of the City Council to provide effective and valued public services and maintain a sound public
infrastructure. Regular replacement of communications technology, broadcasting equipment and other miscellaneous equipment allows the city to
maintain a high level of quality service provided to the residents of the City of Edina. Timely replacement of equipment also ensures equipment
reliability while keeping maintenance costs low.
Useful LifeProject Name Communications Equipment Replacement Category Equipment and Vehicles
Type Replace or repair
Total Project Cost:$110,000
Total2025 2026 2027 2028 2029Expenditures 2030
110,00070,000 40,000Vehicles and Equipment
70,000 40,000 110,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
40,00040,000Construction Fund: Equipment
Levy
70,00070,000Construction Fund: Cable PEG
70,000 40,000 110,000Total
48
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Scott Denfeld
2025 2030thru Department Communications
Description
Replacement of robotic cameras in the Council Chambers due to end of useful life.
Project #COM25100
Justification
Asset Functionality
Sustainability - This replacement equipment is not anticipated to increase energy and resource usage over what we currently use.
Community Engagement - This equipment is used for a lot of community engagement-related projects. The videos produced with the equipment
support community engagement and help to inform people in and around Edina.
Health in all policies - This equipment will not have a negative impact on health-related items, and could certainly be used to help promote health
and wellness initiatives in the future.
Race & Equity - This equipment is used to promote and support race & equity initiatives of the City.
Stewardship - This replacement equipment will help the City continue to provide useful, high-quality video content that benefits all who live and
work in Edina.
Useful LifeProject Name Replacement of Council Chambers Cameras Category Equipment and Vehicles
Type Replace or repair
Total Project Cost:$40,000
Total2025 2026 2027 2028 2029Expenditures 2030
40,00040,000Vehicles and Equipment
40,000 40,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
40,00040,000Construction Fund: Cable PEG
40,000 40,000Total
49
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Scott Denfeld
2025 2030thru Department Communications
Description
Replacement of Tightrope Cablecast server. This server send the Edina TV video content to Comcast cable.
Project #COM25101
Justification
Asset Functionality
Sustainability - It is not anticipated that this replacement server will negatively impact energy efficiency or usage.
Community Engagement - This equipment is used to produce and deliver community engagement-related content.
Health in all policies - This equipment could be used used to produce and deliver health-related content.
Race & Equity - This equipment is used to produce and deliver race & equity-related content.
Stewardship - This equipment benefits all who live and work in Edina by delivering valuable information via the Edina TV cable channel.
Useful LifeProject Name Cable TV Broadcast Server Replacement Category Equipment and Vehicles
Type Replace or repair
Total Project Cost:$70,000
Total2025 2026 2027 2028 2029Expenditures 2030
70,00070,000Vehicles and Equipment
70,000 70,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
70,00070,000Construction Fund: Cable PEG
70,000 70,000Total
50
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Scott Denfeld
2025 2030thru Department Communications
Description
Design and construction of a new video production studio space within a City facility.
Project #COM25102
Justification
Expansion and/or Level of Service
Sustainable - This project would be designed and built in a way that promotes energy efficiency where possible.
Community Engagement - This project would enhance community engagement efforts by providing a high-quality space to produce video content
that will engage and educate community members about a variety of topics.
Health in alll policies - This project could be used to create video content that promotes health-related initiatives.
Race & Equity - This project could be used to create video content that promotes race & equity-related initiatives.
Stewardship - This project would significantly streamline and improve the City's video production work, allowing for more content to be created,
which would benefit those who live and work in Edina.
Useful LifeProject Name Video Production Studio Space Category Equipment and Vehicles
Type New
Total Project Cost:$350,000
Total2025 2026 2027 2028 2029Expenditures 2030
350,000350,000Vehicles and Equipment
350,000 350,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
350,000350,000Construction Fund: Cable PEG
350,000 350,000Total
51
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Ross Bintner
2025 2030thru Department Engineering
Description
This project includes the design of Southdale Water Plant. This plant will filter water from wells 5, 18, and potentially future well 21.
ENVIRONMENTAL CONSIDERATIONS:
Consideration is made in the design for overall operating costs from energy and chemicals. Stormwater features will provide aesthetics, treatment
and recharge.
Project #15-162
Justification
The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier public
facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly high
quality of life enjoyed by our residents and businesses.”
The City’s 2020-2021 Budget Work Plan Goals 1 and 3 are; Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable
Development, respectively. Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient
operations that lessen the City’s carbon footprint and reduce energy costs. Connected and sustainable development includes an efficient multi-
modal transportation system that balances improving personal mobility options with reducing the community’s carbon footprint all the while
reducing negative impacts on human health and safety.
This project is the implementation of the mission statement and the budget work plan goals. The recommended schedule is based on need. It may
also be coordinated with other city, county, and state projects in the area.
Useful LifeProject Name New Water Treatment Plant 5 - Southdale Category Infrastructure
Type Horizon
Total Project Cost:$18,000,000
Total2025 2026 2027 2028 2029Expenditures 2030
18,000,00018,000,000Construction
18,000,000 18,000,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
18,000,00018,000,000Utility Fund: Water
18,000,000 18,000,000Total
52
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Ross Bintner
2025 2030thru Department Engineering
Description
This project continues to update and improve our current asset management system software and associated equipment to be more interactive with
the public and mobile with City Staff.
The current system contains map and condition assessment information on all infrastructure assets such as water, sanitary, storm, transportation,
traffic and electrical systems. Software systems connect the EdinaToGo citizen request application with Cityworks asset management software and
ESRI geographical information system software. Public works crews use tablets to assess and record infrastructure condition, create and fulfill
service requests and work orders.
ENVIRONMENTAL CONSIDERATIONS:
Efficiency in management and operations allows more work with less trips and effort.
Project #15-173
Justification
Expansion and/or Level of Service
The need is emphasized in the 2018 Edina Comprehensive Plan to "evaluate and employ technological advancements to provide city services" and
to "provide a level of City services that sets Edina apart from other communities."
Useful LifeProject Name Asset Management Software and Equipment Category Technology
Type Replace or repair
Total Project Cost:$140,000
Total2025 2026 2027 2028 2029Expenditures 2030
140,00035,000 35,000 35,000 35,000Software
35,000 35,000 35,000 35,000 140,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
60,00015,000 15,000 15,000 15,000Utility Fund: Storm
40,00010,000 10,000 10,000 10,000Utility Fund: Water
40,00010,000 10,000 10,000 10,000Utility Fund: Sewer
35,000 35,000 35,000 35,000 140,000Total
53
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Bill Neuendorf
2025 2030thru Department Engineering
Description
A gateway sign is often the first impression people have of a city, development, business park or other public place. A well planned and executed
gateway sign is important because it gives an immediate sense of a brand and denotes a sense of pride and caring, and makes visitors feel welcome.
One entrance sign was installed at the 66th and York Intersection. This project would develop a plan on locations to continue installing gateway
signs.
The City’s Branding Committee and the Communications Department recommend the placement of "Welcome to Edina" gateway signs.
ENVIRONMENTAL CONSIDERATIONS:
Gateway signs need to be lighted to continue communicating the brand 24-hours a day. Solar lights could be considered to reduce electrical load.
Project #15-189
Justification
Expansion and/or Level of Service
One of the City Leadership Priorities in the 2012 Work Plan was "Improve Communications Tools." One of the objectives toward meeting that
goal is to implement branding standards.
One of the City Leadership Priorities in the 2014 Work Plan is "Development and renewal of commercial and residential areas is essential to the on-
going health of the city." Gateway signs that better reflect the City's brand will contribute to the renewal of those places.
Useful LifeProject Name Gateway Signs Category Infrastructure
Type New
Total Project Cost:$150,000
Total2025 2026 2027 2028 2029Expenditures 2030
150,00050,000 50,000 50,000Construction
50,000 50,000 50,000 150,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
150,00050,000 50,000 50,000HRA Fund: Centennial Lakes
TIF
50,000 50,000 50,000 150,000Total
54
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Chad Millner
2025 2030thru Department Engineering
Description
The scope of this project is to construct a roundabout on W 69th Street to allow vehicles to turn left into Southdale Center at its westerly entrance
from 69th Street. Currently left turns at this location are prohibited. Other related intersection improvements, such as improved geometric design at
the entrances to Southdale Center and The Galleria along with pedestrian and bicycle improvements, are also anticipated as part of this project.
Project #17-011
Justification
See Summary of Street Reconstruction Projects.
Useful LifeProject Name 69th Street Roundabout Category Infrastructure
Type Expand or enhance
Total Project Cost:$1,000,000
Total2025 2026 2027 2028 2029Expenditures 2030
1,000,0001,000,000Construction
1,000,000 1,000,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
450,000450,000Construction Fund: MSA
450,000450,000HRA Fund: Centennial Lakes
TIF
100,000100,000Utility Fund: Storm
1,000,000 1,000,000Total
55
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Andrew Scipioni
2025 2030thru Department Engineering
Description
The project involves the installation of buffered bike lanes on Valley View Road between West 64th Street and West 66th Street. This facility was
proposed in the 2018 Pedestrian and Bicycle Master Plan and the work will be coordinated with MnDOT
ENVIROMENTAL CONISDERATIONS:
Sidewalks, bicycle facilities and trails support non-motorized transportation, which can replace trips taken by single- or low-occupancy motor
vehicles. This can result in a lower carbon footprint, reduced greenhouse gas emissions and improved air quality.
Project #17-018
Justification
See Summary of Pedestrian/Bike Improvements.
Useful LifeProject Name Valley View Rd Bicycle Facility Improvements Category Infrastructure
Type New
Total Project Cost:$350,000
Total2025 2026 2027 2028 2029Expenditures 2030
350,000Construction350,000
350,000Total350,000
Total2025 2026 2027 2028 2029Funding Sources 2030
350,000HRA Fund: Centennial Lakes
TIF
350,000
350,000Total350,000
56
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Andrew Scipioni
2025 2030thru Department Engineering
Description
This project involves the construction of shared-use paths on the East Frontage Road of Highway 169 between Valley View Road and West 78th
Street and on Braemar Boulevard between the East Frontage Road and Hilary Lane. These new paths will connect to existing facilities on Valley
View Road and West 78th Street, a proposed facility on Hilary Lane, and will form part of the Twin Loops pedestrian and bicycle network
proposed in the 2018 Pedestrian and Bicycle Master Plan.
ENVIROMENTAL CONISDERATIONS:
Sidewalks, bicycle facilities and trails support non-motorized transportation, which can replace trips taken by single- or low-occupancy motor
vehicles. This can result in a lower carbon footprint, reduced greenhouse gas emissions and improved air quality.
Project #17-072
Justification
See Summary of Pedestrian/Bike Improvements.
Useful LifeProject Name Hwy 169 Frontage Rd/Braemar Blvd Shared-Use Paths Category Infrastructure
Type New
Total Project Cost:$658,420
Total2025 2026 2027 2028 2029Expenditures 2030
658,420Construction658,420
658,420Total658,420
Total2025 2026 2027 2028 2029Funding Sources 2030
658,420PACS Fund: Utility Franchise
Fees
658,420
658,420Total658,420
57
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Chad Millner
2025 2030thru Department Engineering
Description
The Wooddale Avenue Bridge over Minnehaha Creek is a Historic Bridge in need of rehabilitation. Specifically the wing walls and the bridge
railings are deteriorating and need replacement. Because of the historic designation, the State Historic Preservation Office and HPC need to
approve a plan of treatment.
ENVIRONMENTAL CONSIDERATIONS:
The plan of treatment will be reviewed with a sustainability lens.
Project #19-301
Justification
The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier public
facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly high
quality of life enjoyed by our residents and businesses.”
The City’s 2020-2021 Budget Work Plan Goals 1 and 3 are: Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable
Development. Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient operations that lessen
the City’s carbon footprint and reduce energy costs. Connected and sustainable development includes an efficient multi-modal transportation
system that balances improving personal mobility options with reducing the community’s carbon footprint all the while reducing negative impacts
on human health and safety.
This project is the implementation of the mission statement and the budget work plan goals. The recommended schedule is based on the age and
condition of the structure, public utility systems, and pedestrian and traffic facilities. It may also be coordinated with other city, county, and state
projects in the area.
Useful Life 75Project Name Wooddale Ave Bridge Historic Rehab Category Infrastructure
Type Replace or repair
Total Project Cost:$2,500,000
Total2025 2026 2027 2028 2029Expenditures 2030
2,500,0002,100,000 400,000Construction
2,100,000 400,000 2,500,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
400,000400,000Construction Fund: MSA
400,000400,000Utility Fund: Storm
1,500,0001,500,000Construction Fund:
Grants/Donations
200,000200,000PACS Fund: Utility Franchise
Fees
2,100,000 400,000 2,500,000Total
58
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Aaron Ditzler
2025 2030thru Department Engineering
Description
This project involves the reconstruction and rehabilitation of local streets (Lee Valley Circle, Fleetwood Drive, Lanham Lane, Kemrich Drive, Tara
Road) within the project area. This includes replacing the entire pavement surface, repair/replacement of curb and gutter, and upgrading public
utilities (watermain, sanitary sewer, and storm sewer). The project may also include installation of sump pump discharge pipes, streetlight
upgrades, and pedestrian, bicycle and traffic facility improvements.
Project #19-308
Justification
See Summary of Street Reconstruction Projects.
Useful Life 50Project Name Prospect Knolls C Reconstruction Category Infrastructure
Type Replace or repair
Total Project Cost:$5,208,917
Total2025 2026 2027 2028 2029Expenditures 2030
5,208,9175,208,917Construction
5,208,917 5,208,917Total
Total2025 2026 2027 2028 2029Funding Sources 2030
1,091,2681,091,268Construction Fund: Special
Assess
1,386,9361,386,936Utility Fund: Storm
854,577854,577Utility Fund: Water
573,550573,550Utility Fund: Sewer
319,200319,200PACS Fund: Utility Franchise
Fees
983,386983,386Special Street Levy
5,208,917 5,208,917Total
59
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Aaron Ditzler
2025 2030thru Department Engineering
Description
This project involves the reconstruction and rehabilitation of local streets (Weston Circle and Village Drive(public only?)) within the project area.
This includes replacing the entire pavement surface, repair/replacement of curb and gutter, and upgrading public utilities (watermain, sanitary
sewer, and storm sewer). The project may also include installation of sump pump discharge pipes, streetlight upgrades, and pedestrian, bicycle and
traffic facility improvements.
Project #19-309
Justification
See Summary of Street Reconstruction Projects.
Useful Life 50Project Name Prospect Knolls D Reconstruction Category Infrastructure
Type Replace or repair
Total Project Cost:$1,488,175
Total2025 2026 2027 2028 2029Expenditures 2030
1,488,1751,488,175Construction
1,488,175 1,488,175Total
Total2025 2026 2027 2028 2029Funding Sources 2030
332,125332,125Construction Fund: Special
Assess
422,111422,111Utility Fund: Storm
260,088260,088Utility Fund: Water
174,559174,559Utility Fund: Sewer
299,292299,292Special Street Levy
1,488,175 1,488,175Total
60
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Aaron Ditzler
2025 2030thru Department Engineering
Description
This project involves the reconstruction and rehabilitation of local streets (2nd Street South, Belmore Lane, Van Buren Avenue, Harrison Avenue,
Tyler Avenue, Tyler Court) within the project area. This includes replacing the entire pavement surface, repair/replacement of curb and gutter, and
upgrading public utilities (watermain, sanitary sewer, and storm sewer). The project may also include installation of sump pump discharge pipes,
streetlight upgrades, and pedestrian, bicycle and traffic facility improvements.
Project #19-310
Justification
See Summary of Street Reconstruction Projects.
Useful Life 50Project Name Presidents B Reconstruction Category Infrastructure
Type Replace or repair
Total Project Cost:$5,669,221
Total2025 2026 2027 2028 2029Expenditures 2030
5,669,2215,669,221Construction
5,669,221 5,669,221Total
Total2025 2026 2027 2028 2029Funding Sources 2030
1,129,5461,129,546Construction Fund: Special
Assess
1,305,0781,305,078Utility Fund: Storm
1,413,4941,413,494Utility Fund: Water
998,443998,443Utility Fund: Sewer
822,660822,660Special Street Levy
5,669,221 5,669,221Total
61
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Aaron Ditzler
2025 2030thru Department Engineering
Description
This project involves the reconstruction and rehabilitation of local streets (West Trail, Samuel Road, Sioux Trail, Sally Lane and Iroquois Circle)
within the project area. This includes replacing the entire pavement surface, repair/replacement of curb and gutter, and upgrading public utilities
(watermain, sanitary sewer, and storm sewer). The project may also include installation of sump pump discharge pipes, streetlight upgrades, and
pedestrian, bicycle and traffic facility improvements.
Project #19-314
Justification
See Summary of Street Reconstruction Projects.
Useful Life 50Project Name Indian Trails A Reconstruction Category Infrastructure
Type Replace or repair
Total Project Cost:$3,434,377
Total2025 2026 2027 2028 2029Expenditures 2030
3,434,3773,434,377Construction
3,434,377 3,434,377Total
Total2025 2026 2027 2028 2029Funding Sources 2030
671,785671,785Construction Fund: Special
Assess
1,038,4751,038,475Utility Fund: Storm
584,530584,530Utility Fund: Water
392,308392,308Utility Fund: Sewer
747,279747,279Special Street Levy
3,434,377 3,434,377Total
62
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Andrew Scipioni
2025 2030thru Department Engineering
Description
This project involves the construction of a sidewalk on the north side of Olinger Boulevard between Vernon Avenue and Tracy Avenue. This
sidewalk will connect to existing sidewalks on Vernon Avenue, Olinger Road, Sun Road, Colonial Way, and Tracy Avenue. This project was
proposed in the 2014 Active Routes to School Plan and the 2018 Pedestrian and Bicycle Master Plan.
ENVIROMENTAL CONSIDERATIONS:
Sidewalks, bicycle facilities and trails support non-motorized transportation, which can replace trips taken by single- or low-occupancy motor
vehicles. This can result in a lower carbon footprint, reduced greenhouse gas emissions and improved air quality.
Project #19-334
Justification
See Summary of Pedestrian/Bike Improvements.
Useful Life 50Project Name Olinger Boulevard Sidewalk Category Infrastructure
Type New
Total Project Cost:$883,500
Total2025 2026 2027 2028 2029Expenditures 2030
883,500418,800 464,700Construction
418,800 464,700 883,500Total
Total2025 2026 2027 2028 2029Funding Sources 2030
883,500418,800 464,700PACS Fund: Utility Franchise
Fees
418,800 464,700 883,500Total
63
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Ross Bintner
2025 2030thru Department Engineering
Description
This project will meet increasing sewer capacity needs in southeast Edina by extending the York Avenue sanitary sewer trunk line. The project
follows the Southeast Edina Sanitary Sewer Study (Barr Engineering 2017). The project builds off CIP 15-147 that included two phases, one in
2017 and in 2020. The project area includes York Avenue north of the Promenade.
ENVIRONMENTAL CONSIDERATIONS:
Utility pipe rehabilitation through trenchless technologies reduces greenhouse gases associated with open cut installations. Efforts to reduce
infiltration and inflow of clean waters reduce future capital and infrastructure need both locally and in the regional treatment system.
Project #19-335
Justification
The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier public
facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly high
quality of life enjoyed by our residents and businesses.”
The City’s 2020-2021 Budget Work Plan Goal 1 is: Maintain Physical Assets & Infrastructure. Properly maintained streets, water main, sanitary
sewer and storm sewer systems provide reliable and efficient operations that lessen the City’s carbon footprint and reduce energy costs.
This project is the implementation of the mission statement and the budget work plan goal. The recommended schedule is based on need. It may
also be coordinated with other city, county, and state projects in the area.
Useful Life 75Project Name Sanitary Trunk Capacity Expansion York Segs 2-3 Category Infrastructure
Type Expand or enhance
Total Project Cost:$3,800,000
Total2025 2026 2027 2028 2029Expenditures 2030
3,800,0003,800,000Construction
3,800,000 3,800,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
3,800,0003,800,000Utility Fund: Sewer
3,800,000 3,800,000Total
64
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Ross Bintner
2025 2030thru Department Engineering
Description
This project will meet increasing sewer capacity needs in southeast Edina by extending the York Avenue sanitary sewer trunk line. The project
follows the Southeast Edina Sanitary Sewer Study (Barr Engineering 2017)
The project builds off of CIP 15-147 that included two phases, one in 2017 and another planned for 2019. The project area includes York Avenue
north of 66th, and 69th Street between Barrie Rd and York.
ENVIRONMENTAL CONSIDERATIONS:
Utility pipe rehabilitation through trenchless technologies reduces greenhouse gases associated with open cut installations. Efforts to reduce
infiltration and inflow of clean waters reduce future capital and infrastructure need both locally and in the regional treatment system.
COST CONSIDERATIONS:
This project qualifies for potential TIF/HRA funding. If Southdale TIF generates additional revenue, in its closing years, funding could be directed
to this project.
Project #19-336
Justification
The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier public
facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly high
quality of life enjoyed by our residents and businesses.”
The City’s 2018-2019 Budget Work Plan Goals 1 and 3 are; Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable
Development, respectively. Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient
operations that lessen the City’s carbon footprint and reduce energy costs. Connected and sustainable development includes an efficient multi-
modal transportation system that balances improving personal mobility options with reducing the community’s carbon footprint all the while
reducing negative impacts on human health and safety.
This project is the implementation of the mission statement and the budget work plan goals. The recommended schedule is based on need. It may
also be coordinated with other city, county, and state projects in the area.
Useful Life 75Project Name Sanitary Trunk Capacity Exp York Seg 4 & Fairview Category Infrastructure
Type Expand or enhance
Total Project Cost:$4,700,000
Total2025 2026 2027 2028 2029Expenditures 2030
4,700,0004,700,000Construction
4,700,000 4,700,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
4,700,0004,700,000Utility Fund: Sewer
4,700,000 4,700,000Total
65
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Ross Bintner
2025 2030thru Department Engineering
Description
This project will use flow metering and groundwater data to target areas with high potential for groundwater infiltration and flood inflow for
investigation and elimination of cross connections and leak points.
Inflow of storm and ground water into the sanitary sewer system uses up system capacity, increases the risk of back flow, and wastes money and
natural resources to convey and treat.
A variety of methods such as in-home inspection, smoke testings, dye testing, and video will be used to identify and eliminate sources of inflow in
the targeted area. Cost effective interventions will be designed and implemented in the following year.
ENVIRONMENTAL CONSIDERATIONS:
Utility pipe rehabilitation through trenchless technologies reduces greenhouse gases associated with open cut installations. Efforts to reduce
infiltration and inflow of clean waters reduce future capital and infrastructure need both locally and in the regional treatment
system.
COST CONSIDERATIONS:
Reduction of inflow and infiltration reduces metered flow which determines the City share of Met Council regional system expense.
Project #19-340
Justification
The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier public
facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly high
quality of life enjoyed by our residents and businesses.”
The City’s 2018-2019 Budget Work Plan Goals 1 and 3 are; Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable
Development, respectively. Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient
operations that lessen the City’s carbon footprint and reduce energy costs. Connected and sustainable development includes an efficient multi-
modal transportation system that balances improving personal mobility options with reducing the community’s carbon footprint all the while
reducing negative impacts on human health and safety.
This project is the implementation of the mission statement and the budget work plan goals. The recommended schedule is based on the age and
condition of the pavement surfaces, public utility systems, and pedestrian and traffic facilities. It may also be coordinated with other city, county,
and state projects in the area.
Useful LifeProject Name Sanitary Targeted Inflow Reduction Project Category Infrastructure
Type Replace or repair
Total Project Cost:$130,000
Total2025 2026 2027 2028 2029Expenditures 2030
130,000Construction130,000
130,000Total130,000
Total2025 2026 2027 2028 2029Funding Sources 2030
130,000Utility Fund: Sewer 130,000
130,000Total130,000
66
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Jessica Wilson
2025 2030thru Department Engineering
Description
A major update to the Comprehensive Water Resources Management Plan (CWRMP) is required to incorporate the Flood Risk Reduction Strategy
(CIP item 19-341) and Clean Water Strategy (CIP item 19-342). The Flood Risk Reduction Strategy and corresponding major amendment are
complete. This CIP item in 2024 would be for the Clean Water Strategy piece
ENVIRONMENTAL CONSIDERATIONS:
This would incorporate the aforementioned strategies into the existing CWRMP.
Project #19-346
Justification
The CWRMP lays out a framework for developing the Flood Risk Reduction Strategy and Clean Water Strategy. These would be considered major
amendments to the plan.
Useful LifeProject Name CWRMP Model Update Category Infrastructure
Type Replace or repair
Total Project Cost:$200,000
Total2025 2026 2027 2028 2029Expenditures 2030
200,000200,000Planning and Design
200,000 200,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
200,000200,000Utility Fund: Storm
200,000 200,000Total
67
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Ross Bintner
2025 2030thru Department Engineering
Description
Since September 2014, it has been standard practice to assess water main pipe conditions in project areas of future street reconstruction. The non-
invasive water main testing provides us with more data about the condition of our water main system similar to closed circuit televising does for
sanitary sewer trunk pipes. This data, plus water main break data proves to be a powerful tool in determining where to spend our water main funds
to get the greatest value to our water main system.
Assessments typically occur two years in advance of a neighborhood reconstruction project and include approximately 20,000 linear feet of
watermain per year.
ENVIRONMENTAL CONSIDERATIONS:
The watermain condition data allows us to only replace the pipes that need it with this infrastructure replacement cycle. By getting the most life out
of the existing watermain pipes, we are reducing the need for new resources where they are not needed. This lowers our potential carbon footprint
and uses only the necessary resources to provide the level of service required.
Project #19-351
Justification
The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier public
facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly high
quality of life enjoyed by our residents and businesses.”
The City’s 2020-2021 Budget Work Plan Goal 1 is: Maintain Physical Assets & Infrastructure. Properly maintained streets, water main, sanitary
sewer and storm sewer systems provide reliable and efficient operations that lessen the City’s carbon footprint and reduce energy costs.
This project is the implementation of the mission statement and the budget work plan goals. The recommended schedule is based on need. It may
also be coordinated with other city, county, and state projects in the area.
Useful LifeProject Name Water Main Condition Assessment Category Infrastructure
Type Replace or repair
Total Project Cost:$1,120,000
Total2025 2026 2027 2028 2029Expenditures 2030
955,000150,000 160,000 160,000 165,000 160,000Planning and Design 160,000
150,000 160,000 160,000 165,000 160,000 955,000Total160,000
Total2025 2026 2027 2028 2029Funding Sources 2030
955,000150,000 160,000 160,000 165,000 160,000Utility Fund: Water 160,000
150,000 160,000 160,000 165,000 160,000 955,000Total160,000
68
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Andrew Scipioni
2025 2030thru Department Engineering
Description
This project involves the construction of a shared-use path on the east side of McCauley Trail between Indian Hills Road and Gleason Road. This
facility will connect to existing pedestrian and bicycle infrastructure on Gleason Road and will form part of the Twin Loops pedestrian and bicycle
network proposed in the 2018 Pedestrian and Bicycle Master Plan.
ENVIROMENTAL CONSIDERATIONS:
Sidewalks, bicycle facilities and trails support non-motorized transportation, which can replace trips taken by single- or low-occupancy motor
vehicles. This can result in a lower carbon footprint, reduced greenhouse gas emissions and improved air quality.
Project #ENG21004
Justification
See Summary of Pedestrian/Bike Improvements.
Useful LifeProject Name McCauley Trail Shared-Use Path Phase 2 Category Infrastructure
Type New
Total Project Cost:$392,731
Total2025 2026 2027 2028 2029Expenditures 2030
392,731392,731Construction
392,731 392,731Total
Total2025 2026 2027 2028 2029Funding Sources 2030
392,731392,731PACS Fund: Utility Franchise
Fees
392,731 392,731Total
69
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Andrew Scipioni
2025 2030thru Department Engineering
Description
This project will support Hennepin County's France Avenue at I-494 improvement project. This project includes the construction of new shared-
use paths on both sides of France Avenue between Minnesota Drive and West 76th Street. These facilities will connect to existing sidewalks on
France Avenue, Minnesota drive and West 76th Street.
ENVIROMENTAL CONSIDERATIONS:
Sidewalks, bicycle facilities and trails support non-motorized transportation, which can replace trips taken by single- or low-occupancy motor
vehicles. This can result in a lower carbon footprint, reduced greenhouse gas emissions and improved air quality.
Project #ENG21006
Justification
See Summary of Pedestrian/Bike Improvements.
Useful Life 50Project Name France Avenue Shared-Use Paths Category Infrastructure
Type New
Total Project Cost:$1,541,300
Total2025 2026 2027 2028 2029Expenditures 2030
1,541,300762,900 778,400Construction
762,900 778,400 1,541,300Total
Total2025 2026 2027 2028 2029Funding Sources 2030
1,541,300762,900 778,400PACS Fund: Utility Franchise
Fees
762,900 778,400 1,541,300Total
70
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Andrew Scipioni
2025 2030thru Department Engineering
Description
This project involves the construction of sidewalks on Lincoln Drive between Maloney Avenue and 7th Street, 7th Street between Lincoln Drive
and Highway 169, and Malibu Drive between Lincoln Drive and Park Terrace. These sidewalks will connect to the existing sidewalk on Maloney
Avenue and will provide residents in the Presidents and Parkwood Knolls neighborhoods with a safe walking connection to Van Valkenburg Park.
These sidewalks were proposed in the 2018 Pedestrian and Bicycle Master Plan.
ENVIROMENTAL CONSIDERATIONS:
Sidewalks, bicycle facilities and trails support non-motorized transportation, which can replace trips taken by single- or low-occupancy motor
vehicles. This can result in a lower carbon footprint, reduced greenhouse gas emissions and improved air quality.
Project #ENG21007
Justification
See Summary of Pedestrian/Bike Improvements.
Useful LifeProject Name Lincoln Drive/7th Street/Malibu Drive Sidewalks Category Infrastructure
Type New
Total Project Cost:$419,600
Total2025 2026 2027 2028 2029Expenditures 2030
419,600419,600Construction
419,600 419,600Total
Total2025 2026 2027 2028 2029Funding Sources 2030
419,600419,600PACS Fund: Utility Franchise
Fees
419,600 419,600Total
71
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Andrew Scipioni
2025 2030thru Department Engineering
Description
This project would construct a sidewalk on West 60th Street between France Avenue and Xerxes Avenue. This sidewalk will connect to existing
sidewalks on France Avenue, Beard Avenue and Xerxes Avenue and was proposed in the 2018 Pedestrian and Bicycle Master Plan.
ENVIROMENTAL CONSIDERATIONS:
Sidewalks, bicycle facilities and trails support non-motorized transportation, which can replace trips taken by single- or low-occupancy motor
vehicles. This can result in a lower carbon footprint, reduced greenhouse gas emissions and improved air quality.
Project #ENG21013
Justification
See Summary of Pedestrian/Bike Improvements.
Useful Life 50Project Name West 60th Street Sidewalk Category Infrastructure
Type New
Total Project Cost:$710,500
Total2025 2026 2027 2028 2029Expenditures 2030
710,500Construction710,500
710,500Total710,500
Total2025 2026 2027 2028 2029Funding Sources 2030
710,500PACS Fund: Utility Franchise
Fees
710,500
710,500Total710,500
72
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Andrew Scipioni
2025 2030thru Department Engineering
Description
This project would construct a sidewalk on the north side of West 77th Street between Normandale Road and Parklawn Avenue. This sidewalk will
connect to the existing sidewalk on Parklawn Avenue and will support transit riders along West 77th Street. This sidewalk was proposed in the
2018 Pedestrian and Bicycle Master Plan.
ENVIROMENTAL CONSIDERATIONS:
Sidewalks, bicycle facilities and trails support non-motorized transportation, which can replace trips taken by single- or low-occupancy motor
vehicles. This can result in a lower carbon footprint, reduced greenhouse gas emissions and improved air quality.
Project #ENG21014
Justification
See Summary of Pedestrian/Bike Improvements.
Useful LifeProject Name West 77th Street Sidewalk Category Infrastructure
Type New
Total Project Cost:$483,100
Total2025 2026 2027 2028 2029Expenditures 2030
483,100483,100Construction
483,100 483,100Total
Total2025 2026 2027 2028 2029Funding Sources 2030
483,100483,100PACS Fund: Utility Franchise
Fees
483,100 483,100Total
73
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Andrew Scipioni
2025 2030thru Department Engineering
Description
This project involves construction of a shared-use path on Benton Avenue between Hansen Road and Normandale Road. This path will connect to
existing sidewalks on Normandale Road, Hansen Road and Benton Avenue, and will support transit riders along Benton Avenue. This path will
form part of the Twin Loops pedestrian and bicycle network proposed in the 2018 Pedestrian and Bicycle Master Plan.
ENVIROMENTAL CONSIDERATIONS:
Sidewalks, bicycle facilities and trails support non-motorized transportation, which can replace trips taken by single- or low-occupancy motor
vehicles. This can result in a lower carbon footprint, reduced greenhouse gas emissions and improved air quality.
Project #ENG21015
Justification
The City strives to improve mobility for residents, visitors and businesses through a multi-modal transportation system that accommodates
pedestrians, bicyclists, transit users and motorists. This ideal is reflected in the Comprehensive Plan, the Living Streets Plan, the Active Routes to
School Plan and the Pedestrian and Bicycle Master Plan. Walking and biking infrastructure promotes equity, safety and convenience and provides
meaningful opportunities for active living and better health.
Useful LifeProject Name Benton Avenue Shared-Use Path Category Infrastructure
Type New
Total Project Cost:$730,400
Total2025 2026 2027 2028 2029Expenditures 2030
730,400730,400Construction
730,400 730,400Total
Total2025 2026 2027 2028 2029Funding Sources 2030
730,400730,400PACS Fund: Utility Franchise
Fees
730,400 730,400Total
74
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Andrew Scipioni
2025 2030thru Department Engineering
Description
This project involves construction of a shared-use path on the south side of West 64th Street between West Shore Drive and West 66th Street. This
path will connect to existing sidewalks on West 66th Street, the Edina Aquatic Center, the Edina Art House, Rosland Park, and the pedestrian
bridge over Highway 62. This path will form part of the Twin Loops pedestrian and bicycle network proposed in the 2018 Pedestrian and Bicycle
Master Plan.
ENVIROMENTAL CONSIDERATIONS:
Sidewalks, bicycle facilities and trails support non-motorized transportation, which can replace trips taken by single- or low-occupancy motor
vehicles. This can result in a lower carbon footprint, reduced greenhouse gas emissions and improved air quality.
Project #ENG21016
Justification
The City strives to improve mobility for residents, visitors and businesses through a multi-modal transportation system that accommodates
pedestrians, bicyclists, transit users and motorists. This ideal is reflected in the Comprehensive Plan, the Living Streets Plan, the Active Routes to
School Plan and the Pedestrian and Bicycle Master Plan. Walking and biking infrastructure promotes equity, safety and convenience and provides
meaningful opportunities for active living and better health.
Useful LifeProject Name West 64th Street Shared-Use Path Category Infrastructure
Type New
Total Project Cost:$422,654
Total2025 2026 2027 2028 2029Expenditures 2030
422,654Construction422,654
422,654Total422,654
Total2025 2026 2027 2028 2029Funding Sources 2030
422,654PACS Fund: Utility Franchise
Fees
422,654
422,654Total422,654
75
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Andrew Scipioni
2025 2030thru Department Engineering
Description
This project would construct a sidewalk on the south side of Valley View Road between Chapel Lane and Antrim Road. This sidewalk will connect
to existing sidewalks on Valley View Road and Antrim Road, and was proposed in the 2018 Pedestrian and Bicycle Master Plan.
ENVIROMENTAL CONSIDERATIONS:
Sidewalks, bicycle facilities and trails support non-motorized transportation, which can replace trips taken by single- or low-occupancy motor
vehicles. This can result in a lower carbon footprint, reduced greenhouse gas emissions and improved air quality.
Project #ENG21017
Justification
See Summary of Pedestrian/Bike Improvements.
Useful LifeProject Name Valley View Road Sidewalk Category Infrastructure
Type New
Total Project Cost:$109,100
Total2025 2026 2027 2028 2029Expenditures 2030
109,100109,100Construction
109,100 109,100Total
Total2025 2026 2027 2028 2029Funding Sources 2030
109,100109,100PACS Fund: Utility Franchise
Fees
109,100 109,100Total
76
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Andrew Scipioni
2025 2030thru Department Engineering
Description
This project would construct a sidewalk on Amundson Avenue between Cahill Road and West 70th Street. This sidewalk will connect to existing
sidewalks on the Cahill Road and West 70th Street, to the Nine Mile Creek Regional Trail and to the future Canadian Pacific Rail Regional Trail.
This sidewalk was proposed in the 2018 Pedestrian and Bicycle Master Plan.
ENVIROMENTAL CONSIDERATIONS:
Sidewalks, bicycle facilities and trails support non-motorized transportation, which can replace trips taken by single- or low-occupancy motor
vehicles. This can result in a lower carbon footprint, reduced greenhouse gas emissions and improved air quality.
Project #ENG21018
Justification
See Summary of Pedestrian/Bike Improvements.
Useful LifeProject Name Amundson Avenue Sidewalk Category Infrastructure
Type New
Total Project Cost:$156,100
Total2025 2026 2027 2028 2029Expenditures 2030
156,100Construction156,100
156,100Total156,100
Total2025 2026 2027 2028 2029Funding Sources 2030
156,100PACS Fund: Utility Franchise
Fees 156,100
156,100Total156,100
77
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Andrew Scipioni
2025 2030thru Department Engineering
Description
This project would construct a shared-use path on Interlachen Boulevard between Blake Road and Mirror Lakes Drive. This path will connect to
existing pedestrian and bicycle infrastructure on Blake Road, Interlachen Boulevard and Mirror Lakes Drive, and was proposed in the 2018
Pedestrian and Bicycle Master Plan.
ENVIROMENTAL CONSIDERATIONS:
Sidewalks, bicycle facilities and trails support non-motorized transportation, which can replace trips taken by single- or low-occupancy motor
vehicles. This can result in a lower carbon footprint, reduced greenhouse gas emissions and improved air quality.
Project #ENG21019
Justification
See Summary of Pedestrian/Bike Improvements.
Useful LifeProject Name Interlachen Boulevard Shared-Use Path Category Infrastructure
Type New
Total Project Cost:$381,600
Total2025 2026 2027 2028 2029Expenditures 2030
381,600381,600Construction
381,600 381,600Total
Total2025 2026 2027 2028 2029Funding Sources 2030
381,600381,600PACS Fund: Utility Franchise
Fees
381,600 381,600Total
78
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Aaron Ditzler
2025 2030thru Department Engineering
Description
This project involves the reconstruction and rehabilitation of local streets (Washington Avenue South, Adams Avenue, Jefferson Ave South,
Madison Avenue South, Monroe Avenue South, Jackson Avenue South, Van Buren Avenue South, Harrison Avenue South, Tyler Avenue South,
Tyler Court, 2nd Street South, Belmore Lane, 3rd Street South) within the project area. This includes replacing the entire pavement surface,
repair/replacement of curb and gutter, and upgrading public utilities (watermain, sanitary sewer, and storm sewer). The project may also include
installation of sump pump discharge pipes, streetlight upgrades, and pedestrian, bicycle and traffic facility improvements.
Project #ENG21021
Justification
See Summary of Street Reconstruction Projects.
Useful Life 50Project Name Presidents A Reconstruction Category Infrastructure
Type Replace or repair
Total Project Cost:$10,002,281
Total2025 2026 2027 2028 2029Expenditures 2030
10,002,28110,002,281Construction
10,002,281 10,002,281Total
Total2025 2026 2027 2028 2029Funding Sources 2030
1,946,4511,946,451Construction Fund: Special
Assess
2,248,9282,248,928Utility Fund: Storm
2,435,7532,435,753Utility Fund: Water
1,720,5301,720,530Utility Fund: Sewer
233,000233,000PACS Fund: Utility Franchise
Fees
1,417,6191,417,619Special Street Levy
10,002,281 10,002,281Total
79
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Aaron Ditzler
2025 2030thru Department Engineering
Description
This project involves the reconstruction and rehabilitation of local street Parklawn Court from Parklawn Avenue to the cul-de-sac. This includes
replacing the entire pavement surface, repair/replacement of curb and gutter, and upgrading public utilities (watermain, sanitary sewer, and storm
sewer). The project may also include installation of sump pump discharge pipes, streetlight upgrades, and pedestrian, bicycle and traffic facility
improvements.
Project #ENG21023
Justification
See Summary of Street Reconstruction Projects.
Useful LifeProject Name Parklawn (Parklawn Ct) Reconstruction Category Infrastructure
Type Replace or repair
Total Project Cost:$403,404
Total2025 2026 2027 2028 2029Expenditures 2030
403,404403,404Construction
403,404 403,404Total
Total2025 2026 2027 2028 2029Funding Sources 2030
87,30187,301Construction Fund: Special
Assess
110,184110,184Utility Fund: Storm
59,44959,449Utility Fund: Water
39,89939,899Utility Fund: Sewer
27,90027,900PACS Fund: Utility Franchise
Fees
78,67178,671Special Street Levy
403,404 403,404Total
80
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Aaron Ditzler
2025 2030thru Department Engineering
Description
This project involves the reconstruction and rehabilitation of local streets (Annaway Drive, Bywood West, Crescent Terrace, Mait Lane, Merilane,
Paddock Road, Rolling Green Parkway) within the project area. This includes replacing the entire pavement surface, repair/replacement of curb and
gutter, and upgrading public utilities (watermain, sanitary sewer, and storm sewer). The project may also include installation of sump pump
discharge pipes, streetlight upgrades, and pedestrian, bicycle and traffic facility improvements.
Project #ENG21024
Justification
See Summary of Street Reconstruction Projects.
Useful Life 50Project Name Rolling Green Reconstruction Category Infrastructure
Type Replace or repair
Total Project Cost:$11,258,861
Total2025 2026 2027 2028 2029Expenditures 2030
11,258,86111,258,861Construction
11,258,861 11,258,861Total
Total2025 2026 2027 2028 2029Funding Sources 2030
2,505,0502,505,050Construction Fund: Special
Assess
4,009,2434,009,243Utility Fund: Storm
1,676,6781,676,678Utility Fund: Water
281,326281,326Utility Fund: Sewer
2,786,5642,786,564Special Street Levy
11,258,861 11,258,861Total
81
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Aaron Ditzler
2025 2030thru Department Engineering
Description
This project involves the reconstruction and rehabilitation of local streets (Halifax Lane, Woodland Circle) within the project area. This includes
replacing the entire pavement surface, repair/replacement of curb and gutter, and upgrading public utilities (watermain, sanitary sewer, and storm
sewer). The project may also include installation of sump pump discharge pipes, streetlight upgrades, and pedestrian, bicycle and traffic facility
improvements.
Project #ENG21025
Justification
See Summary of Street Reconstruction Projects.
Useful Life 50Project Name Minnehaha Woods D Reconstruction Category Infrastructure
Type Replace or repair
Total Project Cost:$3,716,209
Total2025 2026 2027 2028 2029Expenditures 2030
3,716,2093,716,209Construction
3,716,209 3,716,209Total
Total2025 2026 2027 2028 2029Funding Sources 2030
456,609456,609Construction Fund: Special
Assess
946,760946,760Utility Fund: Storm
897,902897,902Utility Fund: Water
342,836342,836Utility Fund: Sewer
288,600288,600PACS Fund: Utility Franchise
Fees
783,502783,502Special Street Levy
3,716,209 3,716,209Total
82
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Aaron Ditzler
2025 2030thru Department Engineering
Description
This project involves the reconstruction and rehabilitation of local streets (Andover Road, Claremore Drive, Dunham Drive, Ellsworth Drive,
Fondell Drive, Gilford Drive, Kellogg Avenue, Oaklawn Avenue, West 72nd Street, West Shore Drive, Wooddale Avenue) within the project area.
This includes replacing the entire pavement surface, repair/replacement of curb and gutter, and upgrading public utilities (watermain, sanitary
sewer, and storm sewer). The project may also include installation of sump pump discharge pipes, streetlight upgrades, and pedestrian, bicycle and
traffic facility improvements.
ENVIRONMENTAL CONSIDERATIONS:
Carbon: The Pavement Management Program implemented by the City seeks to utilize resources efficiently by performing
infrastructure renewal that will provide the greatest lifespan increase for the lowest cost. Compared to new construction
projects, our roadway reconstruction projects try to minimize disturbance and/or reuse as much of the existing facilities as
possible to reduce the environmental impact.
Surface water: The Living Streets initiative reduces impervious surfaces and develops roads, bicycle and pedestrian
facilities with low impact development techniques.
Green Alternatives: Alternative construction methods utilized within the City include reclamation of existing bituminous
surfaces to use as aggregate base material, implementation of utility pipe rehabilitation through trenchless technologies
thus reducing greenhouse gases associated with open cut installations, and hydro-seeding restoration versus traditional
sod placement when feasible.
Project #ENG21026
Justification
The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier public
facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly high
quality of life enjoyed by our residents and businesses.”
The City’s 2018-2019 Budget Work Plan Goals 1 and 3 are; Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable
Development, respectively. Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient
operations that lessen the City’s carbon footprint and reduce energy costs. Connected and sustainable development includes an efficient multi-
modal transportation system that balances improving personal mobility options with reducing the community’s carbon footprint all the while
reducing negative impacts on human health and safety.
This project is the implementation of the mission statement and the budget work plan goals. The recommended schedule is based on the age and
condition of the pavement surfaces, public utility systems, and pedestrian and traffic facilities. It may also be coordinated with other city, county,
and state projects in the area.
Useful LifeProject Name South Cornelia B Reconstruction Category Infrastructure
Type Replace or repair
Total Project Cost:$8,543,895
Total2025 2026 2027 2028 2029Expenditures 2030
8,543,8958,543,895Construction
8,543,895 8,543,895Total
Total2025 2026 2027 2028 2029Funding Sources 2030
3,447,2973,447,297Construction Fund: Special
Assess
2,049,8752,049,875Utility Fund: Storm
1,530,6691,530,669Utility Fund: Water
1,071,9041,071,904Utility Fund: Sewer
444,150444,150PACS Fund: Utility Franchise
Fees
8,543,895 8,543,895Total
83
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Aaron Ditzler
2025 2030thru Department Engineering
Description
This project involves the reconstruction and rehabilitation of local streets (Cornelia Drive, Glouchester Avenue, Heatherton Trail, Bristol
Boulevard, Lynmar Lane, Mavelle Drive, Sandell Avenue, Hazelton Road, West 72nd Street) within the project area. This includes replacing the
entire pavement surface, repair/replacement of curb and gutter, and upgrading public utilities (watermain, sanitary sewer, and storm sewer). The
project may also include installation of sump pump discharge pipes, streetlight upgrades, and pedestrian, bicycle and traffic facility improvements.
ENVIRONMENTAL CONSIDERATIONS:
Carbon: The Pavement Management Program implemented by the City seeks to utilize resources efficiently by performing
infrastructure renewal that will provide the greatest lifespan increase for the lowest cost. Compared to new construction
projects, our roadway reconstruction projects try to minimize disturbance and/or reuse as much of the existing facilities as
possible to reduce the environmental impact.
Surface water: The Living Streets initiative reduces impervious surfaces and develops roads, bicycle and pedestrian
facilities with low impact development techniques.
Green Alternatives: Alternative construction methods utilized within the City include reclamation of existing bituminous
surfaces to use as aggregate base material, implementation of utility pipe rehabilitation through trenchless technologies
thus reducing greenhouse gases associated with open cut installations, and hydro-seeding restoration versus traditional
sod placement when feasible.
Project #ENG21027
Justification
The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier public
facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly high
quality of life enjoyed by our residents and businesses.”
The City’s 2018-2019 Budget Work Plan Goals 1 and 3 are; Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable
Development, respectively. Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient
operations that lessen the City’s carbon footprint and reduce energy costs. Connected and sustainable development includes an efficient multi-
modal transportation system that balances improving personal mobility options with reducing the community’s carbon footprint all the while
reducing negative impacts on human health and safety.
This project is the implementation of the mission statement and the budget work plan goals. The recommended schedule is based on the age and
condition of the pavement surfaces, public utility systems, and pedestrian and traffic facilities. It may also be coordinated with other city, county,
and state projects in the area.
Useful LifeProject Name South Cornelia D Reconstruction Category Infrastructure
Type Replace or repair
Total Project Cost:$8,313,293
Total2025 2026 2027 2028 2029Expenditures 2030
8,313,293Construction8,313,293
8,313,293Total8,313,293
Total2025 2026 2027 2028 2029Funding Sources 2030
3,182,394Construction Fund: Special
Assess
3,182,394
1,830,277Utility Fund: Storm 1,830,277
2,343,549Utility Fund: Water 2,343,549
957,073Utility Fund: Sewer 957,073
8,313,293Total8,313,293
84
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Aaron Ditzler
2025 2030thru Department Engineering
Description
This project involves the reconstruction of Municipal State Aid designated Hilary Lane from Braemar Boulevard to Gleason Road. This includes
replacing the entire pavement surface, repair/replacement of curb and gutter, and upgrading public utilities (watermain, sanitary sewer, and storm
sewer). The project may also include streetlight upgrades, and pedestrian, bicycle and traffic facility improvements. The project will meet current
State Aid requirements.
Project #ENG21028
Justification
See Summary of Street Reconstruction Projects.
Useful Life 50Project Name Hilary Lane Reconstruction Category Infrastructure
Type Replace or repair
Total Project Cost:$6,317,053
Total2025 2026 2027 2028 2029Expenditures 2030
6,317,053190,400 6,126,653Construction
190,400 6,126,653 6,317,053Total
Total2025 2026 2027 2028 2029Funding Sources 2030
3,387,9783,387,978Construction Fund: MSA
302,453302,453Construction Fund: Special
Assess
1,009,2451,009,245Utility Fund: Storm
786,652786,652Utility Fund: Water
303,883303,883Utility Fund: Sewer
190,400190,400PACS Fund: Utility Franchise
Fees
336,442336,442Special Street Levy
190,400 6,126,653 6,317,053Total
85
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Aaron Ditzler
2025 2030thru Department Engineering
Description
This project involves the reconstruction of Municipal State Aid designated West 76th Street from Parklawn Avenue to France Avenue. This
includes replacing the entire pavement surface, repair/replacement of curb and gutter, and upgrading public utilities (watermain, sanitary sewer, and
storm sewer). The project may also include streetlight upgrades, and pedestrian, bicycle and traffic facility improvements. The project will meet
current State Aid requirements.
Project #ENG21030
Justification
See Summary of Street Reconstruction Projects.
Useful LifeProject Name West 76th Street A Reconstruction Category Infrastructure
Type Replace or repair
Total Project Cost:$2,008,524
Total2025 2026 2027 2028 2029Expenditures 2030
2,008,5242,008,524Construction
2,008,524 2,008,524Total
Total2025 2026 2027 2028 2029Funding Sources 2030
968,276968,276Construction Fund: MSA
200,919200,919Construction Fund: Special
Assess
385,207385,207Utility Fund: Storm
247,724247,724Utility Fund: Water
165,248165,248Utility Fund: Sewer
41,15041,150PACS Fund: Utility Franchise
Fees
2,008,524 2,008,524Total
86
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Marisa Bayer
2025 2030thru Department Engineering
Description
This project will continue to build electric vehicle charging infrastructure and provide support for fleet improvements to change to electric vehicles.
Electrification of vehicles is happening as costs lower and mileage range continues to grow. Electric vehicles provide to lower GHG emissions and
improve air quality with zero tailpipe emissions. One of the top hurdles to EV adoption is the lack of charging infrastructure to "fuel" up the
vehicle. To support EV adoption, the City will need to make investments in EV infrastructure.
ENVIRONMENTAL CONSIDERATIONS:
Supporting electric vehicle infrastructure and fleet replacements provides an excellent opportunity for the City to continue towards our
sustainability goals. Each specific project will be reviewed from an environmental cost benefit analysis to determine the right balance between
operations and sustainability.
Project #ENG21040
Justification
The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier public
facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly high
quality of life enjoyed by our residents and businesses.”
The City’s 2020-2021 Budget Work Plan Goal 1 is: Maintain Physical Assets & Infrastructure. Properly maintained facilities provide reliable and
efficient operations that lessen the City’s carbon footprint and reduce energy costs.
This project is the implementation of the mission statement and the budget work plan goal.
Useful Life 10Project Name Electric Vehicle Infrastructure & Vehicle Upgrades Category Equipment and Vehicles
Type Replace or repair
Total Project Cost:$600,000
Total2025 2026 2027 2028 2029Expenditures 2030
600,000100,000 100,000 100,000 100,000 100,000Vehicles and Equipment 100,000
100,000 100,000 100,000 100,000 100,000 600,000Total100,000
Total2025 2026 2027 2028 2029Funding Sources 2030
600,000100,000 100,000 100,000 100,000 100,000CAS Fund: Utility Franchise
Fees
100,000
100,000 100,000 100,000 100,000 100,000 600,000Total100,000
87
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Derik Otten
2025 2030thru Department Engineering
Description
In our continuing efforts to provide an accessible environment for residents, visitors and
employees, the City completed an ADA inventory to understand areas of need. The inventory conducted an evaluation for compliance with
applicable laws, codes and design guidelines pertaining to accessibility.
ENVIRONMENTAL CONSIDERATIONS:
Facility improvements provide an excellent opportunity for the City to continue towards our sustainability goals. Each specific project will be
reviewed from an environmental cost benefit analysis to determine the right balance between operations and sustainability.
Project #ENG21045
Justification
The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier public
facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly high
quality of life enjoyed by our residents and businesses.”
This project is the implementation of the mission statement and the budget work plan goal.
Useful LifeProject Name City Wide ADA Facility Improvements Level 3&4 Category Buildings
Type Replace or repair
Total Project Cost:$1,336,000
Total2025 2026 2027 2028 2029Expenditures 2030
1,336,0001,336,000Construction
1,336,000 1,336,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
1,336,0001,336,000Construction Fund: CIP Levy
1,336,000 1,336,000Total
88
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Ross Bintner
2025 2030thru Department Engineering
Description
This project will meet increasing sewer capacity needs near Lift Station #6 along 72nd Street. The pipe is undersized and requires more capacity.
ENVIRONMENTAL CONSIDERATIONS:
Carbon: The Pavement Management Program implemented by the City seeks to utilize resources efficiently by performing infrastructure renewal
that will provide the greatest lifespan increase for the lowest cost. Compared to new construction projects, our roadway reconstruction projects try
to minimize disturbance and/or reuse as much of the existing facilities as possible to reduce the environmental impact.
Surface water: The Living Streets initiative reduces impervious surfaces and develops roads, bicycle and pedestrian facilities with low impact
development techniques.
Green Alternatives: Alternative construction methods utilized within the City include reclamation of existing bituminous surfaces to use as
aggregate base material, implementation of utility pipe rehabilitation through trenchless technologies
thus reducing greenhouse gases associated with open cut installations, and hydro-seeding restoration versus traditional sod placement when
feasible.
Project #ENG21055
Justification
The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier public
facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly high
quality of life enjoyed by our residents and businesses.”
The City’s 2018-2019 Budget Work Plan Goals 1 and 3 are; Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable
Development, respectively. Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient
operations that lessen the City’s carbon footprint and reduce energy costs. Connected and sustainable development includes an efficient multimodal
transportation system that balances improving personal mobility options with reducing the community’s carbon footprint all the while reducing
negative impacts on human health and safety.
This project is the implementation of the mission statement and the budget work plan goals. The recommended schedule is based on the age and
condition of the pavement surfaces, public utility systems, and pedestrian and traffic facilities.
Useful LifeProject Name 72nd Street Sewer Line Upsize Category Infrastructure
Type Replace or repair
Total Project Cost:$1,600,000
Total2025 2026 2027 2028 2029Expenditures 2030
1,600,0001,600,000Construction
1,600,000 1,600,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
1,600,0001,600,000Utility Fund: Sewer
1,600,000 1,600,000Total
89
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Ross Bintner
2025 2030thru Department Engineering
Description
The project is included in the Water Supply Plan to better distribute water out from Water Treatment Plant #6. This project will install new
watermain along Vernon Avenue connecting to 52nd Street. The project will start near the Grandview Parking Ramp.
Project #ENG21058
Justification
The City’s mission statement "is to provide effective and valued public services, maintain a sound public infrastructure, offer premier public
facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly high
quality of life enjoyed by our residents and businesses."
The City’s 2020-2021 Budget Work Plan Goals 1 and 3 are: Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable
Development. Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient operations that lessen
the City’s carbon footprint and reduce energy costs. Connected and sustainable development includes an efficient multi-modal transportation
system that balances improving personal mobility options with reducing the community’s carbon footprint all the while reducing negative impacts
on human health and safety.
This project is the implementation of the mission statement and the budget work plan goals. The recommended schedule is based on the age and
condition of the pavement surfaces, public utility systems, and pedestrian and traffic facilities. It may also be coordinated with other city, county,
and state projects in the area.
Useful LifeProject Name Water Supply Grandview Area PH 3 Category Infrastructure
Type Replace or repair
Total Project Cost:$2,500,000
Total2025 2026 2027 2028 2029Expenditures 2030
2,500,0002,500,000Construction
2,500,000 2,500,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
2,500,0002,500,000Utility Fund: Water
2,500,000 2,500,000Total
90
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Ross Bintner
2025 2030thru Department Engineering
Description
The project is included in the Water Supply Plan to improve fire flows and circulation in the northeast area of the City
Project #ENG21059
Justification
Useful LifeProject Name Water Supply 50th and France Category Infrastructure
Type Replace or repair
Total Project Cost:$2,000,000
Total2025 2026 2027 2028 2029Expenditures 2030
2,000,000Construction2,000,000
2,000,000Total2,000,000
Total2025 2026 2027 2028 2029Funding Sources 2030
2,000,000Utility Fund: Water 2,000,000
2,000,000Total2,000,000
91
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Ross Bintner
2025 2030thru Department Engineering
Description
Project #ENG21060
Justification
Useful LifeProject Name Water Supply Pentagon Park Category Infrastructure
Type Replace or repair
Total Project Cost:$1,000,000
Total2025 2026 2027 2028 2029Expenditures 2030
1,000,000Construction1,000,000
1,000,000Total1,000,000
Total2025 2026 2027 2028 2029Funding Sources 2030
1,000,000Utility Fund: Water 1,000,000
1,000,000Total1,000,000
92
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Chad Millner
2025 2030thru Department Engineering
Description
The multi-tiered retaining wall has a history of small area failures. Each failure requires a small contract with a vendor to patch together at the
location of the failure. This project will remove and replace the entire wall with a large modular block wall system.
ENVIRONMENTAL CONSIDERATIONS:
The retaining wall is due for a complete replacement. A complete replacement with a more structurally sound retaining wall system will greatly
reduce time and resources needed to complete small, frequent repairs to the existing wall.
Project #ENG21061
Justification
The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier public
facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly high
quality of life enjoyed by our residents and businesses.”
The City’s Budget Work Plan Goal 1 is: Maintain Physical Assets & Infrastructure. Properly maintained streets, retaining walls, water main,
sanitary sewer and storm sewer systems provide reliable and efficient operations that lessen the City’s carbon footprint and reduce energy costs.
This project is the implementation of the mission statement and the budget work plan goals.
Useful LifeProject Name 6520 Belmore Lane Multi-Tiered Retaining Wall Category Infrastructure
Type Replace or repair
Total Project Cost:$400,000
Total2025 2026 2027 2028 2029Expenditures 2030
400,000400,000Construction
400,000 400,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
400,000400,000Bridge Maintenance
400,000 400,000Total
93
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Aaron Ditzler
2025 2030thru Department Engineering
Description
This project involves the reconstruction and rehabilitation of local streets (West 70th Street, Antrim Court, Antrim Road, Antrim Terrace, Down
Road, Dublin Circle, Dublin Road, Kerry Road, Lee Valley Road, Shannon Drive, Tralee Drive, Wexford Road) within the project area. This
includes replacing the entire pavement surface, repair/replacement of curb and gutter, and upgrading public utilities (watermain, sanitary sewer, and
storm sewer). The project may also include installation of sump pump discharge pipes, streetlight upgrades, and pedestrian and traffic facility
improvements.
Project #ENG23001
Justification
See Summary of Street Reconstruction Projects.
Useful Life 50Project Name Prospect Knolls A Reconstruction Category Infrastructure
Type Replace or repair
Total Project Cost:$6,650,793
Total2025 2026 2027 2028 2029Expenditures 2030
6,650,7936,650,793Construction
6,650,793 6,650,793Total
Total2025 2026 2027 2028 2029Funding Sources 2030
1,632,1581,632,158Construction Fund: Special
Assess
1,583,4181,583,418Utility Fund: Storm
1,278,1481,278,148Utility Fund: Water
686,265686,265Utility Fund: Sewer
1,470,8041,470,804Special Street Levy
6,650,793 6,650,793Total
94
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Aaron Ditzler
2025 2030thru Department Engineering
Description
This project involves the reconstruction and rehabilitation of local streets (Gate Park Road, Johnson Drive, Ridge Park Road, Warden Avenue)
within the project area. This includes replacing the entire pavement surface, repair/replacement of curb and gutter, and upgrading public utilities
(watermain, sanitary sewer, and storm sewer). The project may also include installation of sump pump discharge pipes, streetlight upgrades, and
pedestrian and traffic facility improvements.
Project #ENG23002
Justification
See Summary of Street Reconstruction Projects.
Useful LifeProject Name Countryside E Reconstruction Category Infrastructure
Type Replace or repair
Total Project Cost:$3,479,516
Total2025 2026 2027 2028 2029Expenditures 2030
3,479,516Construction3,479,516
3,479,516Total3,479,516
Total2025 2026 2027 2028 2029Funding Sources 2030
782,328Construction Fund: Special
Assess
782,328
850,851Utility Fund: Storm 850,851
584,093Utility Fund: Water 584,093
391,999Utility Fund: Sewer 391,999
870,245Special Street Levy 870,245
3,479,516Total3,479,516
95
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Aaron Ditzler
2025 2030thru Department Engineering
Description
This project involves the reconstruction and rehabilitation of local streets (West 48th Street, West 49th Street, Edinbrook Lane, Millpond Place,
Westbrook Lane) within the project area. This includes replacing the entire pavement surface, repair/replacement of curb and gutter, and upgrading
public utilities (watermain, sanitary sewer, and storm sewer). The project may also include installation of sump pump discharge pipes, streetlight
upgrades, and pedestrian and traffic facility improvements.
Project #ENG23003
Justification
See Summary of Street Reconstruction Projects.
Useful Life 50Project Name Todd Park B Reconstruction Category Infrastructure
Type Replace or repair
Total Project Cost:$3,153,546
Total2025 2026 2027 2028 2029Expenditures 2030
3,153,5463,153,546Construction
3,153,546 3,153,546Total
Total2025 2026 2027 2028 2029Funding Sources 2030
523,709523,709Construction Fund: Special
Assess
826,220826,220Utility Fund: Storm
783,583783,583Utility Fund: Water
299,187299,187Utility Fund: Sewer
720,847720,847Special Street Levy
3,153,546 3,153,546Total
96
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Aaron Ditzler
2025 2030thru Department Engineering
Description
This project involves the reconstruction of Municipal State Aid designated Benton Avenue from Tracy Avenue to Hansen Road. This includes
replacing the entire pavement surface, repair/replacement of curb and gutter, and upgrading public utilities (watermain, sanitary sewer, and storm
sewer). The project may also include streetlight upgrades, and pedestrian, bicycle and traffic facility improvements. The project will meet current
State Aid requirements.
Project #ENG23004
Justification
See Summary of Street Reconstruction Projects.
Useful LifeProject Name Benton Avenue A Reconstruction Category Infrastructure
Type Replace or repair
Total Project Cost:$2,834,512
Total2025 2026 2027 2028 2029Expenditures 2030
2,834,512Construction2,834,512
2,834,512Total2,834,512
Total2025 2026 2027 2028 2029Funding Sources 2030
1,475,297Construction Fund: MSA 1,475,297
108,997Construction Fund: Special
Assess
108,997
434,318Utility Fund: Storm 434,318
369,875Utility Fund: Water 369,875
186,198Utility Fund: Sewer 186,198
109,800PACS Fund: Utility Franchise
Fees
109,800
150,027Special Street Levy 150,027
2,834,512Total2,834,512
97
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Ross Bintner
2025 2030thru Department Engineering
Description
This project rehabilitates sanitary sewer adjacent to the Braemar Golf Course. This area of sanitary sewer has high levels in inflow and infiltration
(I & I) or unnecessary clean water entering the system. Pipe and manholes will be lined where needed to reduce I & I.
ENVIRONMENTAL CONSIDERATIONS:
Green Alternatives: Alternative construction methods utilized within the City include reclamation of existing bituminous surfaces to use as
aggregate base material, implementation of utility pipe rehabilitation through trenchless technologies thus reducing greenhouse gases associated
with open cut installations, and hydro-seeding restoration versus traditional sod placement when feasible.
Project #ENG23009
Justification
The City’s mission statement is to provide effective and valued public services, maintain a sound public infrastructure, offer premier public
facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly high
quality of life enjoyed by our residents and businesses.
The City’s 2020-2021 Budget Work Plan Goals 1 and 3 are: Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable
Development. Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient operations that lessen
the City’s carbon footprint and reduce energy costs. Connected and sustainable development includes an efficient multi-modal transportation
system that balances improving personal mobility options with reducing the community’s carbon footprint all the while reducing negative impacts.
Useful LifeProject Name Hilary Lane Sanitary Sewer Lining Category Infrastructure
Type Replace or repair
Total Project Cost:$300,000
Total2025 2026 2027 2028 2029Expenditures 2030
300,000300,000Construction
300,000 300,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
300,000300,000Utility Fund: Sewer
300,000 300,000Total
98
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Ross Bintner
2025 2030thru Department Engineering
Description
This project will reduce flood risk in the Concord and Golf Terrace Neighborhoods, This project follows the 2022(Draft) Local Surface Water
Management Plan.
Project #ENG23010
Justification
ENVIRONMENTAL CONSIDERATIONS:
Flood Infrastructure project take materials and natural resources to build. Design also includes clean surface water consideration.
Useful LifeProject Name Concord Flood Infrastrucure Project #2 area Category Infrastructure
Type New
Total Project Cost:$10,650,000
Total2025 2026 2027 2028 2029Expenditures 2030
10,650,000200,000 950,000 9,500,000Construction
200,000 950,000 9,500,000 10,650,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
10,650,000200,000 950,000 9,500,000Utility Fund: Storm
200,000 950,000 9,500,000 10,650,000Total
99
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Ross Bintner
2025 2030thru Department Engineering
Description
This project will reduce flood risk in the Arden Park and Country Club Neighborhoods, This project need is discussed in the 2022(Draft) Local
Surface Water Management Plan and informed by further staff evaluation of options to divert and add capacity for flood flow on 50th Street. Other
opportunities for flood risk reduction will be evaluated.
ENVIRONMENTAL CONSIDERATIONS:
Flood Infrastructure project take materials and natural resources to build. Design also includes clean surface water consideration.
Project #ENG23011
Justification
This project is included in the 2022 Local water management plan in concept. 2027 and 2028 costs are placeholders for review and design work
ahead of a 2029+ construction. Capital estimates will be further evaluated and included in later CIPs.
Useful LifeProject Name Arden & 50th Flood Infrastructure Project #3 Area Category Infrastructure
Type New
Total Project Cost:$5,150,000
Total2025 2026 2027 2028 2029Expenditures 2030
650,000200,000 450,000Construction
200,000 450,000 650,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
650,000200,000 450,000Utility Fund: Storm
200,000 450,000 650,000Total
100
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Ross Bintner
2025 2030thru Department Engineering
Description
This project will reduce flood risk in the Lake Cornelia and Normandale Park Neighborhoods, This project follows the 2022(Draft) Local Surface
Water Management Plan and will require further evaluation of options to reduce flood risk.
ENVIRONMENTAL CONSIDERATIONS:
Flood Infrastructure project take materials and natural resources to build. Design also includes clean surface water consideration.
Project #ENG23012
Justification
Useful LifeProject Name Lake Cornelia and Normandale Park Flood Infras Category Infrastructure
Type Horizon
Total Project Cost:$16,000,000
Total2025 2026 2027 2028 2029Expenditures 2030
16,000,00016,000,000Construction
16,000,000 16,000,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
16,000,00016,000,000Utility Fund: Storm
16,000,000 16,000,000Total
101
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Ross Bintner
2025 2030thru Department Engineering
Description
This project will reduce flood risk in the Minnehaha Woods and Pamela Park Neighborhoods, This project proposes the increase in flood carrying
capacity of the France Avenue Minnehaha crossing that drives flood risk in very large storm events.
ENVIRONMENTAL CONSIDERATIONS:
Flood Infrastructure project take materials and natural resources to build.
Project #ENG23013
Justification
2027 and 2028 costs are placeholders for review and design work ahead of a 2029+ construction. Capital estimates will be further evaluated and
included in later CIPs.
Useful LifeProject Name France Avenue Crossing (Minnehaha Creek)Category Infrastructure
Type New
Total Project Cost:$6,800,000
Total2025 2026 2027 2028 2029Expenditures 2030
800,000200,000 600,000Construction
200,000 600,000 800,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
800,000200,000 600,000Utility Fund: Storm
200,000 600,000 800,000Total
102
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Ross Bintner
2025 2030thru Department Engineering
Description
This project proposes to retrofit existing flood control smart infrastructure into existing lift station and flow control features across a part of the
City.
ENVIRONMENTAL CONSIDERATIONS:
Adaptive Level management retrofits take minimal materials and natural resources to build. Design also includes clean surface water consideration.
Project #ENG23014
Justification
This project is included in the 2022 Local water management plan in concept and follows the flood risk reduction strategy. 2025 costs are
placeholders for review and design work ahead of a 2027 construction. Capital estimates will be further evaluated and included in later CIPs.
Useful LifeProject Name Adaptive Level Management Project Ph 2 Minnehaha Category Infrastructure
Type New
Total Project Cost:$2,700,000
Total2025 2026 2027 2028 2029Expenditures 2030
2,700,000200,000 2,500,000Construction
200,000 2,500,000 2,700,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
2,700,000200,000 2,500,000Utility Fund: Storm
200,000 2,500,000 2,700,000Total
103
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Ross Bintner
2025 2030thru Department Engineering
Description
This project proposes to retrofit existing flood control smart infrastructure into existing lift station and flow control features across a part of the
City.
ENVIRONMENTAL CONSIDERATIONS:
Adaptive Level management retrofits take minimal materials and natural resources to build. Design also includes clean surface water consideration.
Project #ENG23015
Justification
This project is included in the 2022 Local water management plan in concept and follows the flood risk reduction strategy. 2023 cost is for review
and design work ahead of a 2025 construction. Capital estimates will be further evaluated and included in the next CIP.
Useful LifeProject Name Adaptive Level Management Project Nine Mile Creek Category Infrastructure
Type New
Total Project Cost:$2,500,000
Total2025 2026 2027 2028 2029Expenditures 2030
2,500,0002,500,000Construction
2,500,000 2,500,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
2,500,0002,500,000Utility Fund: Storm
2,500,000 2,500,000Total
104
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Ross Bintner
2025 2030thru Department Engineering
Description
This project proposes to retrofit existing pipe and graded overflows to better pass flow waters where there are minor downstream tradeoffs.
Project #ENG23016
Justification
This project bundles a variety of minor grading and pipe projects from the 2022 Local water management plan. The 2024 costs are for review and
design work ahead of a 2026 construction. Capital estimates will be further evaluated and included in later CIPs.
Useful LifeProject Name Minor Pipe and Grading Project (Citywide)Category Infrastructure
Type New
Total Project Cost:$2,500,000
Total2025 2026 2027 2028 2029Expenditures 2030
2,500,0002,500,000Construction
2,500,000 2,500,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
2,500,0002,500,000Utility Fund: Storm
2,500,000 2,500,000Total
105
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Ross Bintner
2025 2030thru Department Engineering
Description
This project will reduce flood risk in the Chowen Park and Strachauer Park Neighborhoods, This project need is discussed in the 2022 Local
Surface Water Management Plan and informed by further staff evaluation of options to divert and add capacity for flood flow on 60th and France
Avenue
Project #ENG23017
Justification
Useful LifeProject Name Chowen and 60th Flood Project Category Infrastructure
Type Horizon
Total Project Cost:$1,100,000
Total2025 2026 2027 2028 2029Expenditures 2030
1,100,000Construction1,100,000
1,100,000Total1,100,000
Total2025 2026 2027 2028 2029Funding Sources 2030
1,100,000Utility Fund: Storm 1,100,000
1,100,000Total1,100,000
106
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Ross Bintner
2025 2030thru Department Engineering
Description
This project will meet increasing sewer capacity in southeast Edina by extending the York Avenue sanitary sewer trunk line. The project follows
the Southeast Edina Sanitary Sewer Study (Barr Engineering 2017) and the York Avenue Sanitary Sewer Extension (SEH Engineering 2019)
Project #ENG23033
Justification
ENVIRONMENTAL CONSIDERATIONS:
Utility pipe rehabilitation through trenchless technologies reduces greenhouse gases associated with open cut installations. Efforts to reduce
infiltration and inflow of clean waters reduce future capital and infrastructure need both locally and in the regional treatment system.
Useful Life 75Project Name Sanitary Trunk Capacity Exp York Avenue Hazelton Category Infrastructure
Type Expand or enhance
Total Project Cost:$14,400,000
Total2025 2026 2027 2028 2029Expenditures 2030
8,900,000200,000 2,000,000 500,000 5,000,000 1,200,000Construction
200,000 2,000,000 500,000 5,000,000 1,200,000 8,900,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
8,900,000200,000 2,000,000 500,000 5,000,000 1,200,000Utility Fund: Sewer
200,000 2,000,000 500,000 5,000,000 1,200,000 8,900,000Total
107
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Ross Bintner
2025 2030thru Department Engineering
Description
This project will meet increasing sewer capacity in southeast Edina by extending the York Avenue sanitary sewer trunk line. The project follows
the Southeast Edina Sanitary Sewer Study (Barr Engineering 2017) and the York Avenue Sanitary Sewer Extension (SEH Engineering 2019)
Project #ENG23034
Justification
ENVIRONMENTAL CONSIDERATIONS:
Utility pipe rehabilitation through trenchless technologies reduces greenhouse gases associated with open cut installations. Efforts to reduce
infiltration and inflow of clean waters reduce future capital and infrastructure need both locally and in the regional treatment system.
Useful Life 75Project Name Sanitary Trunk Capacity Exp York Avenue 69th St W Category Infrastructure
Type Expand or enhance
Total Project Cost:$1,400,000
Total2025 2026 2027 2028 2029Expenditures 2030
1,400,0001,400,000Construction
1,400,000 1,400,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
1,400,0001,400,000Utility Fund: Sewer
1,400,000 1,400,000Total
108
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Ross Bintner
2025 2030thru Department Engineering
Description
This project will replace, repair and rehabilitate watermain, gate valves,hydrants or service lines in areas that experience high reported breaks or
component failure or are found to be near the end of their expected lifespan though maintenance records and nondestructive testing. One project
area meeting this criteria for a standalone water main rehabilitation is the Heights Neighborhood. Project scope and limits to be determined based
on scale of issue and current construction costs
ENVIRONMENTAL CONSIDERATIONS:
Utility pipe rehabilitation through trenchless technologies reduces greenhouse gases associated with open cut installations. Efforts to reduce water
leaks reduce pumping costs and associated energy use, and reduce future capital and infrastructure need both locally and in the regional production
system.
Project #ENG23035
Justification
The City’s mission statement "is to provide effective and valued public services, maintain a sound public infrastructure, offer premier public
facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly high
quality of life enjoyed by our residents and businesses."
The City’s 2020-2021 Budget Work Plan Goals 1 and 3 are: Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable
Development. Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient operations that lessen
the City’s carbon footprint and reduce energy costs. Connected and sustainable development includes an efficient multi-modal transportation
system that balances improving personal mobility options with reducing the community’s carbon footprint all the while reducing negative impacts
on human health and safety.
This project is the implementation of the mission statement and the budget work plan goals. The recommended schedule is based on the age and
condition of the pavement surfaces, public utility systems, and pedestrian and traffic facilities. It may also be coordinated with other city, county,
and state projects in the area.
Useful LifeProject Name Watermain Rehabilitation (Citywide)Category Infrastructure
Type Replace or repair
Total Project Cost:$1,400,000
Total2025 2026 2027 2028 2029Expenditures 2030
1,400,0001,400,000Construction
1,400,000 1,400,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
1,400,0001,400,000Utility Fund: Water
1,400,000 1,400,000Total
109
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Ross Bintner
2025 2030thru Department Engineering
Description
As part of the 2012 Water Treatment Plant #6 design and construction and the 2018 Water Plan Update, the water distribution system in the
Grandview Area is in need of improvements. The WTP #6 is unable to produce at full capacity because of a lack of pipe size in the distribution
system.
The project would install new watermain pipe from Arcadia Avenue to Grange Road along Vernon Avenue and 50th Street.
ENVIRONMENTAL CONSIDERATIONS:
Utility pipe rehabilitation through trenchless technologies reduces greenhouse gases associated with open cut installations.
Efforts to reduce water leaks reduce pumping costs and associated energy use, and reduce future capital and infrastructure need both locally and in
the regional production system.
Project #ENG23036
Justification
The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier public
facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly high
quality of life enjoyed by our residents and businesses.”
The City’s 2018-2019 Budget Work Plan Goals 1 and 3 are; Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable
Development, respectively. Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient
operations that lessen the City’s carbon footprint and reduce energy costs. Connected and sustainable development includes an efficient multi-
modal transportation system that balances improving personal mobility options with reducing the community’s carbon footprint all the while
reducing negative impacts on human health and safety.
This project is the implementation of the mission statement and the budget work plan goals. The recommended schedule is based on need. It may
also be coordinated with other city, county, and state projects in the area.
Useful LifeProject Name Grandview Area Watermain Improvements PH 2 Category Infrastructure
Type Replace or repair
Total Project Cost:$240,000
Total2025 2026 2027 2028 2029Expenditures 2030
240,000240,000Construction
240,000 240,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
240,000240,000Utility Fund: Water
240,000 240,000Total
110
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Chad Millner
2025 2030thru Department Engineering
Description
This project involves the reconstruction of 50th Street from Grange Road to east of Dale Street. The project was discussed as part of the 4917 Eden
Avenue redevelopment project. It will install traffic safety improvements. This includes replacing the entire pavement surface, repair/replacement
of curb and gutter, upgrading public utilities (watermain, sanitary sewer, and storm sewer) and pedestrian and traffic facility improvements.
Carbon: The Pavement Management Program implemented by the City seeks to utilize resources efficiently by performing infrastructure renewal
that will provide the greatest lifespan increase for the lowest cost. Compared to new construction projects, our roadway reconstruction projects try
to minimize disturbance and/or reuse as much of the existing facilities as possible to reduce the environmental impact. Surface water: The Living
Streets initiative reduces impervious surfaces and develops Roads, bicycle and pedestrian facilities with low impact development techniques. Green
Alternatives: Alternative construction methods utilized within the City include reclamation of existing bituminous surfaces to use as aggregate base
material, implementation of utility pipe rehabilitation through trenchless technologies thus reducing greenhouse gases associated with open cut
installations, and hydro-seeding restoration versus traditional sod placement when feasible
Project #ENG23041
Justification
The City’s mission statement is to provide effective and valued public services, maintain a sound public infrastructure, offer premier public
facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly high
quality of life enjoyed by our residents and businesses. The City’s 2020-2021 Budget Work Plan Goals 1 and 3 are: Maintain Physical Assets &
Infrastructure and Plan for Connected & Sustainable Development. Properly maintained streets, water main, sanitary sewer and storm sewer
systems provide reliable and efficient operations that lessen the City’s carbon footprint and reduce energy costs. Connected and sustainable
development includes an efficient multi-modal transportation system that balances improving personal mobility options with reducing the
community’s carbon footprint all the while reducing negative impacts on human health and safety.
Budget Impact/Other
Useful Life 50Project Name TH Tight Diamond Interchange Category Infrastructure
Type Replace or repair
Total Project Cost:$11,257,404
Total2025 2026 2027 2028 2029Expenditures 2030
11,257,40411,257,404Construction
11,257,404 11,257,404Total
Total2025 2026 2027 2028 2029Funding Sources 2030
5,007,4045,007,404Construction Fund: MSA
250,000250,000HRA Fund: Centennial Lakes
TIF
300,000300,000Utility Fund: Storm
700,000700,000Construction Fund:
Grants/Donations
300,000300,000Utility Fund: Water
300,000300,000Utility Fund: Sewer
400,000400,000PACS Fund: Utility Franchise
Fees
4,000,0004,000,000CIP Bonds
11,257,404 11,257,404Total
111
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Chad Millner
2025 2030thru Department Engineering
Description
Replacement of equipment according to the equipment replacement schedule. This includes essential equipment such as vehicles, surveying and
inspection tools, and technology, among other items.
2025:
2013 Nissan Leaf
2013 Ford F150
2012 GMC Sierra 2500 HD
2026:
2016 GMC Sierra Pickup 1500 4x4
2019 Mitsubishi Outlander
2027:
Department Furniture
2017 GMC Sierra WT
2006 JLG PSESLIFT
2017 Ford Explorer
2028:
2016 Tennant M30 or S30 Power Sweeper
2029:
2017 Toyota Prius II
2017 GMC Sierra Pickup
2030:
GS18i and CS20 GPS Unit and Controller
Project #ENG23200
Justification
As outlined in Vision Edina, it is the mission of the City Council to provide effective and valued public services and maintain a sound public
infrastructure. Regular replacement of department vehicles, surveying and inspection tools, and technology allows the city to maintain a high level
of quality service provided to the residents of the City of Edina. Timely replacement of equipment also ensures equipment reliability while keeping
maintenance costs low.
Useful LifeProject Name Engineering Equipment Replacement Category Equipment and Vehicles
Type Replace or repair
Total Project Cost:$631,331
Total2025 2026 2027 2028 2029Expenditures 2030
631,331150,000 102,631 191,500 64,700 92,500Vehicles and Equipment 30,000
150,000 102,631 191,500 64,700 92,500 631,331Total30,000
Total2025 2026 2027 2028 2029Funding Sources 2030
631,331150,000 102,631 191,500 64,700 92,500Construction Fund: Equipment
Levy
30,000
150,000 102,631 191,500 64,700 92,500 631,331Total30,000
112
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Marisa Bayer
2025 2030thru Department Engineering
Description
The project is the city’s first, city-owned fast charging station. The station will be located at Edina Public Works and Park Maintenance Facility,
providing support for Edina’s growing electric fleet.
Project #ENG25001
Justification
Expansion and/or Level of Service
Sustainability:Adding more electric vehicles to the City’s fleet is a key strategy to achieving our Climate Action Plan (CAP) goals to reduce
greenhouse gas emissions. Fast charging supports electric vehicle adoption by providing quick, convenient charging. This project specifically
supports CAP strategy TL-5.
Community Engagement: These projects encourage people to interact with staff to understand the importance of electric vehicle charging
infrastructure. Focusing on city fleet, this project does not contain an engagement component.
Health in All Policies: Electric vehicles are zero-emission vehicles, meaning there are no harmful tailpipe emissions that negatively impact air
quality.
Race & Equity: Charging stations located across the community create equitable access to infrastructure.
Stewardship: The cost to charge vehicles is decreasing and is already more cost-effective per mile to charge a vehicle when compared to gas-
powered vehicles.
Useful Life 10Project Name DC Fast Charger Category Equipment and Vehicles
Type New
Total Project Cost:$300,000
Total2025 2026 2027 2028 2029Expenditures 2030
300,000300,000Vehicles and Equipment
300,000 300,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
150,000150,000Construction Fund:
Grants/Donations
150,000150,000CAS Fund: Utility Franchise
Fees
300,000 300,000Total
113
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Chad Millner
2025 2030thru Department Engineering
Description
This project involves the reconstruction of Municipal State Aid designated Parklawn Avenue from West 76th Street to West 77th Street. This
includes replacing the entire pavement surface, repair/replacement of curb and gutter, and upgrading public utilities (watermain, sanitary sewer, and
storm sewer). The project may also include streetlight upgrades, and pedestrian, bicycle and traffic facility improvements. The project will meet
current State Aid requirements.
Project #ENG25002
Justification
Expansion and/or Level of Service
Sustainability: Carbon: The Pavement Management Program implemented by the City seeks to utilize resources efficiently by performing
infrastructure renewal that will provide the greatest lifespan increase for the lowest cost. Compared to new construction projects, our roadway
reconstruction projects minimize disturbance and/or reuse as much of the existing facilities as possible to reduce the environmental impact.
Surface water: The Living Streets initiative reduces impervious surfaces and develops roads, bicycle and pedestrian facilities with low impact
development techniques.
Green Alternatives: Alternative construction methods utilized within the City include reclamation of existing bituminous surfaces to use as
aggregate base material and implementation of utility pipe rehabilitation through trenchless technologies thus reducing greenhouse gases associated
with open cut installations.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and utility systems.
Health in All Policies
Connected and sustainable development includes an efficient multi-modal transportation system that balances improving personal mobility options
with reducing the community’s carbon footprint all the while reducing negative impacts on human health and safety.
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses.”
The City’s Budget Work Plan Goals 1 and 3 are: Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable Development.
Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient operations that lessen the City’s
carbon footprint and reduce energy costs.
Useful Life 50Project Name Parklawn Avenue A Reconstruction Category Infrastructure
Type Replace or repair
Total Project Cost:$1,360,247
Total2025 2026 2027 2028 2029Expenditures 2030
1,360,2471,360,247Construction
1,360,247 1,360,247Total
Total2025 2026 2027 2028 2029Funding Sources 2030
524,385524,385Construction Fund: MSA
48,27048,270Construction Fund: Special
Assess
226,673226,673Utility Fund: Storm
201,768201,768Utility Fund: Water
103,924103,924Utility Fund: Sewer
172,400172,400PACS Fund: Utility Franchise
Fees
82,82782,827Special Street Levy
1,360,247 1,360,247Total
114
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Chad Millner
2025 2030thru Department Engineering
Description
This project involves the reconstruction of Municipal State Aid designated West 77th Street from Parklawn Avenue to France Avenue. This
includes replacing the entire pavement surface, repair/replacement of curb and gutter, and upgrading public utilities (watermain, sanitary sewer, and
storm sewer). The project may also include streetlight upgrades, and pedestrian, bicycle and traffic facility improvements. The project will meet
current State Aid requirements.
Project #ENG25003
Justification
Expansion and/or Level of Service
Sustainability:Carbon: The Pavement Management Program implemented by the City seeks to utilize resources efficiently by performing
infrastructure renewal that will provide the greatest lifespan increase for the lowest cost. Compared to new construction projects, our roadway
reconstruction projects minimize disturbance and/or reuse as much of the existing facilities as possible to reduce the environmental impact.
Surface water: The Living Streets initiative reduces impervious surfaces and develops roads, bicycle and pedestrian facilities with low impact
development techniques.
Green Alternatives: Alternative construction methods utilized within the City include reclamation of existing bituminous surfaces to use as
aggregate base material and implementation of utility pipe rehabilitation through trenchless technologies thus reducing greenhouse gases associated
with open cut installations.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and utility systems.
Health in All Policies: Connected and sustainable development includes an efficient multi-modal transportation system that balances improving
personal mobility options with reducing the community’s carbon footprint all the while reducing negative impacts on human health and safety.
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses.
The City’s Budget Work Plan Goals 1 and 3 are: Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable Development.
Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient operations that lessen the City’s
carbon footprint and reduce energy costs.
Useful Life 50Project Name W 77th Street D Reconstruction Category Infrastructure
Type Replace or repair
Total Project Cost:$2,408,348
Total2025 2026 2027 2028 2029Expenditures 2030
2,408,3482,408,348Construction
2,408,348 2,408,348Total
Total2025 2026 2027 2028 2029Funding Sources 2030
987,078987,078Construction Fund: MSA
90,86190,861Construction Fund: Special
Assess
426,678426,678Utility Fund: Storm
379,800379,800Utility Fund: Water
195,622195,622Utility Fund: Sewer
172,400172,400PACS Fund: Utility Franchise
Fees
155,909155,909Special Street Levy
2,408,348 2,408,348Total
115
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Aaron Ditzler
2025 2030thru Department Engineering
Description
This project involves the reconstruction and rehabilitation of local streets (West 55th Street, West 56th Street, West 57th Street, Abbott Avenue,
York Avenue, Zenith Avenue) within the project area. This includes replacing the entire pavement surface, repair / replacement of curb and gutter,
and upgrading public utilities (watermain, sanitary sewer, and storm sewer). The project may also include installation of sump pump discharge
pipes, streetlight upgrades, and pedestrian and traffic facility improvements.
Project #ENG25005
Justification
Expansion and/or Level of Service
Sustainability: Carbon: The Pavement Management Program implemented by the City seeks to utilize resources efficiently by performing
infrastructure renewal that will provide the greatest lifespan increase for the lowest cost. Compared to new construction projects, our roadway
reconstruction projects minimize disturbance and/or reuse as much of the existing facilities as possible to reduce the environmental impact.
Surface water: The Living Streets initiative reduces impervious surfaces and develops roads, bicycle and pedestrian facilities with low impact
development techniques.
Green Alternatives: Alternative construction methods utilized within the City include reclamation of existing bituminous surfaces to use as
aggregate base material and implementation of utility pipe rehabilitation through trenchless technologies thus reducing greenhouse gases associated
with open cut installations.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and utility systems.
Health in All Policies: Connected and sustainable development includes an efficient multi-modal transportation system that balances improving
personal mobility options with reducing the community’s carbon footprint all the while reducing negative impacts on human health and safety.
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses.
The City’s Budget Work Plan Goals 1 and 3 are: Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable Development.
Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient operations that lessen the City’s
carbon footprint and reduce energy costs.
Useful Life 50Project Name Chowen Park C Reconstruction Category Infrastructure
Type Replace or repair
Total Project Cost:$9,237,718
Total2025 2026 2027 2028 2029Expenditures 2030
9,237,7189,237,718Construction
9,237,718 9,237,718Total
Total2025 2026 2027 2028 2029Funding Sources 2030
1,414,9911,414,991Construction Fund: Special
Assess
2,460,7762,460,776Utility Fund: Storm
2,434,7052,434,705Utility Fund: Water
929,616929,616Utility Fund: Sewer
50,00050,000PACS Fund: Utility Franchise
Fees
1,947,6301,947,630Special Street Levy
9,237,718 9,237,718Total
116
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Aaron Ditzler
2025 2030thru Department Engineering
Description
This project involves the reconstruction and rehabilitation of local streets (West 57th Street, Beard Avenue, Chowen Avenue, Drew Avenue, Ewing
Avenue) within the project area. This includes replacing the entire pavement surface, repair / replacement of curb and gutter, and upgrading public
utilities (watermain, sanitary sewer, and storm sewer). The project may also include installation of sump pump discharge pipes, streetlight
upgrades, and pedestrian and traffic facility improvements.
Project #ENG25006
Justification
Expansion and/or Level of Service
Sustainability: Carbon: The Pavement Management Program implemented by the City seeks to utilize resources efficiently by performing
infrastructure renewal that will provide the greatest lifespan increase for the lowest cost. Compared to new construction projects, our roadway
reconstruction projects minimize disturbance and/or reuse as much of the existing facilities as possible to reduce the environmental impact.
Surface water: The Living Streets initiative reduces impervious surfaces and develops roads, bicycle and pedestrian facilities with low impact
development techniques.
Green Alternatives: Alternative construction methods utilized within the City include reclamation of existing bituminous surfaces to use as
aggregate base material and implementation of utility pipe rehabilitation through trenchless technologies thus reducing greenhouse gases associated
with open cut installations.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and utility systems.
Health in All Policies: Connected and sustainable development includes an efficient multi-modal transportation system that balances improving
personal mobility options with reducing the community’s carbon footprint all the while reducing negative impacts on human health and safety.
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses.
The City’s Budget Work Plan Goals 1 and 3 are: Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable Development.
Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient operations that lessen the City’s
carbon footprint and reduce energy costs.
Useful Life 50Project Name Chowen Park E Reconstruction Category Infrastructure
Type Replace or repair
Total Project Cost:$5,860,721
Total2025 2026 2027 2028 2029Expenditures 2030
5,860,7215,860,721Construction
5,860,721 5,860,721Total
Total2025 2026 2027 2028 2029Funding Sources 2030
878,270878,270Construction Fund: Special
Assess
1,527,3781,527,378Utility Fund: Storm
1,511,1961,511,196Utility Fund: Water
577,003577,003Utility Fund: Sewer
158,000158,000PACS Fund: Utility Franchise
Fees
1,208,8741,208,874Special Street Levy
5,860,721 5,860,721Total
117
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Aaron Ditzler
2025 2030thru Department Engineering
Description
This project involves the reconstruction and rehabilitation of local streets (Brookview Avenue, Park Place, Woodcrest Drive, Woodland Road)
within the project area. This includes replacing the entire pavement surface, repair/replacement of curb and gutter, and upgrading public utilities
(watermain, sanitary sewer, and storm sewer). The project may also include installation of sump pump discharge pipes, streetlight upgrades, and
pedestrian and traffic facility improvements.
Project #ENG25009
Justification
Expansion and/or Level of Service
Sustainability: Carbon: The Pavement Management Program implemented by the City seeks to utilize resources efficiently by performing
infrastructure renewal that will provide the greatest lifespan increase for the lowest cost. Compared to new construction projects, our roadway
reconstruction projects minimize disturbance and/or reuse as much of the existing facilities as possible to reduce the environmental impact.
Surface water: The Living Streets initiative reduces impervious surfaces and develops roads, bicycle and pedestrian facilities with low impact
development techniques.
Green Alternatives: Alternative construction methods utilized within the City include reclamation of existing bituminous surfaces to use as
aggregate base material and implementation of utility pipe rehabilitation through trenchless technologies thus reducing greenhouse gases associated
with open cut installations.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and utility systems.
Health in All Policies: Connected and sustainable development includes an efficient multi-modal transportation system that balances improving
personal mobility options with reducing the community’s carbon footprint all the while reducing negative impacts on human health and safety.
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses.
The City’s Budget Work Plan Goals 1 and 3 are: Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable Development.
Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient operations that lessen the City’s
carbon footprint and reduce energy costs.
Useful Life 50Project Name Minnehaha Woods B Reconstruction Category Infrastructure
Type Replace or repair
Total Project Cost:$4,119,420
Total2025 2026 2027 2028 2029Expenditures 2030
4,119,4204,119,420Construction
4,119,420 4,119,420Total
Total2025 2026 2027 2028 2029Funding Sources 2030
618,632618,632Construction Fund: Special
Assess
1,282,7071,282,707Utility Fund: Storm
692,075692,075Utility Fund: Water
464,487464,487Utility Fund: Sewer
1,061,5191,061,519Special Street Levy
4,119,420 4,119,420Total
118
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Aaron Ditzler
2025 2030thru Department Engineering
Description
Pamela Park B (Peacedale Avenue)This project involves the reconstruction and rehabilitation of local street Peacedale Avenue from the Highway
62 frontage road to West 62nd Street. This includes replacing the entire pavement surface, repair/replacement of curb and gutter, and upgrading
public utilities (watermain, sanitary sewer, and storm sewer). The project may also include installation of sump pump discharge pipes, streetlight
upgrades, and pedestrian and traffic facility improvements.
Project #ENG25010
Justification
Expansion and/or Level of Service
Sustainability: Carbon: The Pavement Management Program implemented by the City seeks to utilize resources efficiently by performing
infrastructure renewal that will provide the greatest lifespan increase for the lowest cost. Compared to new construction projects, our roadway
reconstruction projects minimize disturbance and/or reuse as much of the existing facilities as possible to reduce the environmental impact.
Surface water: The Living Streets initiative reduces impervious surfaces and develops roads, bicycle and pedestrian facilities with low impact
development techniques.
Green Alternatives: Alternative construction methods utilized within the City include reclamation of existing bituminous surfaces to use as
aggregate base material and implementation of utility pipe rehabilitation through trenchless technologies thus reducing greenhouse gases associated
with open cut installations.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and utility systems.
Health in All Policies: Connected and sustainable development includes an efficient multi-modal transportation system that balances improving
personal mobility options with reducing the community’s carbon footprint all the while reducing negative impacts on human health and safety.
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses.
The City’s Budget Work Plan Goals 1 and 3 are: Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable Development.
Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient operations that lessen the City’s
carbon footprint and reduce energy costs.
Useful Life 50Project Name Pamela Park B (Peacdale Avenue) Reconstruction Category Infrastructure
Type Replace or repair
Total Project Cost:$1,815,098
Total2025 2026 2027 2028 2029Expenditures 2030
1,815,0981,815,098Construction
1,815,098 1,815,098Total
Total2025 2026 2027 2028 2029Funding Sources 2030
250,399250,399Construction Fund: Special
Assess
454,631454,631Utility Fund: Storm
492,398492,398Utility Fund: Water
188,007188,007Utility Fund: Sewer
429,663429,663Special Street Levy
1,815,098 1,815,098Total
119
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Aaron Ditzler
2025 2030thru Department Engineering
Description
This project involves the reconstruction and rehabilitation of local street Halifax Avenue from the Highway 62 frontage road to West 62nd Street.
This includes replacing the entire pavement surface, repair/replacement of curb and gutter, and upgrading public utilities (watermain, sanitary
sewer, and storm sewer). The project may also include installation of sump pump discharge pipes, streetlight upgrades, and pedestrian and traffic
facility improvements.
Project #ENG25011
Justification
Expansion and/or Level of Service
Sustainability: Carbon: The Pavement Management Program implemented by the City seeks to utilize resources efficiently by performing
infrastructure renewal that will provide the greatest lifespan increase for the lowest cost. Compared to new construction projects, our roadway
reconstruction projects minimize disturbance and/or reuse as much of the existing facilities as possible to reduce the environmental impact.
Surface water: The Living Streets initiative reduces impervious surfaces and develops roads, bicycle and pedestrian facilities with low impact
development techniques.
Green Alternatives: Alternative construction methods utilized within the City include reclamation of existing bituminous surfaces to use as
aggregate base material and implementation of utility pipe rehabilitation through trenchless technologies thus reducing greenhouse gases associated
with open cut installations.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and utility systems.
Health in All Policies: Connected and sustainable development includes an efficient multi-modal transportation system that balances improving
personal mobility options with reducing the community’s carbon footprint all the while reducing negative impacts on human health and safety.
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses.
The City’s Budget Work Plan Goals 1 and 3 are: Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable Development.
Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient operations that lessen the City’s
carbon footprint and reduce energy costs.
Useful Life 50Project Name Pamela Park C (Halifax Avenue) Reconstruction Category Infrastructure
Type Replace or repair
Total Project Cost:$1,388,016
Total2025 2026 2027 2028 2029Expenditures 2030
1,388,0161,388,016Construction
1,388,016 1,388,016Total
Total2025 2026 2027 2028 2029Funding Sources 2030
191,481191,481Construction Fund: Special
Assess
347,659347,659Utility Fund: Storm
376,540376,540Utility Fund: Water
143,770143,770Utility Fund: Sewer
328,566328,566Special Street Levy
1,388,016 1,388,016Total
120
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Aaron Ditzler
2025 2030thru Department Engineering
Description
This project involves the reconstruction and rehabilitation of local street Washington Avenue from Valley View Road to the City limits north of
Valley View Road, which is a shared street with the City of Eden Prairie. This includes replacing the entire pavement surface, repair/replacement of
curb and gutter, and upgrading public utilities (watermain, sanitary sewer, and storm sewer). The project may also include installation of sump
pump discharge pipes, streetlight upgrades, and pedestrian and traffic facility improvements.
Project #ENG25012
Justification
Expansion and/or Level of Service
Sustainability: Carbon: The Pavement Management Program implemented by the City seeks to utilize resources efficiently by performing
infrastructure renewal that will provide the greatest lifespan increase for the lowest cost. Compared to new construction projects, our roadway
reconstruction projects minimize disturbance and/or reuse as much of the existing facilities as possible to reduce the environmental impact.
Surface water: The Living Streets initiative reduces impervious surfaces and develops roads, bicycle and pedestrian facilities with low impact
development techniques.
Green Alternatives: Alternative construction methods utilized within the City include reclamation of existing bituminous surfaces to use as
aggregate base material and implementation of utility pipe rehabilitation through trenchless technologies thus reducing greenhouse gases associated
with open cut installations.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and utility systems.
Health in All Policies: Connected and sustainable development includes an efficient multi-modal transportation system that balances improving
personal mobility options with reducing the community’s carbon footprint all the while reducing negative impacts on human health and safety.
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses.
The City’s Budget Work Plan Goals 1 and 3 are: Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable Development.
Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient operations that lessen the City’s
carbon footprint and reduce energy costs.
Useful Life 50Project Name Braemar Hills E (Washington Avenue) Reconstruction Category Infrastructure
Type Replace or repair
Total Project Cost:$964,181
Total2025 2026 2027 2028 2029Expenditures 2030
964,181Construction964,181
964,181Total964,181
Total2025 2026 2027 2028 2029Funding Sources 2030
172,485Construction Fund: Special
Assess
172,485
332,148Utility Fund: Storm 332,148
51,164Utility Fund: Water 51,164
34,339Utility Fund: Sewer 34,339
374,045Special Street Levy 374,045
964,181Total964,181
121
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Aaron Ditzler
2025 2030thru Department Engineering
Description
This project involves the reconstruction and rehabilitation of local streets (West 66th Street, Cahill Lane, Cahill Road, Galway Drive, Hillside
Lane, Limerick Lane) within the project area. This includes replacing the entire pavement surface, repair/replacement of curb and gutter, and
upgrading public utilities (watermain, sanitary sewer, and storm sewer). The project may also include installation of sump pump discharge pipes,
streetlight upgrades, and pedestrian and traffic facility improvements.
Project #ENG25013
Justification
Expansion and/or Level of Service
Sustainability: Carbon: The Pavement Management Program implemented by the City seeks to utilize resources efficiently by performing
infrastructure renewal that will provide the greatest lifespan increase for the lowest cost. Compared to new construction projects, our roadway
reconstruction projects minimize disturbance and/or reuse as much of the existing facilities as possible to reduce the environmental impact.
Surface water: The Living Streets initiative reduces impervious surfaces and develops roads, bicycle and pedestrian facilities with low impact
development techniques.
Green Alternatives: Alternative construction methods utilized within the City include reclamation of existing bituminous surfaces to use as
aggregate base material and implementation of utility pipe rehabilitation through trenchless technologies thus reducing greenhouse gases associated
with open cut installations.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and utility systems.
Health in All Policies: Connected and sustainable development includes an efficient multi-modal transportation system that balances improving
personal mobility options with reducing the community’s carbon footprint all the while reducing negative impacts on human health and safety.
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses.
The City’s Budget Work Plan Goals 1 and 3 are: Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable Development.
Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient operations that lessen the City’s
carbon footprint and reduce energy costs.
Useful Life 50Project Name The Heights A Reconstruction Category Infrastructure
Type Replace or repair
Total Project Cost:$9,343,836
Total2025 2026 2027 2028 2029Expenditures 2030
9,343,836Construction9,343,836
9,343,836Total9,343,836
Total2025 2026 2027 2028 2029Funding Sources 2030
1,127,030Construction Fund: Special
Assess
1,127,030
2,370,717Utility Fund: Storm 2,370,717
2,248,376Utility Fund: Water 2,248,376
858,472Utility Fund: Sewer 858,472
295,200PACS Fund: Utility Franchise
Fees
295,200
2,444,041Special Street Levy 2,444,041
9,343,836Total9,343,836
122
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Aaron Ditzler
2025 2030thru Department Engineering
Description
This project involves the reconstruction and rehabilitation of local streets (West 66th Street, West 68th Street, Grace Terrace, Hillside Circle,
Hillside Court, Lois Lane, Susan Avenue, Tracy Avenue) within the project area. This includes replacing the entire pavement surface,
repair/replacement of curb and gutter, and upgrading public utilities (watermain, sanitary sewer, and storm sewer). The project may also include
installation of sump pump discharge pipes, streetlight upgrades, and pedestrian and traffic facility improvements.
Project #ENG25014
Justification
Expansion and/or Level of Service
Sustainability: Carbon: The Pavement Management Program implemented by the City seeks to utilize resources efficiently by performing
infrastructure renewal that will provide the greatest lifespan increase for the lowest cost. Compared to new construction projects, our roadway
reconstruction projects minimize disturbance and/or reuse as much of the existing facilities as possible to reduce the environmental impact.
Surface water: The Living Streets initiative reduces impervious surfaces and develops roads, bicycle and pedestrian facilities with low impact
development techniques.
Green Alternatives: Alternative construction methods utilized within the City include reclamation of existing bituminous surfaces to use as
aggregate base material and implementation of utility pipe rehabilitation through trenchless technologies thus reducing greenhouse gases associated
with open cut installations.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and utility systems.
Health in All Policies: Connected and sustainable development includes an efficient multi-modal transportation system that balances improving
personal mobility options with reducing the community’s carbon footprint all the while reducing negative impacts on human health and safety.
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses.
The City’s Budget Work Plan Goals 1 and 3 are: Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable Development.
Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient operations that lessen the City’s
carbon footprint and reduce energy costs.
Useful Life 50Project Name The Heights C Reconstruction Category Infrastructure
Type Replace or repair
Total Project Cost:$7,590,070
Total2025 2026 2027 2028 2029Expenditures 2030
7,590,070Construction7,590,070
7,590,070Total7,590,070
Total2025 2026 2027 2028 2029Funding Sources 2030
939,192Construction Fund: Special
Assess
939,192
1,729,936Utility Fund: Storm 1,729,936
1,873,647Utility Fund: Water 1,873,647
715,394Utility Fund: Sewer 715,394
295,200PACS Fund: Utility Franchise
Fees
295,200
2,036,701Special Street Levy 2,036,701
7,590,070Total7,590,070
123
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Aaron Ditzler
2025 2030thru Department Engineering
Description
The multi-tiered retaining wall has a history of small area failures. Each failure requires a small contract with a vendor to patch together at the
location of the failure. This project will remove and replace the entire wall with a large modular block wall system.
Project #ENG25018
Justification
Health, Safety & Regulatory Compliance
Sustanability: The City seeks to utilize resources efficiently by performing infrastructure renewal that will provide the greatest lifespan increase for
the lowest cost. Compared to new construction projects, rehabilitation projects try to minimize disturbance and/or reuse as much of the existing
facilities as possible to reduce the environmental impact.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and utility systems.
Health in All Policies: Connected and sustainable development includes an efficient multi-modal transportation system that balances improving
personal mobility options with reducing the community’s carbon footprint all the while reducing negative impacts on human health and safety.
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses.
The City’s Budget Work Plan Goals 1 and 3 are: Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable Development.
Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient operations that lessen the City’s
carbon footprint and reduce energy costs.
Useful Life 50Project Name 6932 Valley View Road Multi-Tiered Retaining Wall Category Infrastructure
Type Replace or repair
Total Project Cost:$360,000
Total2025 2026 2027 2028 2029Expenditures 2030
360,000360,000Construction
360,000 360,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
360,000360,000Bridge Maintenance
360,000 360,000Total
124
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Chad Millner
2025 2030thru Department Engineering
Description
The material around the railroad tracks along Dewey Hill Road that provides a smooth transition from the street pavement over the railroad tracks
is starting to fail. The city is responsible for providing the materials to CP Rail for their crews to install.
Project #ENG25020
Justification
Health, Safety & Regulatory Compliance
Sustanability: The City seeks to utilize resources efficiently by performing infrastructure renewal that will provide the greatest lifespan increase for
the lowest cost. Compared to new construction projects, rehabilitation projects try to minimize disturbance and/or reuse as much of the existing
facilities as possible to reduce the environmental impact.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and utility systems.
Health in All Policies: Connected and sustainable development includes an efficient multi-modal transportation system that balances improving
personal mobility options with reducing the community’s carbon footprint all the while reducing negative impacts on human health and safety.
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses.
The City’s Budget Work Plan Goals 1 and 3 are: Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable Development.
Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient operations that lessen the City’s
carbon footprint and reduce energy costs.
Useful Life 50Project Name Dewey Hill Road CP Rail Crossing Category Infrastructure
Type Replace or repair
Total Project Cost:$35,000
Total2025 2026 2027 2028 2029Expenditures 2030
35,00035,000Construction
35,000 35,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
35,00035,000Bridge Maintenance
35,000 35,000Total
125
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Chad Millner
2025 2030thru Department Engineering
Description
The project will create an ADA pedestrian access route from the new Grandview Pedestrian Bridge across the top level of the Grandview Parking
Ramp. It will create a route for users to access Jerry’s Tower that has an elevator. The elevator would be accessible during normal business hours.
Coordination with Jerry’s Enterprise is needed to discuss the impact of losing 16 parking stalls and maintenance and operations responsibilities.
Project #ENG25021
Justification
Health, Safety & Regulatory Compliance
Sustanability: The City seeks to utilize resources efficiently by performing infrastructure renewal that will provide the greatest lifespan increase for
the lowest cost. Compared to new construction projects, rehabilitation projects try to minimize disturbance and/or reuse as much of the existing
facilities as possible to reduce the environmental impact.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and utility systems.
Health in All Policies: Connected and sustainable development includes an efficient multi-modal transportation system that balances improving
personal mobility options with reducing the community’s carbon footprint all the while reducing negative impacts on human health and safety.
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses.
The City’s Budget Work Plan Goals 1 and 3 are: Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable Development.
Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient operations that lessen the City’s
carbon footprint and reduce energy costs.
Useful Life 50Project Name Grandview Parking Ramp ADA Access Route Category Infrastructure
Type New
Total Project Cost:$200,000
Total2025 2026 2027 2028 2029Expenditures 2030
200,000200,000Construction
200,000 200,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
200,000200,000Construction Fund: CIP Levy
200,000 200,000Total
126
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Chad Millner
2025 2030thru Department Engineering
Description
The project will create an ADA pedestrian access route from the new Grandview Pedestrian Bridge across the top level of the Grandview Parking
Ramp. It will create a route for users to access Jerry’s Tower that has an elevator. The elevator would be accessible during normal business hours.
Coordination with Jerry’s Enterprise is needed to discuss the impact of losing 16 parking stalls and maintenance and operations responsibilities.
Project #ENG25022
Justification
Health, Safety & Regulatory Compliance
Sustanability: The City seeks to utilize resources efficiently by performing infrastructure renewal that will provide the greatest lifespan increase for
the lowest cost. Compared to new construction projects, rehabilitation projects try to minimize disturbance and/or reuse as much of the existing
facilities as possible to reduce the environmental impact.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and utility systems.
Health in All Policies: Connected and sustainable development includes an efficient multi-modal transportation system that balances improving
personal mobility options with reducing the community’s carbon footprint all the while reducing negative impacts on human health and safety.
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses.
The City’s Budget Work Plan Goals 1 and 3 are: Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable Development.
Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient operations that lessen the City’s
carbon footprint and reduce energy costs.
Useful Life 50Project Name Grandview Parking Ramp ADA Access Route to Gus Yng Category Infrastructure
Type New
Total Project Cost:$2,000,000
Total2025 2026 2027 2028 2029Expenditures 2030
2,000,0002,000,000Construction
2,000,000 2,000,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
2,000,0002,000,000Construction Fund: CIP Levy
2,000,000 2,000,000Total
127
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Chad Millner
2025 2030thru Department Engineering
Description
The project will replace 2,500 linear feet of 8-ft tall wood fence that is at the end of its useful life. The fence was installed in 1994. It has many
trees, shrubs and other vegetation growing in and around it that increases the difficulty of replacement.
Project #ENG25023
Justification
Expansion and/or Level of Service
Sustanability: The City seeks to utilize resources efficiently by performing infrastructure renewal that will provide the greatest lifespan increase for
the lowest cost. Compared to new construction projects, rehabilitation projects try to minimize disturbance and/or reuse as much of the existing
facilities as possible to reduce the environmental impact.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and utility systems.
Health in All Policies: These projects continue to provide a physical barrier between private property and the vehicle traveled way. This separation
creates a safter environment for the individual property owners.
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses.
The City’s Budget Work Plan Goals 1 and 3 are: Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable Development.
Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient operations that lessen the City’s
carbon footprint and reduce energy costs.
Useful Life 25Project Name Valley View Rd Fence Replace Sdale Neighborhood Category Infrastructure
Type Replace or repair
Total Project Cost:$100,000
Total2025 2026 2027 2028 2029Expenditures 2030
100,000100,000Construction
100,000 100,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
100,000100,000Construction Fund: MSA
100,000 100,000Total
128
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Chad Millner
2025 2030thru Department Engineering
Description
The project will create a pedestrian connection under France Avenue between Gallagher Drive and 72nd Street. It will extend into potential
development projects on both the east and west sides of France Avenue. It will provide much safer pedestrian access on the east and west sides of
France Avenue to Centennial Lakes Park and the Cornelia Neighborhood.
Project #ENG25025
Justification
Expansion and/or Level of Service
Sustainability:Carbon: The Pavement Management Program implemented by the City seeks to utilize resources efficiently by performing
infrastructure renewal that will provide the greatest lifespan increase for the lowest cost. Compared to new construction projects, our roadway
reconstruction projects try to minimize disturbance and/or reuse as much of the existing facilities as possible to reduce the environmental impact.
Surface water: The Living Streets initiative reduces impervious surfaces and develops roads, bicycle and pedestrian facilities with low impact
development techniques.
Green Alternatives: Alternative construction methods utilized within the City include reclamation of existing bituminous surfaces to use as
aggregate base material and implementation of utility pipe rehabilitation through trenchless technologies thus reducing greenhouse gases associated
with open cut installations.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and utility systems.
Health in All Policies: Connected and sustainable development includes an efficient multi-modal transportation system that balances improving
personal mobility options with reducing the community’s carbon footprint all the while reducing negative impacts on human health and safety.
Race & Equity: Connected and sustainable development includes an efficient multi-modal transportation system that balances improving personal
mobility options with reducing the community’s carbon footprint all the while reducing negative impacts on human health and safety.
Stewardship: The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses.”
The City’s Budget Work Plan Goals 1 and 3 are: Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable Development.
Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient operations that lessen the City’s
carbon footprint and reduce energy costs.
Useful Life 75Project Name France Avenue Crossing Gallagher & 72nd Category Infrastructure
Type New
Total Project Cost:$16,000,000
Total2025 2026 2027 2028 2029Expenditures 2030
16,000,000500,000 1,500,000 7,000,000 7,000,000Construction
500,000 1,500,000 7,000,000 7,000,000 16,000,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
16,000,000500,000 1,500,000 7,000,000 7,000,000HRA Fund: Centennial Lakes
TIF
500,000 1,500,000 7,000,000 7,000,000 16,000,000Total
129
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Chad Millner
2025 2030thru Department Engineering
Description
Project #ENG25026
Justification
Health, Safety & Regulatory Compliance
Sustainability: Carbon: The Pavement Management Program implemented by the City seeks to utilize resources efficiently by performing
infrastructure renewal that will provide the greatest lifespan increase for the lowest cost. Compared to new construction projects, our roadway
reconstruction projects try to minimize disturbance and/or reuse as much of the existing facilities as possible to reduce the environmental impact.
Surface water: The Living Streets initiative reduces impervious surfaces and develops roads, bicycle and pedestrian facilities with low impact
development techniques.
Green Alternatives: Alternative construction methods utilized within the City include reclamation of existing bituminous surfaces to use as
aggregate base material and implementation of utility pipe rehabilitation through trenchless technologies thus reducing greenhouse gases associated
with open cut installations.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and utility systems.
Health in All Policies: Connected and sustainable development includes an efficient multi-modal transportation system that balances improving
personal mobility options with reducing the community’s carbon footprint all the while reducing negative impacts on human health and safety.
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses.”
The City’s Budget Work Plan Goals 1 and 3 are: Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable Development.
Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient operations that lessen the City’s
carbon footprint and reduce energy costs.
Useful Life 75Project Name Rosland Park Pedestrian Bridge Category Infrastructure
Type New
Total Project Cost:$6,000,000
Total2025 2026 2027 2028 2029Expenditures 2030
6,000,0006,000,000Construction
6,000,000 6,000,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
6,000,0006,000,000Construction Fund:
Grants/Donations
6,000,000 6,000,000Total
130
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Chad Millner
2025 2030thru Department Engineering
Description
The project will replace 1,300 linear feet of concrete curb and gutter in the 50th and France District along 50th Street between Halifax Avenue and
France Avenue. The curb is at the end of its useful life. This work will be coordinated with a mill and overlay project.
Project #ENG25027
Justification
Expansion and/or Level of Service
Sustainability:The City seeks to utilize resources efficiently by performing infrastructure renewal that will provide the greatest lifespan increase for
the lowest cost. Compared to new construction projects, our roadway reconstruction projects try to minimize disturbance and/or reuse as much of
the existing facilities as possible to reduce the environmental impact.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and utility systems.
Health in All Policies: Connected and sustainable development includes an efficient multi-modal transportation system that balances improving
personal mobility options with reducing the community’s carbon footprint all the while reducing negative impacts on human health and safety.
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses."
The City’s Budget Work Plan Goals 1 and 3 are: Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable Development.
Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient operations that lessen the City’s
carbon footprint and reduce energy costs.
Useful Life 75Project Name 50th St Concrete Curb and Gutter Replacement Category Infrastructure
Type Replace or repair
Total Project Cost:$55,000
Total2025 2026 2027 2028 2029Expenditures 2030
55,00055,000Construction
55,000 55,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
55,00055,000Utility Fund: Storm
55,000 55,000Total
131
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Chad Millner
2025 2030thru Department Engineering
Description
The traffic signal poles and bolt connections to the structural foundations are rusting and are nearing the end of their useful life. This project will
install a new traffic control signal system.
Project #ENG25028
Justification
Health, Safety, and Regulatory Compliance
Sustainability:The City seeks to utilize resources efficiently by performing infrastructure renewal that will provide the greatest lifespan increase for
the lowest cost. Compared to new construction projects, our roadway reconstruction projects try to minimize disturbance and/or reuse as much of
the existing facilities as possible to reduce the environmental impact.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and utility systems.
Health in All Policies: Connected and sustainable development includes an efficient multi-modal transportation system that balances improving
personal mobility options with reducing the community’s carbon footprint all the while reducing negative impacts on human health and safety.
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses."
The City’s Budget Work Plan Goals 1 and 3 are: Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable Development.
Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient operations that lessen the City’s
carbon footprint and reduce energy costs.
Useful LifeProject Name Traffic Signal at Halifax and 50th St Category Infrastructure
Type Replace or repair
Total Project Cost:$400,000
Total2025 2026 2027 2028 2029Expenditures 2030
400,000400,000Construction
400,000 400,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
400,000400,000Construction Fund: MSA
400,000 400,000Total
132
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Chad Millner
2025 2030thru Department Engineering
Description
The retaining wall along the north side of the 50th Street Bridge over Minnehaha Creek is starting to separate from the structure. This project will
remove and replace the retaining wall.
Project #ENG25029
Justification
Health, Safety and Regulatory Compliance
Sustainability: The City seeks to utilize resources efficiently by performing infrastructure renewal that will provide the greatest lifespan increase for
the lowest cost. Compared to new construction projects, rehabilitation projects try to minimize disturbance and/or reuse as much of the existing
facilities as possible to reduce the environmental impact.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and utility systems.
Health in All Policies: Connected and sustainable development includes an efficient multi-modal transportation system that balances improving
personal mobility options with reducing the community’s carbon footprint all the while reducing negative impacts on human health and safety.
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses.”
The City’s Budget Work Plan Goals 1 and 3 are: Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable Development.
Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient operations that lessen the City’s
carbon footprint and reduce energy costs.
Useful Life 50Project Name 50th over Minnehaha Creek North Retaining Wall Category Infrastructure
Type Replace or repair
Total Project Cost:$275,000
Total2025 2026 2027 2028 2029Expenditures 2030
275,000275,000Construction
275,000 275,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
275,000275,000Construction Fund: MSA
275,000 275,000Total
133
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Chad Millner
2025 2030thru Department Engineering
Description
The Benton Ave Bridge over CP Rail has maintenance needs. The beams under the deck are due for painting to extend the life of the structure.
Project #ENG25030
Justification
Health, Safety & Regulatory Compliance
Sustainability: The City seeks to utilize resources efficiently by performing infrastructure renewal that will provide the greatest lifespan increase for
the lowest cost. Compared to new construction projects, rehabilitation projects try to minimize disturbance and/or reuse as much of the existing
facilities as possible to reduce the environmental impact.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and utility systems.
Health in All Policies: Connected and sustainable development includes an efficient multi-modal transportation system that balances improving
personal mobility options with reducing the community’s carbon footprint all the while reducing negative impacts on human health and safety.
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses.”
The City’s Budget Work Plan Goals 1 and 3 are: Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable Development.
Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient operations that lessen the City’s
carbon footprint and reduce energy costs.
Useful Life 50Project Name Benton Avenue Over CP Rail Beam Painting Category Infrastructure
Type Replace or repair
Total Project Cost:$250,000
Total2025 2026 2027 2028 2029Expenditures 2030
250,000Construction250,000
250,000Total250,000
Total2025 2026 2027 2028 2029Funding Sources 2030
250,000Construction Fund: MSA 250,000
250,000Total250,000
134
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Chad Millner
2025 2030thru Department Engineering
Description
The Valley View Bridge over CP Rail has maintenance needs. The beams under the deck are due for painting to extend the life of the structure.
Project #ENG25031
Justification
Health, Safety & Regulatory Compliance
Sustainability: The City seeks to utilize resources efficiently by performing infrastructure renewal that will provide the greatest lifespan increase for
the lowest cost. Compared to new construction projects, rehabilitation projects try to minimize disturbance and/or reuse as much of the existing
facilities as possible to reduce the environmental impact.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and utility systems.
Health in All Policies: Connected and sustainable development includes an efficient multi-modal transportation system that balances improving
personal mobility options with reducing the community’s carbon footprint all the while reducing negative impacts on human health and safety.
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses.”
The City’s Budget Work Plan Goals 1 and 3 are: Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable Development.
Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient operations that lessen the City’s
carbon footprint and reduce energy costs.
Useful Life 50Project Name Valley View Road Bridge over CP Rail Beam Painting Category Infrastructure
Type Replace or repair
Total Project Cost:$250,000
Total2025 2026 2027 2028 2029Expenditures 2030
250,000Construction250,000
250,000Total250,000
Total2025 2026 2027 2028 2029Funding Sources 2030
250,000Construction Fund: MSA 250,000
250,000Total250,000
135
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Chad Millner
2025 2030thru Department Engineering
Description
The project will cure in place line 3,400 linear feet of clay sanitary sewer pipe. This type of trenchless rehabilitation technology only needs access
to the manholes for installation. It does not require large scale open cutting operations. It builds a long-term structural pipe within the existing pipe.
Project #ENG25033
Justification
Expansion and/or Level of Service
Sustainability: Infiltration and inflow required the Lift Station pumps to run much more often to lift the sewage and infiltration into the next gravity
sewer main.
Elimination of this inflow will use less energy.
Alternative construction methods utilized within the City include implementation of utility pipe rehabilitation through trenchless technologies thus
reducing greenhouse gases associated with open cut installations where applicable.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and utility systems.
Health in All Policies: These projects provide the City's sewer customers with safe, reliable, and efficient removal of wastewater for residents and
customers in the City of Edina, while eliminating risk of inflow, infiltration, and backflow to protect the health, safety, and welfare of our citizens
now and into the future.
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses.”
The City’s Budget Work Plan Goals 1 and 3 are: Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable Development.
Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient operations that lessen the City’s
carbon footprint and reduce energy costs.
Useful Life 75Project Name Nine Mile Village Sanitary Sewer Lining Category Infrastructure
Type Replace or repair
Total Project Cost:$175,000
Total2025 2026 2027 2028 2029Expenditures 2030
175,000175,000Construction
175,000 175,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
175,000175,000Utility Fund: Sewer
175,000 175,000Total
136
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Chad Millner
2025 2030thru Department Engineering
Description
The project will replace approximately 130 linear feet of sanitary sewer pipe that has settled and created a sag in the pipe. The sag slows flow and
collects debris. The pipe will be replaced by open cut method and along with impacted street pavements
Project #ENG25034
Justification
Expansion and/or Level of Service
Sustainability: Infiltration and inflow required the Lift Station pumps to run much more often to lift the sewage and infiltration into the next gravity
sewer main.
Elimination of this inflow will use less energy.
Alternative construction methods utilized within the City include implementation of utility pipe rehabilitation through trenchless technologies thus
reducing greenhouse gases associated with open cut installations where applicable.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and utility systems.
Health in All Policies: These projects provide the City's sewer customers with safe, reliable, and efficient removal of wastewater for residents and
customers in the City of Edina, while eliminating risk of inflow, infiltration, and backflow to protect the health, safety, and welfare of our citizens
now and into the future.
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses.”
The City’s Budget Work Plan Goals 1 and 3 are: Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable Development.
Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient operations that lessen the City’s
carbon footprint and reduce energy costs.
Useful Life 75Project Name Olinger Road Sanitary Sewer Replacement Category Infrastructure
Type Replace or repair
Total Project Cost:$100,000
Total2025 2026 2027 2028 2029Expenditures 2030
100,000100,000Construction
100,000 100,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
100,000100,000Utility Fund: Sewer
100,000 100,000Total
137
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Ross Bintner
2025 2030thru Department Engineering
Description
"This project will use iron and aluminum chemical additions to sequester the sediment phosphorus that causes algae blooms and fuels lake and
creek water quality impairments. The project will work citywide in priority watersheds. The work is an implementation step of the Clean
Water Strategy (CWS), to promote a healthy ecosystem equilibrium where waters are clear, safe and accessible.Decades of urban development
and runoff have lead to waterbodies with nutrient rich sediment. The sediment phosphorus fuels aerobic and anerobic decay of accumulated
biomass and leads to low oxygen levels and phosphorus release into the water column that impairing waters. This project begins restore ecological
processes by resetting the sequestering the sediment phosphorus. "
Project #ENG25036
Justification
Expansion and/or Level of Service
Useful LifeProject Name CWS 1 - Lake & Pond Sediment Phosphorus Sequest Category Infrastructure
Type New
Total Project Cost:$550,000
Total2025 2026 2027 2028 2029Expenditures 2030
550,00050,000 100,000 100,000 100,000 100,000Installation/Maintenance 100,000
50,000 100,000 100,000 100,000 100,000 550,000Total100,000
Total2025 2026 2027 2028 2029Funding Sources 2030
550,00050,000 100,000 100,000 100,000 100,000Utility Fund: Storm 100,000
50,000 100,000 100,000 100,000 100,000 550,000Total100,000
138
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Ross Bintner
2025 2030thru Department Engineering
Description
"This project will prevent pollution at and near their source on the roads draining to priority waters. Targeted intensive street sweeping is one of
the most effective interventions cities can make to promote clean waters. Cleaner streets = cleaner water. The project will work citywide in
priority watersheds. The work is an implementation step of the Clean Water Strategy (CWS), to promote a healthy ecosystem equilibrium
where waters are clear, safe and accessible. Urban development with curb and gutter speeds water and accumulated pollutants like sediment,
phosphorus and nitrogen downstream to waters where it accumulates causing water quality impairments. Sweeping removes the pollutants at and
near their source before they have a chance to break down and make their way into waters."
Project #ENG25037
Justification
Expansion and/or Level of Service
Useful LifeProject Name CWS 2 - Targeted Intensive Street Sweeping Category Infrastructure
Type New
Total Project Cost:$100,000
Total2025 2026 2027 2028 2029Expenditures 2030
100,00010,000 20,000 70,000Installation/Maintenance
10,000 20,000 70,000 100,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
100,00010,000 20,000 70,000Utility Fund: Storm
10,000 20,000 70,000 100,000Total
139
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Jessica Wilson
2025 2030thru Department Engineering
Description
This project will coordinate with local watersheds and/or the Met Council to expand the network of monitoring for trends in waterbody
health.The work is an implementation step of the Clean Water Strategy (CWS) the values and goals of which include;City actions align to do
the most good towards measurable, desirable clean water outcomes leveraging creativity and innovation.•The city uses an iterative ‘build, test,
learn’ model to make progress.•The city uses a systems approach in its implementation to consider cumulative benefits.•Clean water goals are
pursued with consideration for multiple benefits and available resources.By tracking trends in close partnership with local water agencies, the
City can better align and target its work for greater effect.
Project #ENG25038
Justification
Expansion and/or Level of Service
Useful LifeProject Name CWS 3 - Assurance, Monitoring, Lakegrades Category Infrastructure
Type New
Total Project Cost:$215,000
Total2025 2026 2027 2028 2029Expenditures 2030
215,00040,000 35,000 35,000 35,000 35,000Installation/Maintenance 35,000
40,000 35,000 35,000 35,000 35,000 215,000Total35,000
Total2025 2026 2027 2028 2029Funding Sources 2030
215,00040,000 35,000 35,000 35,000 35,000Utility Fund: Storm 35,000
40,000 35,000 35,000 35,000 35,000 215,000Total35,000
140
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Jessica Wilson
2025 2030thru Department Engineering
Description
This project will control rough fish like carp and hybrid goldfish to reduce their harmful effects on clean water. The work is an implementation
step of the Clean Water Strategy (CWS), to promote a healthy ecosystem equilibrium where waters are clear, safe and accessible. Rough fish
feed and stir up bottom sediments releasing accumulated pollutants into the water column causing algae blooms and water quality impairments.
Project #ENG25039
Justification
Expansion and/or Level of Service
Useful LifeProject Name CWS 4 - Rough Fish Management Category Infrastructure
Type New
Total Project Cost:$190,000
Total2025 2026 2027 2028 2029Expenditures 2030
190,00030,000 40,000 40,000 40,000Installation/Maintenance 40,000
30,000 40,000 40,000 40,000 190,000Total40,000
Total2025 2026 2027 2028 2029Funding Sources 2030
190,00030,000 40,000 40,000 40,000Utility Fund: Storm 40,000
30,000 40,000 40,000 40,000 190,000Total40,000
141
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Ross Bintner
2025 2030thru Department Engineering
Description
This project will mitigate pollution in the stormwater systems draining to priority waters. While not as cost competitive as some of the in-
waterbody and pollution control work in CWS 1,2, and 4, Clean water infrastructure can work in combination with these practices to further reduce
water pollutants.The work is an implementation step of the Clean Water Strategy (CWS), to promote a healthy ecosystem equilibrium where
waters are clear, safe and accessible. The project will work citywide in priority watersheds. Urban development with curb and gutter speeds
water and accumulated pollutants like sediment, phosphorus and nitrogen downstream to waters where it accumulates causing water quality
impairments. Clean water infrastructure intercepts the water, and filters, settles, or adsorbs pollutants to sequester them so they can be removed by
a maintenance action and properly disposes or reuses them.
Project #ENG25040
Justification
Expansion and/or Level of Service
Useful LifeProject Name CWS 5 - New Clean Water Infrastructure Category Infrastructure
Type New
Total Project Cost:$150,000
Total2025 2026 2027 2028 2029Expenditures 2030
150,000150,000Installation/Maintenance
150,000 150,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
150,000150,000Utility Fund: Storm
150,000 150,000Total
142
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Chad Millner
2025 2030thru Department Engineering
Description
The project will rehabilitate approximately 1,200 linear feet of watermain pipe along Chapel Drive between Chapel Lane and Antrim Road. The
pipes are located under the streets. The pipes are breaking at high frequencies and need rehabilitation. It is anticipated that the project will use the
cured-in-place pipe rehabilitation method.
Project #ENG25043
Justification
Expansion and/or Level of Service
Sustainability: Alternative construction methods utilized within the City include implementation of utility pipe rehabilitation through trenchless
technologies thus reducing greenhouse gases associated with open cut installations where applicable.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and utility systems.
Health in All Policies: These projects provide the City's water customers with safe and reliable drinking and water for fire protection with a lens to
protect the health, safety, and welfare of our citizens now and into the future..
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses.”
The City’s Budget Work Plan Goals 1 and 3 are: Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable Development.
Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient operations that lessen the City’s
carbon footprint and reduce energy costs.
Useful LifeProject Name Chapel Drive Watermain Rehabilitation Category Infrastructure
Type Replace or repair
Total Project Cost:$300,000
Total2025 2026 2027 2028 2029Expenditures 2030
300,000300,000Construction
300,000 300,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
300,000300,000Utility Fund: Water
300,000 300,000Total
143
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Aaron Ditzler
2025 2030thru Department Engineering
Description
The project will rehabilitate approximately 4,000 linear feet of watermain pipe along Maloney Avenue between Washington Avenue and Blake
Road. The pipes are located under the streets. The pipes are breaking at high frequencies and need rehabilitation. It is anticipated that the project
will use the cured-in-place pipe rehabilitation method. This work may be combined with the Presidents Neighborhood Street Reconstruction
Project.
Project #ENG25044
Justification
Expansion and/or Level of Service
Sustainability: Alternative construction methods utilized within the City include implementation of utility pipe rehabilitation through trenchless
technologies thus reducing greenhouse gases associated with open cut installations where applicable.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and utility systems.
Health in All Policies: These projects provide the City's water customers with safe and reliable drinking and water for fire protection with a lens to
protect the health, safety, and welfare of our citizens now and into the future..
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses.”
The City’s Budget Work Plan Goals 1 and 3 are: Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable Development.
Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient operations that lessen the City’s
carbon footprint and reduce energy costs.
Useful LifeProject Name Maloney Ave Watermain Rehabilitation Category Infrastructure
Type Replace or repair
Total Project Cost:$1,000,000
Total2025 2026 2027 2028 2029Expenditures 2030
1,000,0001,000,000Construction
1,000,000 1,000,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
1,000,0001,000,000Utility Fund: Water
1,000,000 1,000,000Total
144
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Chad Millner
2025 2030thru Department Engineering
Description
Project #ENG25045
Justification
The project will replace approximately 175 linear feet of watermain pipe under Nine Mile Creek between residential properties on the north and
commercial properties on the south. The pipe is failing and needs replacement. The adjacent properties will need to provide access for the project.
Useful LifeProject Name Watermain Replacement under NMC at 5901 Lincoln Dr Category Infrastructure
Type Replace or repair
Total Project Cost:$50,000
Total2025 2026 2027 2028 2029Expenditures 2030
50,00050,000Construction
50,000 50,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
50,00050,000Utility Fund: Water
50,000 50,000Total
145
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Chad Millner
2025 2030thru Department Engineering
Description
The project will replace approximately 1150 linear feet of watermain pipe between Long Brake Trail, Shannon Drive and Coventry Way. The pipes
are located behind residential properties in green space and storm water management areas. The pipes are failing and need replacement. The
adjacent properties will need to provide access for the project.
Project #ENG25046
Justification
Expansion and/or Level of Service
Sustainability: Alternative construction methods utilized within the City include implementation of utility pipe rehabilitation through trenchless
technologies thus reducing greenhouse gases associated with open cut installations where applicable.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and utility systems.
Health in All Policies: These projects provide the City's water customers with safe and reliable drinking and water for fire protection with a lens to
protect the health, safety, and welfare of our citizens now and into the future..
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses.”
The City’s Budget Work Plan Goals 1 and 3 are: Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable Development.
Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient operations that lessen the City’s
carbon footprint and reduce energy costs.
Useful LifeProject Name Watermain Replcmnt LB Tr/Shannon Dr/Coventry Way Category Infrastructure
Type Replace or repair
Total Project Cost:$225,000
Total2025 2026 2027 2028 2029Expenditures 2030
225,000225,000Construction
225,000 225,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
225,000225,000Utility Fund: Water
225,000 225,000Total
146
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Chad Millner
2025 2030thru Department Engineering
Description
The project will rehabilitate approximately 25,000 linear feet of watermain pipe within the Heights Neighborhood. The pipes are located under the
streets. The pipes are breaking at high frequencies and need rehabilitation. It is anticipated that the project will use the cured-in-place pipe
rehabilitation method.
Project #ENG25047
Justification
Expansion and/or Level of Service
Sustainability: Alternative construction methods utilized within the City include implementation of utility pipe rehabilitation through trenchless
technologies thus reducing greenhouse gases associated with open cut installations where applicable.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and utility systems.
Health in All Policies: These projects provide the City's water customers with safe and reliable drinking and water for fire protection with a lens to
protect the health, safety, and welfare of our citizens now and into the future.
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses.”
The City’s Budget Work Plan Goals 1 and 3 are: Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable Development.
Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient operations that lessen the City’s
carbon footprint and reduce energy costs.
Useful LifeProject Name Heights Neighborhood Watermain Rehabilitation Category Infrastructure
Type Replace or repair
Total Project Cost:$6,250,000
Total2025 2026 2027 2028 2029Expenditures 2030
6,250,0006,250,000Construction
6,250,000 6,250,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
6,250,0006,250,000Utility Fund: Water
6,250,000 6,250,000Total
147
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Andrew Scipioni
2025 2030thru Department Engineering
Description
This project will include repair or replacement of public sidewalks and pedestrian curb ramps maintained by the City of Edina. This project
supports the City’s ADA Transition Plan.
Project #ENG25050
Justification
Health, Safety & Regulatory Compliance
Sustainability: Carbon - The Pavement Management Program implemented by the City seeks to utilize resources efficiently by performing
infrastructure renewal that will provide the greatest lifespan increase for the lowest cost.
Surface water - The Living Streets initiative reduces impervious surfaces and develops roads, bicycle and pedestrian facilities with low impact
development techniques.
Green Alternatives - Alternative construction methods utilized within the City include reclamation of existing bituminous surfaces to use as
aggregate base material.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and accessible systems.
Health in All Policies: Connected and sustainable development includes an efficient multi-modal transportation system that balances improving
personal mobility options with reducing the community’s carbon footprint all the while reducing negative impacts on human health and safety.
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses.
The 2018 Comprehensive Plan notes to "maintain and enhance mobility for residents and businesses through creation and maintenance of a
balanced system of transportation alternatives," and to "promote safe walking, bicycling, and driving."
The approved Living Streets Policy and Plan strive to balance the needs of motorists, bicyclists, pedestrians and transit riders in ways that promote
safety and convenience, and provide meaningful opportunities for active living and better health.
Useful LifeProject Name Sidewalk Inspection Program Category Infrastructure
Type Replace or repair
Total Project Cost:$350,000
Total2025 2026 2027 2028 2029Expenditures 2030
300,00050,000 50,000 50,000 50,000 50,000Installation/Maintenance 50,000
50,000 50,000 50,000 50,000 50,000 300,000Total50,000
Total2025 2026 2027 2028 2029Funding Sources 2030
300,00050,000 50,000 50,000 50,000 50,000PACS Fund: Utility Franchise
Fees
50,000
50,000 50,000 50,000 50,000 50,000 300,000Total50,000
148
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Andrew Scipioni
2025 2030thru Department Engineering
Description
This project will provide funding for roadway improvements that seek to reduce vehicle speeds and improve safety for pedestrians and cyclists.
Such improvements may include curb extensions, medians, refuge islands, or dynamic display speed signs. Specific projects will be determined by
staff based on observed data, traffic safety requests, and with input from the Traffic Safety Committee and the Transportation Commission.
Project #ENG25051
Justification
Expansion and/or Level of Service
Sustainability: Carbon - The Pavement Management Program implemented by the City seeks to utilize resources efficiently by performing
infrastructure renewal that will provide the greatest lifespan increase for the lowest cost.
Surface water - The Living Streets initiative reduces impervious surfaces and develops roads, bicycle and pedestrian facilities with low impact
development techniques.
Green Alternatives - Alternative construction methods utilized within the City include reclamation of existing bituminous surfaces to use as
aggregate base material.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and accessible systems.
Health in All Policies: Connected and sustainable development includes an efficient multi-modal transportation system that balances improving
personal mobility options with reducing the community’s carbon footprint all the while reducing negative impacts on human health and safety.
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses.
The 2018 Comprehensive Plan notes to "maintain and enhance mobility for residents and businesses through creation and maintenance of a
balanced system of transportation alternatives," and to "promote safe walking, bicycling, and driving."
The approved Living Streets Policy and Plan strive to balance the needs of motorists, bicyclists, pedestrians and transit riders in ways that promote
safety and convenience, and provide meaningful opportunities for active living and better health.
Useful LifeProject Name Drive 25 Improvements Category Infrastructure
Type Replace or repair
Total Project Cost:$120,000
Total2025 2026 2027 2028 2029Expenditures 2030
120,00020,000 20,000 20,000 20,000 20,000Construction 20,000
20,000 20,000 20,000 20,000 20,000 120,000Total20,000
Total2025 2026 2027 2028 2029Funding Sources 2030
120,00020,000 20,000 20,000 20,000 20,000PACS Fund: Utility Franchise
Fees
20,000
20,000 20,000 20,000 20,000 20,000 120,000Total20,000
149
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Andrew Scipioni
2025 2030thru Department Engineering
Description
This project involves implementing a road diet on Normandale Road between 77th Street and Viking Drive and on Viking Drive between
Normandale Road and Computer Avenue. The reallocation of right-of-way will provide space to add on-street bicycle facilities. This work will be
implemented as part of a scheduled pavement maintenance project.
Project #ENG25052
Justification
Expansion and/or Level of Service
Sustainability: Carbon - The Pavement Management Program implemented by the City seeks to utilize resources efficiently by performing
infrastructure renewal that will provide the greatest lifespan increase for the lowest cost.
Surface water - The Living Streets initiative reduces impervious surfaces and develops roads, bicycle and pedestrian facilities with low impact
development techniques.
Green Alternatives - Alternative construction methods utilized within the City include reclamation of existing bituminous surfaces to use as
aggregate base material.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and accessible systems.
Health in All Policies: Connected and sustainable development includes an efficient multi-modal transportation system that balances improving
personal mobility options with reducing the community’s carbon footprint all the while reducing negative impacts on human health and safety.
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses.
The 2018 Comprehensive Plan notes to "maintain and enhance mobility for residents and businesses through creation and maintenance of a
balanced system of transportation alternatives," and to "promote safe walking, bicycling, and driving."
The approved Living Streets Policy and Plan strive to balance the needs of motorists, bicyclists, pedestrians and transit riders in ways that promote
safety and convenience, and provide meaningful opportunities for active living and better health.
Useful LifeProject Name Normandale Road/Viking Drive Bike Lanes Category Infrastructure
Type New
Total Project Cost:$28,200
Total2025 2026 2027 2028 2029Expenditures 2030
28,20028,200Construction
28,200 28,200Total
Total2025 2026 2027 2028 2029Funding Sources 2030
28,20028,200PACS Fund: Utility Franchise
Fees
28,200 28,200Total
150
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Andrew Scipioni
2025 2030thru Department Engineering
Description
This project involves updating the City’s Pedestrian and Bicycle Master Plan, which guides the development of the Edina’s multi-modal
transportation network. This project will involve hiring a consultant to assist with community engagement, coordinating meetings with staff and
officials, reviewing existing policies and best-practices, and developing recommendations.
Project #ENG25053
Justification
Expansion and/or Level of Service
Sustainability: Carbon - The Pavement Management Program implemented by the City seeks to utilize resources efficiently by performing
infrastructure renewal that will provide the greatest lifespan increase for the lowest cost.
Surface water - The Living Streets initiative reduces impervious surfaces and develops roads, bicycle and pedestrian facilities with low impact
development techniques.
Green Alternatives - Alternative construction methods utilized within the City include reclamation of existing bituminous surfaces to use as
aggregate base material.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and accessible systems.
Health in All Policies: Connected and sustainable development includes an efficient multi-modal transportation system that balances improving
personal mobility options with reducing the community’s carbon footprint all the while reducing negative impacts on human health and safety.
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses.
The 2018 Comprehensive Plan notes to "maintain and enhance mobility for residents and businesses through creation and maintenance of a
balanced system of transportation alternatives," and to "promote safe walking, bicycling, and driving."
The approved Living Streets Policy and Plan strive to balance the needs of motorists, bicyclists, pedestrians and transit riders in ways that promote
safety and convenience, and provide meaningful opportunities for active living and better health.
Useful LifeProject Name Pedestrian and Bicycle Master Plan Update Category Infrastructure
Type Replace or repair
Total Project Cost:$100,000
Total2025 2026 2027 2028 2029Expenditures 2030
100,000100,000Construction
100,000 100,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
100,000100,000PACS Fund: Utility Franchise
Fees
100,000 100,000Total
151
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Andrew Scipioni
2025 2030thru Department Engineering
Description
This project involves upgrading the existing bike lanes on Wooddale Avenue between 50th Street and Valley View Road. This facility is
recommended in the City’s Pedestrian and Bicycle Master Plan and will connect to existing facilities on Valley View Road and Wooddale Avenue.
Project #ENG25054
Justification
Expansion and/or Level of Service
Sustainability: Carbon - The Pavement Management Program implemented by the City seeks to utilize resources efficiently by performing
infrastructure renewal that will provide the greatest lifespan increase for the lowest cost.
Surface water - The Living Streets initiative reduces impervious surfaces and develops roads, bicycle and pedestrian facilities with low impact
development techniques.
Green Alternatives - Alternative construction methods utilized within the City include reclamation of existing bituminous surfaces to use as
aggregate base material.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and accessible systems.
Health in All Policies: Connected and sustainable development includes an efficient multi-modal transportation system that balances improving
personal mobility options with reducing the community’s carbon footprint all the while reducing negative impacts on human health and safety.
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses.
The 2018 Comprehensive Plan notes to "maintain and enhance mobility for residents and businesses through creation and maintenance of a
balanced system of transportation alternatives," and to "promote safe walking, bicycling, and driving."
The approved Living Streets Policy and Plan strive to balance the needs of motorists, bicyclists, pedestrians and transit riders in ways that promote
safety and convenience, and provide meaningful opportunities for active living and better health.
Useful LifeProject Name Wooddale Avenue Bike Lanes Category Infrastructure
Type New
Total Project Cost:$111,100
Total2025 2026 2027 2028 2029Expenditures 2030
111,10091,600 19,500Construction
91,600 19,500 111,100Total
Total2025 2026 2027 2028 2029Funding Sources 2030
111,10091,600 19,500PACS Fund: Utility Franchise
Fees
91,600 19,500 111,100Total
152
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Andrew Scipioni
2025 2030thru Department Engineering
Description
This project involves the construction of a shared-use path on McCauley Trail between Post Lane and Indian Hills Trail. This facility is
recommended in the City’s Pedestrian and Bicycle Master Plan and will connect to existing facilities on McCauley Trail and proposed facilities on
McCauley Trail and Indian Hills Trail.
Project #ENG25055
Justification
Expansion and/or Level of Service
Sustainability: Carbon - The Pavement Management Program implemented by the City seeks to utilize resources efficiently by performing
infrastructure renewal that will provide the greatest lifespan increase for the lowest cost.
Surface water - The Living Streets initiative reduces impervious surfaces and develops roads, bicycle and pedestrian facilities with low impact
development techniques.
Green Alternatives - Alternative construction methods utilized within the City include reclamation of existing bituminous surfaces to use as
aggregate base material.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and accessible systems.
Health in All Policies: Connected and sustainable development includes an efficient multi-modal transportation system that balances improving
personal mobility options with reducing the community’s carbon footprint all the while reducing negative impacts on human health and safety.
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses.
The 2018 Comprehensive Plan notes to "maintain and enhance mobility for residents and businesses through creation and maintenance of a
balanced system of transportation alternatives," and to "promote safe walking, bicycling, and driving."
The approved Living Streets Policy and Plan strive to balance the needs of motorists, bicyclists, pedestrians and transit riders in ways that promote
safety and convenience, and provide meaningful opportunities for active living and better health.
Useful LifeProject Name McCauley Trail Shared-Use Path Category Infrastructure
Type New
Total Project Cost:$503,000
Total2025 2026 2027 2028 2029Expenditures 2030
503,000503,000Construction
503,000 503,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
503,000503,000PACS Fund: Utility Franchise
Fees
503,000 503,000Total
153
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Andrew Scipioni
2025 2030thru Department Engineering
Description
This project involves implementing a road diet on 69th Street between France Avenue and York Avenue. The reallocation of right-of-way will
provide space to add on-street bicycle facilities. This work will be implemented as part of a scheduled pavement maintenance project.
Project #ENG25056
Justification
Expansion and/or Level of Service
Sustainability: Carbon - The Pavement Management Program implemented by the City seeks to utilize resources efficiently by performing
infrastructure renewal that will provide the greatest lifespan increase for the lowest cost.
Surface water - The Living Streets initiative reduces impervious surfaces and develops roads, bicycle and pedestrian facilities with low impact
development techniques.
Green Alternatives - Alternative construction methods utilized within the City include reclamation of existing bituminous surfaces to use as
aggregate base material.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and accessible systems.
Health in All Policies: Connected and sustainable development includes an efficient multi-modal transportation system that balances improving
personal mobility options with reducing the community’s carbon footprint all the while reducing negative impacts on human health and safety.
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses.
The 2018 Comprehensive Plan notes to "maintain and enhance mobility for residents and businesses through creation and maintenance of a
balanced system of transportation alternatives," and to "promote safe walking, bicycling, and driving."
The approved Living Streets Policy and Plan strive to balance the needs of motorists, bicyclists, pedestrians and transit riders in ways that promote
safety and convenience, and provide meaningful opportunities for active living and better health.
Useful LifeProject Name 69th Street Bike Lanes Category Infrastructure
Type New
Total Project Cost:$24,400
Total2025 2026 2027 2028 2029Expenditures 2030
24,40024,400Construction
24,400 24,400Total
Total2025 2026 2027 2028 2029Funding Sources 2030
24,40024,400PACS Fund: Utility Franchise
Fees
24,400 24,400Total
154
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Andrew Scipioni
2025 2030thru Department Engineering
Description
This project involves the construction of a bike boulevard on West Shore Drive between 66th Street and 70th Street. This facility is recommended
in the City’s Pedestrian and Bicycle Master Plan and will connect to existing facilities on 70th Street and proposed facilities on 66th Street and
West Shore Drive.
Project #ENG25057
Justification
Expansion and/or Level of Service
Sustainability: Carbon - The Pavement Management Program implemented by the City seeks to utilize resources efficiently by performing
infrastructure renewal that will provide the greatest lifespan increase for the lowest cost.
Surface water - The Living Streets initiative reduces impervious surfaces and develops roads, bicycle and pedestrian facilities with low impact
development techniques.
Green Alternatives - Alternative construction methods utilized within the City include reclamation of existing bituminous surfaces to use as
aggregate base material.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and accessible systems.
Health in All Policies: Connected and sustainable development includes an efficient multi-modal transportation system that balances improving
personal mobility options with reducing the community’s carbon footprint all the while reducing negative impacts on human health and safety.
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses.
The 2018 Comprehensive Plan notes to "maintain and enhance mobility for residents and businesses through creation and maintenance of a
balanced system of transportation alternatives," and to "promote safe walking, bicycling, and driving."
The approved Living Streets Policy and Plan strive to balance the needs of motorists, bicyclists, pedestrians and transit riders in ways that promote
safety and convenience, and provide meaningful opportunities for active living and better health.
Useful LifeProject Name West Shore Drive Bike Boulevard Category Infrastructure
Type New
Total Project Cost:$35,100
Total2025 2026 2027 2028 2029Expenditures 2030
35,10035,100Construction
35,100 35,100Total
Total2025 2026 2027 2028 2029Funding Sources 2030
35,10035,100PACS Fund: Utility Franchise
Fees
35,100 35,100Total
155
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Andrew Scipioni
2025 2030thru Department Engineering
Description
This project involves the construction of bike lanes on 44th Street between France Avenue and Grimes Avenue. This facility is recommended in the
City’s Pedestrian and Bicycle Master Plan and will connect to existing facilities on 44th Street and Grimes Avenue.
Project #ENG25058
Justification
Expansion and/or Level of Service
Sustainability: Carbon - The Pavement Management Program implemented by the City seeks to utilize resources efficiently by performing
infrastructure renewal that will provide the greatest lifespan increase for the lowest cost.
Surface water - The Living Streets initiative reduces impervious surfaces and develops roads, bicycle and pedestrian facilities with low impact
development techniques.
Green Alternatives - Alternative construction methods utilized within the City include reclamation of existing bituminous surfaces to use as
aggregate base material.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and accessible systems.
Health in All Policies: Connected and sustainable development includes an efficient multi-modal transportation system that balances improving
personal mobility options with reducing the community’s carbon footprint all the while reducing negative impacts on human health and safety.
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses.
The 2018 Comprehensive Plan notes to "maintain and enhance mobility for residents and businesses through creation and maintenance of a
balanced system of transportation alternatives," and to "promote safe walking, bicycling, and driving."
The approved Living Streets Policy and Plan strive to balance the needs of motorists, bicyclists, pedestrians and transit riders in ways that promote
safety and convenience, and provide meaningful opportunities for active living and better health.
Useful LifeProject Name W 44th St Bike Lanes Category Infrastructure
Type New
Total Project Cost:$18,100
Total2025 2026 2027 2028 2029Expenditures 2030
18,10018,100Construction
18,100 18,100Total
Total2025 2026 2027 2028 2029Funding Sources 2030
18,10018,100PACS Fund: Utility Franchise
Fees
18,100 18,100Total
156
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Andrew Scipioni
2025 2030thru Department Engineering
Description
This project involves the construction of bike lanes on Metro Boulevard between 70th Street and Edina Industrial Boulevard. This facility is
recommended in the City’s Pedestrian and Bicycle Master Plan and will connect to existing facilities on 70th Street and 72nd Street.
Project #ENG25059
Justification
Expansion and/or Level of Service
Sustainability: Carbon - The Pavement Management Program implemented by the City seeks to utilize resources efficiently by performing
infrastructure renewal that will provide the greatest lifespan increase for the lowest cost.
Surface water - The Living Streets initiative reduces impervious surfaces and develops roads, bicycle and pedestrian facilities with low impact
development techniques.
Green Alternatives - Alternative construction methods utilized within the City include reclamation of existing bituminous surfaces to use as
aggregate base material.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and accessible systems.
Health in All Policies: Connected and sustainable development includes an efficient multi-modal transportation system that balances improving
personal mobility options with reducing the community’s carbon footprint all the while reducing negative impacts on human health and safety.
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses.
The 2018 Comprehensive Plan notes to "maintain and enhance mobility for residents and businesses through creation and maintenance of a
balanced system of transportation alternatives," and to "promote safe walking, bicycling, and driving."
The approved Living Streets Policy and Plan strive to balance the needs of motorists, bicyclists, pedestrians and transit riders in ways that promote
safety and convenience, and provide meaningful opportunities for active living and better health.
Useful LifeProject Name Metro Boulevard Bike Lanes Category Infrastructure
Type New
Total Project Cost:$60,900
Total2025 2026 2027 2028 2029Expenditures 2030
60,90060,900Construction
60,900 60,900Total
Total2025 2026 2027 2028 2029Funding Sources 2030
60,90060,900PACS Fund: Utility Franchise
Fees
60,900 60,900Total
157
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Andrew Scipioni
2025 2030thru Department Engineering
Description
This project involves the replacement of an existing pedestrian bridge over Minnehaha Creek between Beard Avenue and Beard Court. This project
will create a fully accessible pedestrian and bicycle bridge connecting the Creek Knoll and Chowen Park neighborhoods.
Project #ENG25060
Justification
Expansion and/or Level of Service
Sustainability: Carbon - The Pavement Management Program implemented by the City seeks to utilize resources efficiently by performing
infrastructure renewal that will provide the greatest lifespan increase for the lowest cost.
Surface water - The Living Streets initiative reduces impervious surfaces and develops roads, bicycle and pedestrian facilities with low impact
development techniques.
Green Alternatives - Alternative construction methods utilized within the City include reclamation of existing bituminous surfaces to use as
aggregate base material.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and accessible systems.
Health in All Policies: Connected and sustainable development includes an efficient multi-modal transportation system that balances improving
personal mobility options with reducing the community’s carbon footprint all the while reducing negative impacts on human health and safety.
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses.
The 2018 Comprehensive Plan notes to "maintain and enhance mobility for residents and businesses through creation and maintenance of a
balanced system of transportation alternatives," and to "promote safe walking, bicycling, and driving."
The approved Living Streets Policy and Plan strive to balance the needs of motorists, bicyclists, pedestrians and transit riders in ways that promote
safety and convenience, and provide meaningful opportunities for active living and better health.
Useful LifeProject Name Minnehaha Creek Pedestrian Bridge Category Infrastructure
Type New
Total Project Cost:$1,200,000
Total2025 2026 2027 2028 2029Expenditures 2030
1,200,0001,200,000Construction
1,200,000 1,200,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
1,200,0001,200,000PACS Fund: Utility Franchise
Fees
1,200,000 1,200,000Total
158
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Andrew Scipioni
2025 2030thru Department Engineering
Description
This project involves the construction of a sidewalk on the north side of Edina Industrial Boulevard between Bush Lake Road and Metro
Boulevard. This facility is recommended in the City’s Pedestrian and Bicycle Master Plan and will connect to existing facilities on Metro
Boulevard and Edina Industrial Boulevard.
Project #ENG25061
Justification
Expansion and/or Level of Service
Sustainability: Carbon - The Pavement Management Program implemented by the City seeks to utilize resources efficiently by performing
infrastructure renewal that will provide the greatest lifespan increase for the lowest cost.
Surface water - The Living Streets initiative reduces impervious surfaces and develops roads, bicycle and pedestrian facilities with low impact
development techniques.
Green Alternatives - Alternative construction methods utilized within the City include reclamation of existing bituminous surfaces to use as
aggregate base material.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and accessible systems.
Health in All Policies: Connected and sustainable development includes an efficient multi-modal transportation system that balances improving
personal mobility options with reducing the community’s carbon footprint all the while reducing negative impacts on human health and safety.
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses.
The 2018 Comprehensive Plan notes to "maintain and enhance mobility for residents and businesses through creation and maintenance of a
balanced system of transportation alternatives," and to "promote safe walking, bicycling, and driving."
The approved Living Streets Policy and Plan strive to balance the needs of motorists, bicyclists, pedestrians and transit riders in ways that promote
safety and convenience, and provide meaningful opportunities for active living and better health.
Useful LifeProject Name Edina Industrial Boulevard Sidewalk Category Infrastructure
Type New
Total Project Cost:$297,500
Total2025 2026 2027 2028 2029Expenditures 2030
297,500297,500Construction
297,500 297,500Total
Total2025 2026 2027 2028 2029Funding Sources 2030
297,500297,500PACS Fund: Utility Franchise
Fees
297,500 297,500Total
159
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Andrew Scipioni
2025 2030thru Department Engineering
Description
This project involves the construction of a sidewalk on the north side of 66th Street between Ridgeview Drive and Josephine Avenue. This facility
is recommended in the City’s Pedestrian and Bicycle Master Plan and will connect to existing facilities on Ridgeview Drive, 66th Street and
Normandale Road.
Project #ENG25062
Justification
Expansion and/or Level of Service
Sustainability: Carbon - The Pavement Management Program implemented by the City seeks to utilize resources efficiently by performing
infrastructure renewal that will provide the greatest lifespan increase for the lowest cost.
Surface water - The Living Streets initiative reduces impervious surfaces and develops roads, bicycle and pedestrian facilities with low impact
development techniques.
Green Alternative - Alternative construction methods utilized within the City include reclamation of existing bituminous surfaces to use as
aggregate base material.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and accessible systems.
Health in All Policies: Connected and sustainable development includes an efficient multi-modal transportation system that balances improving
personal mobility options with reducing the community’s carbon footprint all the while reducing negative impacts on human health and safety.
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses.
The 2018 Comprehensive Plan notes to "maintain and enhance mobility for residents and businesses through creation and maintenance of a
balanced system of transportation alternatives," and to "promote safe walking, bicycling, and driving."
The approved Living Streets Policy and Plan strive to balance the needs of motorists, bicyclists, pedestrians and transit riders in ways that promote
safety and convenience, and provide meaningful opportunities for active living and better health.
Useful LifeProject Name W 66th Street Sidewalk Category Infrastructure
Type New
Total Project Cost:$476,000
Total2025 2026 2027 2028 2029Expenditures 2030
476,000476,000Construction
476,000 476,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
476,000476,000PACS Fund: Utility Franchise
Fees
476,000 476,000Total
160
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Andrew Scipioni
2025 2030thru Department Engineering
Description
This project involves hiring a consultant to design bicycle facilities on Valley View Road between 64th Street and 66th Street underneath the
Highway 62 overpass. This facility is recommended in the City’s Pedestrian and Bicycle Master Plan and will connect to existing facilities on
Valley View Road and proposed facilities on 66th Street.
Project #ENG25063
Justification
Expansion and/or Level of Service
Sustainability: Carbon - The Pavement Management Program implemented by the City seeks to utilize resources efficiently by performing
infrastructure renewal that will provide the greatest lifespan increase for the lowest cost.
Surface water - The Living Streets initiative reduces impervious surfaces and develops roads, bicycle and pedestrian facilities with low impact
development techniques.
Green Alternatives - Alternative construction methods utilized within the City include reclamation of existing bituminous surfaces to use as
aggregate base material.
Community Engagement: These projects encourage people to interact with staff to understand how important infrastructure is for safety and health
of all. Engagement occurs over years, and it helps shape some of the project details. It also increases the awareness of having well maintained
transportation and accessible systems.
Health in All Policies: Connected and sustainable development includes an efficient multi-modal transportation system that balances improving
personal mobility options with reducing the community’s carbon footprint all the while reducing negative impacts on human health and safety.
Race & Equity: This project impacts infrastructure that may not be ADA compliant. Reconstruction is conducted to ADA standards, making the
new infrastructure accessible to all users.
Stewardship: The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer premier
public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and uncommonly
high quality of life enjoyed by our residents and businesses.
The 2018 Comprehensive Plan notes to "maintain and enhance mobility for residents and businesses through creation and maintenance of a
balanced system of transportation alternatives," and to "promote safe walking, bicycling, and driving."
The approved Living Streets Policy and Plan strive to balance the needs of motorists, bicyclists, pedestrians and transit riders in ways that promote
safety and convenience, and provide meaningful opportunities for active living and better health.
Useful LifeProject Name Valley View Road Bike Lane Design Category Infrastructure
Type New
Total Project Cost:$50,000
Total2025 2026 2027 2028 2029Expenditures 2030
50,000Construction50,000
50,000Total50,000
Total2025 2026 2027 2028 2029Funding Sources 2030
50,000PACS Fund: Utility Franchise
Fees
50,000
50,000Total50,000
161
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Chad Millner
2025 2030thru Department Engineering
Description
This proejct would provide for the lining of a neighborhood that experiences a significant amount of inflow and infiltration into the sanitary sewer
system
ENVIRONMENTAL CONSIDERATIONS:
Infiltration and inflow required the Lift Station pumps to run much more often to lift the sewage and infiltration into the next gravity sewer main.
Elimination of this inflow will use less energy.
Project #PW23010
Justification
Our Vision Edina mission statement is to provide efficient and valued public services and to maintain sound public infrastructure. Specifically, our
Comprehgensive Plan identifies a goal to provide the City's sewer customers with safe, reliable, and efficient removal of wastewater for residents
and customers in the City of Edina, while eliminating risk of inflow, infiltration, and backflow to protectthe health, safety, and welfare of our
citizens now and into the future.
Useful LifeProject Name Nine Mile Village Sewer Lining Category Infrastructure
Type Replace or repair
Total Project Cost:$175,000
Total2025 2026 2027 2028 2029Expenditures 2030
175,000175,000Construction
175,000 175,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
175,000175,000Utility Fund: Sewer
175,000 175,000Total
162
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Chad Millner
2025 2030thru Department Engineering
Description
This project will replace 130 LF of sewer main on Olinger Boulevard. This dip in the sewer line collects debris and does not allow the sewer to
flow properly which leads to potential blockages of the sewer.
ENVIRONMENTAL CONSIDERATIONS:
As mentioned in the description, there is a large dip in the sewer at this location. Since there is not free flowing sewage at this location, solids tend
to settle out and create potential for blockages. This section of sewer needs to cleaned more frequently thereby creating addition trips and fuel
usage.
Project #PW23011
Justification
Our Vision Edina mission statement is to provide efficient and valued public services and to maintain sound public infrastructure. Specifically, our
Comprehensive Plan identifies a goal to provide the City's sewer customers with safe, reliable, and efficient removal of wastewater for residents
and customers in the City of Edina, while eliminating risk of inflow, infiltration, and backflow to protect the health, safety, and welfare of our
citizens now and into the future.
Useful LifeProject Name Olinger Road Dip Replacement: 130 LF + Road Repair Category Infrastructure
Type Replace or repair
Total Project Cost:$80,000
Total2025 2026 2027 2028 2029Expenditures 2030
80,00080,000Construction
80,000 80,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
80,00080,000Utility Fund: Sewer
80,000 80,000Total
163
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Derik Otten
2025 2030thru Department Facilities
Description
In our continuing efforts to provide an accessible environment for residents, visitors and employees, the City completed an ADA inventory to
understand areas of need. The inventory conducted an evaluation for compliance with applicable laws, codes and design guidelines pertaining to
accessibility. This project will begin to address the recommendations prioritized for completion in 3-8 years.
ENVIRONMENTAL CONSIDERATIONS:
Facility improvements provide an excellent opportunity for the City to continue towards our sustainability goals. Each specific project will be
reviewed from an environmental cost benefit analysis to determine the right balance between operations and sustainability.
Project #ENG21044
Justification
See Summary of Facilities Improvements.
Useful LifeProject Name City Wide ADA Facility Improvements Level 2 Category Buildings
Type Replace or repair
Total Project Cost:$300,000
Total2025 2026 2027 2028 2029Expenditures 2030
300,00050,000 100,000 50,000Construction 100,000
50,000 100,000 50,000 300,000Total100,000
Total2025 2026 2027 2028 2029Funding Sources 2030
300,00050,000 100,000 50,000Construction Fund: CIP Levy 100,000
50,000 100,000 50,000 300,000Total100,000
164
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Derik Otten
2025 2030thru Department Facilities
Description
In 2018, the City completed a three-year review process of 117 buildings to create a master replacement schedule for the components of each
physical building. This extensive list includes repairs and replacements of Mechanical Electrical & Plumbing Systems (MEP), Furniture Fixtures
and Equipment (FFE), and the building envelope components like roofing and glazing. Maintaining assets aligns with the following city goals.
Project #ENG21051
Justification
See Summary of Facilities Improvements.
Useful LifeProject Name Pamela Park Facility Maintenance Category Buildings
Type Replace or repair
Total Project Cost:$210,000
Total2025 2026 2027 2028 2029Expenditures 2030
210,000210,000Construction
210,000 210,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
210,000210,000Construction Fund: CIP Levy
210,000 210,000Total
165
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Marisa Bayer
2025 2030thru Department Facilities
Description
This project will create funding to build new buildings more sustainable and replace failing mechanical systems with more energy efficient systems.
These actions reduce energy use and greenhouse gas emissions.
ENVIRONMENTAL CONSIDERATIONS:
Major facility mechanical equipment replacements provide an excellent opportunity for the City to continue towards our sustainability goals. Each
specific project will be reviewed from an environmental cost benefit analysis to determine the right balance between operations and sustainability.
Project #ENG21062
Justification
See Summary of Facilities Improvements
Useful Life 50Project Name Facility Efficiency Upgrades Category Buildings
Type Replace or repair
Total Project Cost:$3,000,000
Total2025 2026 2027 2028 2029Expenditures 2030
3,000,000500,000 500,000 500,000 500,000 500,000Construction 500,000
500,000 500,000 500,000 500,000 500,000 3,000,000Total500,000
Total2025 2026 2027 2028 2029Funding Sources 2030
3,000,000500,000 500,000 500,000 500,000 500,000CAS Fund: Utility Franchise
Fees
500,000
500,000 500,000 500,000 500,000 500,000 3,000,000Total500,000
166
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Derik Otten
2025 2030thru Department Facilities
Description
Kitchen cabinets and remodel, exterior doors, gas furnace, swinging doors, painting, carpeting, new greenhouse, interior doors museum, museum
carpet, mau maintence area, museum exterior windows and doors, museum stucco ceiling, museum roof, and basement wall paint, museum lights,
maintenance roof, walls, casework and lights, painting, restroom accessories, ceramic tile, wood treatments, vct, concrete sealing, plaster, ceiling
tile, exhst systems, electric controls, pa system, OH doors, partitions, water htrs, fire alarm system, security system, exit signs, batteries, restroom
accessories, frp walls, 2025 - Museum Sprinkler, staining, 2026 - Museum restroom fixture, water distribution,cooler,maintenance bldg,custodial
sinks, and restroom plumbing, electric feeder, exit signs, concrete sealing, water distribution
Project #FAC23109
Justification
See Summary of Facilities Improvements.
Useful LifeProject Name Arneson Acres Park Facility Improvements Category Infrastructure
Type Replace or repair
Total Project Cost:$700,000
Total2025 2026 2027 2028 2029Expenditures 2030
700,000700,000Installation/Maintenance
700,000 700,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
700,000700,000Construction Fund: CIP Levy
700,000 700,000Total
167
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Derik Otten
2025 2030thru Department Facilities
Description
"This project will provide upgrades to fire alarm systems for planned centralized monitoring and location services to 911 dispatch.This project
will expand card reader access devices to additional buildings and spaces."
Project #FAC25101
Justification
Expansion and/or Level of Service
Useful LifeProject Name City Wide Card Reader & Fire Alarm Updates Category Buildings
Type Expand or enhance
Total Project Cost:$100,000
Total2025 2026 2027 2028 2029Expenditures 2030
100,000100,000Construction
100,000 100,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
100,000100,000Construction Fund: CIP Levy
100,000 100,000Total
168
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Derik Otten
2025 2030thru Department Facilities
Description
This project involves a scheduled replacement of roofs of city owned buildings. Many of the roofs are nearing the end of their useful life and if not
addressed failure is likely causing damage to property and possible downtime for portions of city operations. Schedule replacement allows for
planning of disruption to building and surroundings and can lessen the likelihood of critical system failures.
In 2023 a consultant was retained to inspect and evaluate the roofing system on all buildings. The report detailed the conditions outlining the
needs for repairs and total replacements indicating both remaining life expectancy and estimated costs.
A roof photovoltaic (PV) feasibility study was conducted in 2023 researching possible solar arrays with planned replacements. If installed and
planned together the probability of damage to the roofing during installation of PV systems is minimized. This also allows the city to time future
replacement of both systems to happen simultaneously.
The PV systems are submitted under a separate project.
Roofs
2025 #1 Public Works Building Offices $800,000
2026 #2 Fire Station #1 $600,000
2027 #3 Edinborough Park $2,000,000
Roofs w/ PV
2026 #1 York Ave. Liquor $450,000
2026 #2 Pamela Park $100,000
2029 #3 SMPSTG $500,000
2030 #4 Public Works Building Shops $4,000,000
Project #FAC25103
Justification
Asset Functionality
Sustainability - By providing preventative maintenance and scheduled repairs and replacement the city is able to extend the useful life of equipment
and structures thus eliminating items from the waste stream. This includes minor maintenance like cleaning carpets and painting and major
maintenance such as replacement of HVAC, plumbing, and electrical service equipment.
Stewardship - By providing preventative maintenance and scheduled repairs and replacement the city is able to extend the useful life of equipment
and structures thus extending the useful life of the buildings ensuring their use by future generations. This includes minor maintenance like
cleaning carpets and painting and major maintenance such as replacement of HVAC, plumbing, and electrical service equipment.
Useful LifeProject Name City Wide Roof Replacement Category Buildings
Type Replace or repair
Total Project Cost:$12,500,000
Total2025 2026 2027 2028 2029Expenditures 2030
12,500,000800,000 700,000 2,000,000 5,000,000Construction 4,000,000
800,000 700,000 2,000,000 5,000,000 12,500,000Total4,000,000
Total2025 2026 2027 2028 2029Funding Sources 2030
12,500,000800,000 700,000 2,000,000 5,000,000CIP Bonds 4,000,000
800,000 700,000 2,000,000 5,000,000 12,500,000Total4,000,000
169
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Jon Darsow
2025 2030thru Department Facilities
Description
"This project involves a multi-faceted approach to repairs and maintenance within the 50th and France Special Services District also referred to as
“50th & France ” . The 50th & France District is a high-quality commercial and residential community asset that has seen numerous private
developments and public improvements over the years giving it a unique and complex history. The majority of the district’s streetscape
improvements were either reconstructed or newly installed in 1990. Kimley Horn & Associates have conducted a number of assessments over
the past decade highlighting needed repairs and improvements in the district. The most recent of which in 2021 identified over $6M of items
needing attention. This includes the street and pedestrian lighting, granite-cladding to raised planters, at grade foundation plantings, street trees
planted in pits with tree grates, public fountain, benches, trash receptacles, and concrete paver sidewalks. These items are amplified by the new
development in the area such as Nolan Mains and the Carillon Building. Investments in the city owned property are needed to ensure these items
don’t fall into further dismay discouraging future development and investments in the area. 2025-$400,000 planning2026 --$3.0M--Phase
12027 --$3.0M--Phase 22029--$1.0M--Phase 3"
Project #FAC25105
Justification
Asset Functionality
Sustainability - By providing preventative maintenance and scheduled repairs and replacement the city is able to extend the useful life of equipment
and structures thus eliminating items from the waste stream. This includes minor maintenance like cleaning carpets and painting and major
maintenance such as replacement of HVAC, plumbing, and electrical service equipment.
Stewardship - By providing preventative maintenance and scheduled repairs and replacement the city is able to extend the useful life of equipment
and structures thus extending the useful life of the buildings ensuring their use by future generations. This includes minor maintenance like
cleaning carpets and painting and major maintenance such as replacement of HVAC, plumbing, and electrical service equipment.
Useful LifeProject Name 50th & France Streetscapes Improvements Category Land
Type Replace or repair
Total Project Cost:$7,400,000
Total2025 2026 2027 2028 2029Expenditures 2030
7,400,000400,000 3,000,000 3,000,000 1,000,000Installation/Maintenance
400,000 3,000,000 3,000,000 1,000,000 7,400,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
7,400,000400,000 3,000,000 3,000,000 1,000,000CIP Bonds
400,000 3,000,000 3,000,000 1,000,000 7,400,000Total
170
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Derik Otten
2025 2030thru Department Facilities
Description
This project would renovate and update the living quarters in Fire Station 231.
Project #FAC25108
Justification
Asset Functionality
Useful LifeProject Name Fire Station #1 Living Quarters Category Buildings
Type Replace or repair
Total Project Cost:$500,000
Total2025 2026 2027 2028 2029Expenditures 2030
500,000Installation/Maintenance 500,000
500,000Total500,000
Total2025 2026 2027 2028 2029Funding Sources 2030
500,000Construction Fund: CIP Levy 500,000
500,000Total500,000
171
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Zuly Marquez
2025 2030thru Department Facilities
Description
This project involves the demolition of Fire Station #2, York Ave, and assumes the building is removed and site left as pad ready. No other
modifications to building or site amenities are included.
Project #FAC25109
Justification
Asset Functionality
Useful LifeProject Name Fire Station #2 York Ave. Building Demo Category Buildings
Type Replace or repair
Total Project Cost:$500,000
Total2025 2026 2027 2028 2029Expenditures 2030
500,000500,000Installation/Maintenance
500,000 500,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
500,000500,000Utility Fund: Water
500,000 500,000Total
172
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Derik Otten
2025 2030thru Department Facilities
Description
"This project involves the replacement of software used to track the overall condition of city owned facilities. In addition to indexing the buildings
this software would allow the city to process work orders for planned preventative maintenance, routine and emergency repairs to building
components and other areas of the city like utility and infrastructure components, park playground structures, natural resource areas and enterprise
sites. The software used to conduct the study in 2018 no longer meets the operational requirements of buildings as it does allow for tracking of
resources spent on maintenance and repairs. Purchase of software is a lump sum price and will require an annual maintenance agreement."
Project #FAC25110
Justification
Asset Functionality
Sustainability - By providing preventative maintenance and scheduled repairs and replacement the city is able to extend the useful life of equipment
and structures thus eliminating items from the waste stream.
Stewardship - By providing preventative maintenance and scheduled repairs and replacement the city is able to extend the useful life of equipment
and structures thus extending the useful life of the buildings ensuring their use by future generations.
Useful LifeProject Name Facility Asset Maintenance Software Category Technology
Type Replace or repair
Total Project Cost:$1,044,000
Total2025 2026 2027 2028 2029Expenditures 2030
1,044,000300,000 135,000 142,000 150,000 155,000Installation/Maintenance 162,000
300,000 135,000 142,000 150,000 155,000 1,044,000Total162,000
Total2025 2026 2027 2028 2029Funding Sources 2030
1,044,000300,000 135,000 142,000 150,000 155,000Construction Fund: Equipment
Levy 162,000
300,000 135,000 142,000 150,000 155,000 1,044,000Total162,000
173
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Derik Otten
2025 2030thru Department Facilities
Description
"A structural engineering review in 2020 of the existing cold storage discovered damage to the building structure. Repairs were made to extend the
useful life, but the extent was deemed temporary, the reviewing consultant recommended complete replacement in 2-5 years. $200,000 for
planning $2,300,000 for new building "
Project #FAC25113
Justification
Asset Functionality
Useful LifeProject Name Public Works Cold Storage Building Replacement Category Buildings
Type Replace or repair
Total Project Cost:$2,600,000
Total2025 2026 2027 2028 2029Expenditures 2030
300,000300,000Planning and Design
2,300,0002,300,000Installation/Maintenance
300,000 2,300,000 2,600,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
2,300,0002,300,000CIP Bonds
300,000300,000Construction Fund: Reserves
300,000 2,300,000 2,600,000Total
174
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Derik Otten
2025 2030thru Department Facilities
Description
"Reconfigure office spaces within Public Works to meet current and future staffing needs. As staffing increases to meet the needs of essential
functions for the City, the office spaces for staff will require updates and reconfiguration as well. Many of these building are over-occupied with
multiple staff using spaces that were once designed for storage or ancillary functions like copy rooms. Renovations allows the city to maximize
within spaces while also providing flexible work spaces to attract prospective employees and align with current trends in work-flex and office
policies. Expansion of Parking Lot also needed. "
Project #FAC25114
Justification
Expansion and/or Level of Service
Useful LifeProject Name Public Works Space Reconfiguration Category Buildings
Type Expand or enhance
Total Project Cost:$850,000
Total2025 2026 2027 2028 2029Expenditures 2030
75,00075,000Planning and Design
775,000775,000Construction
75,000 775,000 850,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
850,00075,000 775,000Construction Fund: CIP Levy
75,000 775,000 850,000Total
175
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Derik Otten
2025 2030thru Department Facilities
Description
"Replace access gates in 2 locations at Public Works Building. Existing gates have reached the end of their useful life and require extensive
maintenance and financial resources. These gates provide essential security and access control to the complex, when broken can affect the cities
ability to provide essential services like utility repairs, snow management and ice-treatments and fueling services for public safety equipment of
police and fire. "
Project #FAC25115
Justification
Asset Functionality
Useful LifeProject Name Public Works Access Gates Category Buildings
Type Replace or repair
Total Project Cost:$300,000
Total2025 2026 2027 2028 2029Expenditures 2030
300,000300,000Installation/Maintenance
300,000 300,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
300,000300,000Construction Fund: CIP Levy
300,000 300,000Total
176
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Derik Otten
2025 2030thru Department Facilities
Description
Existing Building Automation System (BAS) components has reached the end of its useful life. These systems provide control over the HVAC
systems in the building and allow for building optimization during heat and cooling events. In addition the lighting systems in the building also
need to be replaced as they are also nearing end of life.
Project #FAC25117
Justification
Asset Functionality
Sustainability - Updated BAS & Lighting systems will reduce energy consumption and loss throughout the building. Thus lowering the carbon
footprint of the building.
Stewardship - By providing preventative maintenance and scheduled repairs and replacement the city is able to extend the useful life of equipment
and structures thus extending the useful life of the buildings ensuring their use by future generations. This includes minor maintenance like
cleaning carpets and painting and major maintenance such as replacement of HVAC, plumbing, and electrical service equipment.
Useful LifeProject Name Public Works BAS & Lighting Upgrades Category Buildings
Type Replace or repair
Total Project Cost:$825,000
Total2025 2026 2027 2028 2029Expenditures 2030
125,000125,000Planning and Design
700,000700,000Installation/Maintenance
125,000 700,000 825,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
825,000125,000 700,000Construction Fund: CIP Levy
125,000 700,000 825,000Total
177
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Derik Otten
2025 2030thru Department Facilities
Description
"Replace existing AV equipment throughout space. Equipment is used for programming in space by city staff, residents and paid programming.
Quote produced in 2023"
Project #FAC25118
Justification
Expansion and/or Level of Service
Stewardship - By providing preventative maintenance and scheduled repairs and replacement the city is able to extend the useful life of equipment
and structures thus extending the useful life of the buildings ensuring their use by future generations. This includes minor maintenance like
cleaning carpets and painting and major maintenance such as replacement of HVAC, plumbing, and electrical service equipment.
Useful LifeProject Name Senior Center AV Equipment Category Technology
Type Replace or repair
Total Project Cost:$55,000
Total2025 2026 2027 2028 2029Expenditures 2030
55,00055,000Installation/Maintenance
55,000 55,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
55,00055,000Construction Fund: Cable PEG
55,000 55,000Total
178
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Derik Otten
2025 2030thru Department Facilities
Description
This project involves the design and replacement of the Audio Visual Systems at Braemar Golf Course. Includes both meeting rooms in basement
and minor changes to banquet area.
Project #FAC25120
Justification
Asset Functionality
Useful LifeProject Name Golf Course Audio Visual Replacement Category Equipment and Vehicles
Type New
Total Project Cost:$250,000
Total2025 2026 2027 2028 2029Expenditures 2030
250,000250,000Vehicles and Equipment
250,000 250,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
250,000250,000Golf Course Fund
250,000 250,000Total
179
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Derik Otten
2025 2030thru Department Facilities
Description
"This project involves the replacement of the emergency radio repeater/booster in the Public Works Building. The system provides signal boost to
emergency services personal inside the building during an emergency and is vital to their ability to communicate.The existing system was
damaged a number of years ago and is no longer functioning. "
Project #FAC25121
Justification
Health, Safety & Regulatory Compliance
Useful LifeProject Name PW Building Emergency Services Radio Repeater Category Equipment and Vehicles
Type Replace or repair
Total Project Cost:$250,000
Total2025 2026 2027 2028 2029Expenditures 2030
250,000250,000Installation/Maintenance
250,000 250,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
250,000250,000Public Safety Aid
250,000 250,000Total
180
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Derik Otten
2025 2030thru Department Facilities
Description
"Design Services to replace existing studio lighting in City Council Chambers. System is standalone from rest of building lighting and will
remain so. Project includes design fees only to allow for a budget to be set in subsequent CIP. Facilities would lead project with support from
Communications. "
Project #FAC25122
Justification
Asset Functionality
Justification - By providing preventative maintenance and scheduled repairs and replacement the city is able to extend the useful life of equipment
and structures thus eliminating items from the waste stream. This includes minor maintenance like cleaning carpets and painting and major
maintenance such as replacement of HVAC, plumbing, and electrical service equipment.
Stewardship - By providing preventative maintenance and scheduled repairs and replacement the city is able to extend the useful life of equipment
and structures thus extending the useful life of the buildings ensuring their use by future generations. This includes minor maintenance like
cleaning carpets and painting and major maintenance such as replacement of HVAC, plumbing, and electrical service equipment.
Useful LifeProject Name City Hall Council Chambers Studio Lighting Category Equipment and Vehicles
Type Replace or repair
Total Project Cost:$300,000
Total2025 2026 2027 2028 2029Expenditures 2030
300,000300,000Installation/Maintenance
300,000 300,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
300,000300,000Construction Fund: Cable PEG
300,000 300,000Total
181
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Derik Otten
2025 2030thru Department Facilities
Description
"Existing HVAC unit servicing Edinborough Park Pool area has reached the end of useful life. Mechanical failures in early 2024 resulted in a
repair bill in excess of $15,000. This unit has a history of requiring major repairs similar to this over the past 3-5 years.$100K for design
services, $250K for equipment and installation. "
Project #FAC25123
Justification
Asset Functionality
Sustainability - By providing preventative maintenance and scheduled repairs and replacement the city is able to extend the useful life of equipment
and structures thus eliminating items from the waste stream. This includes minor maintenance like cleaning carpets and painting and major
maintenance such as replacement of HVAC, plumbing, and electrical service equipment.
Stewardship - By providing preventative maintenance and scheduled repairs and replacement the city is able to extend the useful life of equipment
and structures thus extending the useful life of the buildings ensuring their use by future generations. This includes minor maintenance like
cleaning carpets and painting and major maintenance such as replacement of HVAC, plumbing, and electrical service equipment
Useful LifeProject Name Edinborough Park Pool HVAC Unit Category Equipment and Vehicles
Type Replace or repair
Total Project Cost:$350,000
Total2025 2026 2027 2028 2029Expenditures 2030
350,000350,000Installation/Maintenance
350,000 350,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
350,000350,000CIP Bonds
350,000 350,000Total
182
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Jon Darsow
2025 2030thru Department Facilities
Description
"This project will install a new comfort station facility near hole 6. Facilities along with Braemar staff identified an area in the front 9 portion of
the golf course where a much needed comfort station could be easily located. The amount included in the CIP is meant to be a match to funding
from the Golf Course. "
Project #FAC25124
Justification
Expansion and/or Level of Service
Sustainability - The new comfort station will possibly utilize solar power for all electrical and water heating needs.
Useful LifeProject Name Golf Course Restroom Front 9 Category Parks
Type Expand or enhance
Total Project Cost:$400,000
Total2025 2026 2027 2028 2029Expenditures 2030
400,000400,000Construction
400,000 400,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
400,000400,000Golf Course Fund
400,000 400,000Total
183
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Derik Otten
2025 2030thru Department Facilities
Description
"Replace 2 existing HVAC condensing units servicing city hall. These units provide necessary refrigeration to keep the building comfortable
during cooling season. The existing units have reached the end of their useful life and need replacement. Preparations for the replacement will
happen concurrently with the re-roofing of the building in 2024. "
Project #FAC25125
Justification
Asset Functionality
Sustainability - By providing preventative maintenance and scheduled repairs and replacement the city is able to extend the useful life of equipment
and structures thus eliminating items from the waste stream. This includes minor maintenance like cleaning carpets and painting and major
maintenance such as replacement of HVAC, plumbing, and electrical service equipment.
Stewardship - By providing preventative maintenance and scheduled repairs and replacement the city is able to extend the useful life of equipment
and structures thus extending the useful life of the buildings ensuring their use by future generations. This includes minor maintenance like
cleaning carpets and painting and major maintenance such as replacement of HVAC, plumbing, and electrical service equipment.
Useful LifeProject Name City Hall HVAC Equipment Replacement Category Equipment and Vehicles
Type Replace or repair
Total Project Cost:$500,000
Total2025 2026 2027 2028 2029Expenditures 2030
500,000500,000Installation/Maintenance
500,000 500,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
500,000500,000Construction Fund: CIP Levy
500,000 500,000Total
184
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Derik Otten
2025 2030thru Department Facilities
Description
A roof photovoltaic (PV) feasibility study was conducted in 2023 researching possible solar arrays and Electric Vehicle (EV) charging stations for
both private and public use. The study reviewed all city buildings, parking ramps, and large parking surface lots taking into consideration possible
array size, energy generation, and required infrastructure upgrades and made recommendations on ideal sites.
The installation of the PV & EV systems should align with the replacement of any roofing or parking lots to minimize disruption and avoid costly
retrofitting of systems.
PV
2026 #1 York Ave Liquor $225,000
2026 #2 Pamela Park $300,000
2028 #3 Senior Center $500,000
2029 #4 SMPSTF $500,000
EV
2030 #1 City Hall $600,000 Lvl. 3 Fast Charger
2030 #2 SMPSTF $500,000 Lvl 2 chargers
Project #FAC25126
Justification
Expansion and/or Level of Service
Sustainability:This project supports Climate Action Plan Strategy BE 7: Achieve 25% municipal building thermal “fuel switching"" from on-site
fossil fuel combustion to less carbon intensive, or carbon neutral sources by 2030.
Adding more electric vehicles to the City’s fleet is a key strategy to achieving our Climate Action Plan (CAP) goals to reduce greenhouse gas
emissions. Fast charging supports electric vehicle adoption by providing quick, convenient charging. This project specifically supports CAP
strategy TL-5.
Community Engagement: These projects encourage people to interact with staff to understand the importance of electric vehicle charging
infrastructure. Focusing on city fleet, this project does not contain an engagement component.
Health in All Policies: Electric vehicles are zero-emission vehicles, meaning there are no harmful tailpipe emissions that negatively impact air
quality.
Race & Equity: Charging stations located across the community create equitable access to infrastructure.
Stewardship: The cost to charge vehicles is decreasing and is already more cost-effective per mile to charge a vehicle when compared to gas-
powered vehicles
Useful LifeProject Name Photovoltaic & EV Charger Installation Category Equipment and Vehicles
Type Expand or enhance
Total Project Cost:$2,225,000
Total2025 2026 2027 2028 2029Expenditures 2030
2,225,000575,000 50,000 500,000Vehicles and Equipment 1,100,000
575,000 50,000 500,000 2,225,000Total1,100,000
Total2025 2026 2027 2028 2029Funding Sources 2030
2,225,000575,000 50,000 500,000CAS Fund: Utility Franchise
Fees
1,100,000
575,000 50,000 500,000 2,225,000Total1,100,000
185
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Derik Otten
2025 2030thru Department Facilities
Description
The project will continue the process of making our buildings more efficient by conducting an evaluation of entire building systems across the
cities portfolio. These studies review performance or MEP systems as well as those of that create the building envelope replacing inefficient system
with newer technology. These types of projects are co-led by Facilities and Sustainability and work directly with building occupants and staff
involved in the operations of the space.
Project #FAC25127
Justification
Asset Functionality
Useful LifeProject Name Fire Station #1 Energy Management Study Category Buildings
Type Replace or repair
Total Project Cost:$500,000
Total2025 2026 2027 2028 2029Expenditures 2030
500,000500,000Planning and Design
500,000 500,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
500,000500,000CAS Fund: Utility Franchise
Fees
500,000 500,000Total
186
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Derik Otten
2025 2030thru Department Facilities
Description
A portion of the current CIP levy will be held in reserve at the beginning of each year to address unforeseen or unplanned repairs that must be
made. The intent is that the money will be used to lessen the impact on facilities and enterprise sites operating funds, better helping those
responsible for the site to make sound decisions on proper repairs vs. band-aid solutions. The CIP committee will meet periodically each year to
review the available funds against any items that may have come up, or when possible how those funds can be used to expand other programs or
projects that didn’t make the initial funding list.
Project #FAC25200
Justification
See Summary of Facilities Improvements.
Useful LifeProject Name Asset Preservation Funding Category Buildings
Type Replace or repair
Total Project Cost:$4,450,000
Total20252026202720282029Expenditures2030
4,450,000800,000 700,000 700,000 700,000 750,000Construction 800,000
800,000 700,000 700,000 700,000 750,000 4,450,000Total800,000
Total20252026202720282029Funding Sources 2030
4,450,000800,000 700,000 700,000 700,000 750,000Construction Fund: CIP Levy 800,000
800,000 700,000 700,000 700,000 750,000 4,450,000Total800,000
187
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Zuly Marquez
2025 2030thru Department Fire
Description
For several years, the Edina Fire Department has been responding to an increasing number of emergency medical calls for service. The area of
town with the greatest growth and concentration of medical calls is the southeast quadrant of the city, south of the Crosstown and east of Minnesota
Highway 100.
The Fire Department currently operates Fire Station 2 on York Avenue next to the Southdale YMCA. Staffed with two Firefighter/Paramedics, Fire
Station 2 is not large enough to provide the level of services needed in the southeast quadrant in the future. The land is also too small to build the
size of station needed to best serve the community.
On May 4, 2022, City Council gave approval for the City to enter into a purchase agreement for the property at 4401 West 76th Street for the
purposes of building a new fire station. City Council authorized financing for up to $39 million of general obligation bonds for the land acquisition
and construction of the fire station project.
Project #FIR21008
Justification
Relocation and construction of Fire Station No. 2 near the southeast corner of the Southdale Center in Edina is imperative to the city’s attempt at
addressing the major call density in that part of the city; as well as expands the capability of offering mutual aid assistance on a regional scale. As a
provider of ambulance-based life support services in Hennepin County, Edina Fire Department must also meet Hennepin County Ordinance 9,
Emergency Medical Services. This ordinance requires among other things that the department achieve a travel time of 10 minutes to 80% of the
community for a city like Edina, with increase call for assistance within and outside of city limits these travel times will prove to become more
challenging without the relocation of Fire Station 2. It should also be noted that more than 1/3 of the response zone for Station 2 is in Richfield;
moving the station north and west of the current location will better center it and move it closer to growing areas of the community.
Housing and the population of the Southdale area has increased significantly in recent years. The Greater Southdale District Plan, adopted by the
city on December 18, 2018, reports that the population of this area grew 28% from 2000 to 2018, compared to an overall 9% population growth
citywide over the same period.
The Greater Southdale area, formerly used for primarily commercial purposes, has been transitioning in recent years to more multi-family housing
with new commercial on first floor.
The increased demand for fire and advanced life support ambulances also coincides with continued growth of the M-Health Fairview Southdale
Hospital campus. Over the past 20 years, the hospital has nearly doubled in size from 395,000 sq ft in 2001 to 720,000 sq ft in 2021.
Finally, the Greater Southdale District Plan also reports a larger percentage of older residents in this area than citywide. Aging demographics can
be linked to an increase in the calls for emergency medical response in the Southdale area.
Budget Impact/Other
Useful LifeProject Name Community Health & Safety Center Category Buildings
Type New
Total Project Cost:$26,000,000
Total20252026202720282029Expenditures2030
26,000,00026,000,000Construction
26,000,000 26,000,000Total
Total20252026202720282029Funding Sources 2030
26,000,00026,000,000CIP Bonds
26,000,000 26,000,000Total
188
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Andrew Slama
2025 2030thru Department Fire
Description
Plan for the continued growth in the northeast quadrant of the city. It is anticipated that in 5-10 years there will be a need for a station in the
general location of City Hall to support the need for improved ALS and fire response in the northern quadrants of the City. The Five Bugles Design
report recommended the:
- Acquisition of 2-4 acres of land for Proposed Station No. 3 near City Hall.
- Construction of proposed Station No. 3 as needed (assumed to be required in next 5-10 years).
Project #FIR21009
Justification
In 2018, the Fire Department hired Five Bugles Design to conduct a response time and station location study. The final report was submitted to
City Council in January 2019.The report recommended adding Fire Station 3 in the next 5 - 10 years. The new fire station would be approximately
13,400 sq. ft consisting of 3 bays, sleeping accommodations for 5 - 6 personnel. This 24-hour station would be capable of housing one ALS
ambulance crew and one engine company and space for a utility/staff vehicle.
Budget Impact/Other
Useful LifeProject Name Fire Station #3 Category Buildings
Type New
Total Project Cost:$50,000,000
Total20252026202720282029Expenditures2030
50,000,00050,000,000Construction
50,000,000 50,000,000Total
Total20252026202720282029Funding Sources 2030
50,000,00050,000,000CIP Bonds
50,000,000 50,000,000Total
189
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Andrew Slama
2025 2030thru Department Fire
Description
Replacement of equipment according to the equipment replacement schedule. This includes essential equipment such as fire trucks, ambulances,
safety equipment, emergency medical equipment and technology, among other items.
2025 Equipment Levy:
2016 Ford F350
Ambulance/Fire Truck Debt Payment 2019A GO Bond
2015 Toyota Prius C
2015 Toyota Prius C
2015 Toyota Prius C
2015 Toyota Prius C
2025 Public Safety Aid:
Mobile Air Cart Response
LUCAS 2 Chest Compression Device
Respirator Fit Tester Machine
Thermal Imager
EOC IT Equipment Hub
Zoll X-series Monitor/Defibrillator
Zoll X-series Monitor/Defibrillator
Zoll X-series Monitor/Defibrillator
Zoll X-series Monitor/Defibrillator
Zoll X-series Monitor/Defibrillator
2026 Equipment Levy:
Equip Cert Payment
Ultrasound Devices
Ambulance/Fire Truck Debt Payment 2019A GO Bond
2027 Equipment Levy:
2018 Chevrolet Tahoe
2018 Chevrolet Tahoe
Equip Cert Payment
Fire Protective Gear Dryer
Ambulance/Fire Truck Debt Payment 2019A GO Bond
Warning Siren #6 - Gleason/Dewey Hill
Warning Siren #9 -7235 France Ave.
Warning Siren #4 - 5300 Blake Rd
Warning Siren #5 - 6250 Hansen Rd
Warning System Siren (#2 - 4201 W.44th St.)
2028 Equipment Levy:
2018 Chevrolet Tahoe
2018 Chevrolet Tahoe
Equip Cert Payment
Station Alerting
Ambulance/Fire Truck Debt Payment 2019A GO Bond
2016 Toyota Prius C
2016 Toyota Prius C
2018 Toyota Prius C
2018 Toyota Prius C
2029 Equipment Levy:
Project #FIR25200 Useful LifeProject Name Fire Equipment Replacement Category Equipment and Vehicles
Type Replace or repair
Total Project Cost:$6,675,492
190
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Andrew Slama
2025 2030thru Department Fire
LUCAS 2 Chest Compression Device
LUCAS 2 Chest Compression Device
LUCAS 2 Chest Compression Device
Equip Cert Payment
Station 1 &2 Floor Scrubber
Ambulance/Fire Truck Debt Payment 2019A GO Bond
Warning Siren #3 - 7200 Metro Blvd
2030 Equipment Levy:
Equip Cert Payment
Justification
As outlined in Vision Edina, it is the mission of the City Council to provide effective and valued public services and maintain a sound public
infrastructure. Regular replacement of fire safety equipment, emergency and medical equipment and vehicles allows the city to maintain a high
level of quality service provided to the residents of the City of Edina. Timely replacement of equipment also ensures equipment reliability while
keeping maintenenace costs low.
Budget Impact/Other
Total2025 2026 2027 2028 2029Expenditures 2030
6,675,492890,500 1,044,845 1,258,995 1,403,395 1,112,350Vehicles and Equipment 965,407
890,500 1,044,845 1,258,995 1,403,395 1,112,350 6,675,492Total965,407
Total2025 2026 2027 2028 2029Funding Sources 2030
6,300,292515,300 1,044,845 1,258,995 1,403,395 1,112,350Construction Fund: Equipment
Levy
965,407
375,200375,200Public Safety Aid
890,500 1,044,845 1,258,995 1,403,395 1,112,350 6,675,492Total965,407
191
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Tom Swenson
2025 2030thru Department Park & Recreation
Description
This project involves replacement of the Normandale Park shelter building with a more modern design similar to Countryside and Pamela Park.
Normandale Park is a 10 acre neighborhood park. Staff would complete a master plan of Normandale Park is 2027 and recommends the
replacement of the playground in 2028.
ENVIRONMENTAL CONSIDERATIONS:
Replacing this building will upgrade the lighting and heating systems with more energy efficient equipment.
Project #15-048
Justification
The Normandale Park shelter building was designed and build in the 1970ss and no longer meets resident's needs and expectations. A park
building assessment was completed in conjunction with the Parks, Recreation & Trails Strategic Plan and the shelter building was assessed to be in
poor condition. The building requires extensive maintenance, is poorly insulated, and visually intimidating with no windows, and was
recommended for scheduled replacement.
Useful LifeProject Name Normandale Park Shelter Building Replacement Category Buildings
Type Replace or repair
Total Project Cost:$1,040,000
Total2025 2026 2027 2028 2029Expenditures 2030
1,040,00040,000 1,000,000Construction
40,000 1,000,000 1,040,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
1,040,00040,000 1,000,000Construction Fund: CIP Levy
40,000 1,000,000 1,040,000Total
192
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Tom Swenson
2025 2030thru Department Park & Recreation
Description
Creek Valley park is an active park within our parks system, with two soccer fields that are utilized by private athletic leagues and the Edina Public
School system. The current system is 35 years old, and is due for replacement. We are unable to secure parts for this system, uses an excess amount
of water and is not efficient. It is important to note that the athletic fields are on school district property but we maintain them.
Project #17-143
Justification
This is a part of our City Work plan to maintain optimum field operations.
Useful LifeProject Name Creek Valley Irrigation Category Parks
Type Replace or repair
Total Project Cost:$50,000
Total2025 2026 2027 2028 2029Expenditures 2030
50,00050,000Vehicles and Equipment
50,000 50,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
50,00050,000Special Park Improvement
Levy
50,000 50,000Total
193
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Tom Swenson
2025 2030thru Department Park & Recreation
Description
This is a project to replace the existing playground structure and safety surface at Tingdale Park.
Project #19-763
Justification
See Summary of Playground Improvements
Useful LifeProject Name Tingdale Park Playground Replacement Category Parks
Type Replace or repair
Total Project Cost:$155,000
Total2025 2026 2027 2028 2029Expenditures 2030
155,000155,000Vehicles and Equipment
155,000 155,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
155,000155,000Special Park Improvement
Levy
155,000 155,000Total
194
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Perry Vetter
2025 2030thru Department Park & Recreation
Description
This project includes the repair and replacement of general park and recreation park assets and infrastructure. Final evaluation of the amenity will
be made in order to continue replacement of park equipment prior to scheduled replacement to ensure improvements are made as needed. This
includes items such as tennis, basketball and other hard court repair and replacement; fencing for tennis, softball and baseball; replacement of
hockey rinks, basketball standards as well as other property in the open such as benches, tables, drinking fountains and trash receptacles. Regular
repair and replacement of these amenities will extend the life of these facilities.
ENVIRONMENTAL CONSIDERATIONS:
Per city policy staff will incorporate the use of recycled materials in products as available to offset these replacements.
Project #P&R21001
Justification
As outlined in Vision Edina it is the mission of the City Council to provide effective and valued public services and maintain a sound public
infrastructure. This is part of our City Work Plan to maintain optimum facility operations.
Useful LifeProject Name General Park Asset Equipment Replacement Category Equipment and Vehicles
Type Replace or repair
Total Project Cost:$250,000
Total20252026202720282029Expenditures2030
250,00050,000 50,000 50,000 50,000Construction 50,000
50,000 50,000 50,000 50,000 250,000Total50,000
Total20252026202720282029Funding Sources 2030
200,00050,000 50,000 50,000Construction Fund: Equipment
Levy 50,000
50,00050,000Construction Fund: CIP Levy
50,000 50,000 50,000 50,000 250,000Total50,000
195
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Perry Vetter
2025 2030thru Department Park & Recreation
Description
This project schedules the repair and replacement of existing outdoor athletic lighting for fields and rinks. This project does not expand lighting to
areas that currently does not have lights.
Project #P&R21003
Justification
As outlined in Vision Edina it is the mission of the City Council to provide effective and valued public services and maintain a sound public
infrastructure. This is part of our City Work Plan to maintain optimum facility operations.
Useful LifeProject Name Outdoor Athletic Field Lighting Category Infrastructure
Type Replace or repair
Total Project Cost:$900,000
Total2025 2026 2027 2028 2029Expenditures 2030
900,000180,000 180,000 180,000 180,000Installation/Maintenance 180,000
180,000 180,000 180,000 180,000 900,000Total180,000
Total2025 2026 2027 2028 2029Funding Sources 2030
900,000180,000 180,000 180,000 180,000Special Park Improvement
Levy
180,000
180,000 180,000 180,000 180,000 900,000Total180,000
196
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Tom Swenson
2025 2030thru Department Park & Recreation
Description
This project would improve the field condition and enhancements for programmed athletic fields in Edina Parks. Improvements would increase
field drainage, field health, player safety, and sustainability. Improvement would increase field reliability for associations and users as well as
improved participant experience.
Project #P&R21006
Justification
This field could support more youth athletics activities if the conditions are improved.
Useful LifeProject Name Athletic Field Improvements Category Parks
Type Replace or repair
Total Project Cost:$1,400,000
Total2025 2026 2027 2028 2029Expenditures 2030
1,050,000350,000 350,000Construction 350,000
350,000 350,000 1,050,000Total350,000
Total2025 2026 2027 2028 2029Funding Sources 2030
1,050,000350,000 350,000Construction Fund: CIP Levy 350,000
350,000 350,000 1,050,000Total350,000
197
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Perry Vetter
2025 2030thru Department Park & Recreation
Description
This project includes master planning for Strachauer Park, a 4.5 acre neighborhood park.
This project is the second phase of implementation for the Strachauer Park Master Plan. This phase includes the removal and relocation of the park
shelter. Design for this phase will incorporate park and programming requirements as well as community feedback.
Project #P&R21039
Justification
The shelter building was assessed to be in poor condition. The building requires extensive maintenance.
Useful LifeProject Name Strachauer Park Master Plan Phase II Category Parks
Type Expand or enhance
Total Project Cost:$1,100,000
Total2025 2026 2027 2028 2029Expenditures 2030
1,100,0001,100,000Construction
1,100,000 1,100,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
1,100,0001,100,000Special Park Improvement
Levy
1,100,000 1,100,000Total
198
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Tom Swenson
2025 2030thru Department Park & Recreation
Description
This is a project to replace the existing playground structure and safety surface at Normandale Park.
Project #P&R21046
Justification
See Summary of Playground Improvements
Useful LifeProject Name Normandale Park Playground Equipment Category Equipment and Vehicles
Type Replace or repair
Total Project Cost:$200,000
Total2025 2026 2027 2028 2029Expenditures 2030
200,000200,000Vehicles and Equipment
200,000 200,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
200,000200,000Construction Fund: CIP Levy
200,000 200,000Total
199
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Tom Swenson
2025 2030thru Department Park & Recreation
Description
This is a project to replace the existing playground structure and safety surface at Heights Park.
Project #P&R21047
Justification
See Summary of Playground Improvements
Useful LifeProject Name Heights Park Playground Equipment Category Equipment and Vehicles
Type Replace or repair
Total Project Cost:$175,000
Total2025 2026 2027 2028 2029Expenditures 2030
175,000175,000Vehicles and Equipment
175,000 175,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
175,000175,000Construction Fund: CIP Levy
175,000 175,000Total
200
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Tom Swenson
2025 2030thru Department Park & Recreation
Description
This is a project to replace the existing playground structure and safety surface at Sherwood Park.
Project #P&R21048
Justification
See Summary of Playground Improvements
Useful LifeProject Name Sherwood Park Playground Equipment Category Equipment and Vehicles
Type Replace or repair
Total Project Cost:$150,000
Total2025 2026 2027 2028 2029Expenditures 2030
150,000150,000Vehicles and Equipment
150,000 150,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
150,000150,000Special Park Improvement
Levy
150,000 150,000Total
201
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Tom Swenson
2025 2030thru Department Park & Recreation
Description
This is a project to replace the existing playground structure and safety surface at Kojetin Park.
Project #P&R21049
Justification
See Summary of Playground Improvements
Useful LifeProject Name Kojetin Park Playground Equipment Category Equipment and Vehicles
Type Replace or repair
Total Project Cost:$165,000
Total2025 2026 2027 2028 2029Expenditures 2030
165,000165,000Vehicles and Equipment
165,000 165,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
165,000165,000Special Park Improvement
Levy
165,000 165,000Total
202
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Perry Vetter
2025 2030thru Department Park & Recreation
Description
Replacement of and update to outdoor and indoor public facing furniture. Many of the amenities are outdated, mismatched and have no draw to
users. Earlier this year, new outdoor furniture was installed at the Golf Course and at the Aquatic Center and was welcomed and positively received.
$40,000 for furniture at Centennial Lakes Park and $25,000 for furniture at Edinborough Park.
Project #P&R23100
Justification
Replacement of and update to outdoor and indoor public facing furniture at these two locations will benefit users and visitors to each location.
Useful LifeProject Name CLP & EP Interior and Exterior Public Furniture Category Equipment and Vehicles
Type Replace or repair
Total Project Cost:$40,000
Total2025 2026 2027 2028 2029Expenditures 2030
40,00040,000Vehicles and Equipment
40,000 40,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
40,00040,000Federal ARPA
40,000 40,000Total
203
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Tom Swenson
2025 2030thru Department Park & Recreation
Description
Replace equipment according to the equipment replacement schedule. The Parks Maintenance Department has almost $2 million of equipment
covered under this program. Types of equipment include small machinery, mowers, passenger vehicles and heavy equipment. Most of this
equipment has an estimated useful life of between 10-20 years.
2025:
2008 Ford Ranger
2013 GMC Sierra
60" turf Sweeper
2010 Terex Track Loader
2011 Ford XLT Ranger 4x4
2013 Chevrolet Silverado 2500HD
2026:
2013 Chevrolet Silverado 2500HD
Toro Groundsmaster 5910
2015 John Deere 1570 Mower
2011 Ford Ranger
2013 F-450
2015 Ford F250
2010 Farm King Snowblower
2014 John Deere X540 Tractor
2015 Toro 2Master
2027:
2016 Toro SandPro 2040Z
2009 Silverado 1500
2017 Exmark Lazer Mower
2017 Bobcat 5600
2016 Toro GTX Workman
2006 Jacovsen Truck Cart
2028:
GPS Line Marking System
Toro Groundmaster 3500 Mower
2016 Chevrolet Colorado
2016 Polaris Ranger ATV
2004 John Deere Tractor
2029:
2015 Land Pride Mower 4216
2011 Freightliner M2106
2030:
2010 Vermeer Brush Chipper
2015 John Deere 5115M Tractor
Groundsmaster 3280-D Mower
Groundsmaster 3280-D Mower
2020 Ford F550
Project #P&R23120 Useful LifeProject Name Park Maintenance Equip Replacement - Vehicles Category Equipment and Vehicles
Type Replace or repair
Total Project Cost:$1,693,750
204
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Tom Swenson
2025 2030thru Department Park & Recreation
Justification
As outlined in Vision Edina, it is the mission of the City Council is to provide effective and valued public services and maintain a sound public
infrastructure. Regular updates to equipment helps to keep maintenance costs low but most importantly allows us to keep maintaining our parks to
high standards. Breakdowns delay performance. We are being fiscally responsible with our fleet as is outlined in our IQS and we cannot perform
the functions of the Park Maintenance division without a reliable fleet.
Total2025 2026 2027 2028 2029Expenditures 2030
1,693,750329,300 411,700 234,250 223,500 191,000Vehicles and Equipment 304,000
329,300 411,700 234,250 223,500 191,000 1,693,750Total304,000
Total2025 2026 2027 2028 2029Funding Sources 2030
1,693,750329,300 411,700 234,250 223,500 191,000Construction Fund: Equipment
Levy
304,000
329,300 411,700 234,250 223,500 191,000 1,693,750Total304,000
205
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Tom Swenson
2025 2030thru Department Park & Recreation
Description
This project replaces the existing playground structure and safety surface at Alden Park.
Project #P&R23203
Justification
See Summary of Playground Improvements.
Useful LifeProject Name Alden Park Playground Replacement Category Parks
Type Replace or repair
Total Project Cost:$185,000
Total2025 2026 2027 2028 2029Expenditures 2030
185,000185,000Vehicles and Equipment
185,000 185,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
185,000185,000Special Park Improvement
Levy
185,000 185,000Total
206
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Tom Swenson
2025 2030thru Department Park & Recreation
Description
This is a project to replace the existing playground structure and safety surface at McGuire Park.
Project #P&R23206
Justification
See Summary of Playground Improvements
Useful LifeProject Name McGuire Park Playground Equipment Replacement.Category Parks
Type Replace or repair
Total Project Cost:$250,000
Total2025 2026 2027 2028 2029Expenditures 2030
250,000250,000Vehicles and Equipment
250,000 250,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
250,000250,000Special Park Improvement
Levy
250,000 250,000Total
207
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Tom Swenson
2025 2030thru Department Park & Recreation
Description
This project will provide for infrastructure enhancements at the Van Valenburg dog park.
Project #P&R23207
Justification
The dog park at Van Valkenburg is in need of repairs and for the provision of water for park users.
Useful LifeProject Name Off Leash Dog Park Investments Category Parks
Type Expand or enhance
Total Project Cost:$10,000
Total2025 2026 2027 2028 2029Expenditures 2030
10,00010,000Construction
10,000 10,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
10,00010,000Special Park Improvement
Levy
10,000 10,000Total
208
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Tom Swenson
2025 2030thru Department Park & Recreation
Description
This is a project to replace the existing playground structure and safety surface at Pamela Park.
Project #P&R23208
Justification
See Summary of Playground Improvements
Useful LifeProject Name Pamela Park Playground Equipment Replacement Category Parks
Type Replace or repair
Total Project Cost:$300,000
Total2025 2026 2027 2028 2029Expenditures 2030
300,000300,000Vehicles and Equipment
300,000 300,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
300,000300,000Special Park Improvement
Levy
300,000 300,000Total
209
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Tom Swenson
2025 2030thru Department Park & Recreation
Description
This is a project to replace the existing playground structure and safety surface at York Park.
Project #P&R23212
Justification
See summary of Playground Improvements.
Useful LifeProject Name York Park Playground Replacement Category Parks
Type Replace or repair
Total Project Cost:$175,000
Total2025 2026 2027 2028 2029Expenditures 2030
175,000175,000Vehicles and Equipment
175,000 175,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
175,000175,000Special Park Improvement
Levy
175,000 175,000Total
210
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Perry Vetter
2025 2030thru Department Park & Recreation
Description
"Fred Richards Park, 4400 Parklawn Ave., is being created from the former Fred Richards Executive Golf Course, which closed in 2014. It
alsoincludes what was formerly known as Lake Edina Park. The 43-acre site, almost double the size of Centennial Lakes Park, will become a
multi-use park for a variety of year-round activities.Fred Richards Park will subtly divide into sections, providing different experiences for
people and nature:(1)Central Green with pickleball courts, basketball courts, lawn games area, stage/pavilion area, clubhouse renovation,
landscaping, turf and walkways, parking and access via West 77th Street, lighting, signs and infrastructure.(2)The Nature Bank with native
vegetation restoration and establishment, trees and shrubs, play nodes, wildlife habitat structures, boardwalk and trail, seating, signs and
infrastructure.(3)Great Lawn and Loop with a pedestrian bridge restoration and new trail, great lawn area with high-quality drainage, picnic
pavilion, traditionaland bike playgrounds, lighting, seating, signs and infrastructure."
Project #P&R25100
Justification
Expansion and/or Level of Service
Useful LifeProject Name Fred Richards Park Category Parks
Type Expand or enhance
Total Project Cost:$16,255,000
Total2025 2026 2027 2028 2029Expenditures 2030
16,255,0005,500,000 9,250,000 805,000 700,000Construction
5,500,000 9,250,000 805,000 700,000 16,255,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
16,255,0005,500,000 9,250,000 805,000 700,000Local Option Sales Tax
5,500,000 9,250,000 805,000 700,000 16,255,000Total
211
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Perry Vetter
2025 2030thru Department Park & Recreation
Description
"At 500 acres, Braemar Park, 6364 John Harris Drive, is the largest recreational space in Edina. It is home to Braemar Golf Course, Braemar
GolfDome, Braemar Arena, Braemar Field, Courtney Fields and the South Metro Public Safety Training Facility.While most of the land in
Braemar Park already is in use, several opportunities for improvements were identified and explored starting in 2017 with the help of resident input
at community meetings and through online surveys.The Braemar Park Master Plan balances the most-sought amenities with the park's
environmental and natural resource needs. It includes an estimated $8.1 million in improvements, including: walking trails, mountain biking trails,
cross-country skiing trails, pickleball and platform tennis courts, baseball complex improvements, wayfinding signs and trail connections, natural
resource restoration, improved parking and access to Braemar Golf Course, Braemar Arena and Courtney Fields.Braemar Arena is home to
Edina High School, the Edina Hockey Association, Breakaway Academy and the Braemar-City of Lakes Figure Skating Club. Braemar Arena is
one of the busiest ice arenas in the entire state; approximately 500,000 annual visits are recorded there from residents of 158 Minnesota
communities, 12 states and one other country. The project covers $13.5 million in capital rehabilitation improvements in Braemar Arena’s
operating infrastructure, including: dasherboard and glass safety system replacements, flooring replacements, ice refrigeration system and delivery
replacements, heat and boiler replacements for all rinks, electrical system replacements for all rinks, window and roofing replacements and repairs,
hot water system replacements, domestic water distribution system replacements, sanitary system and fixture replacements, locker room
rehabilitation, restroom rehabilitation, permafrost removal in East Rink, energy efficiency improvements and insulation, ADA route and
walkwayimprovements, ADA door and access improvements, ADA restroom improvements, ADA viewing and seating improvements,
waterproofing and moisture control, fire protection and security improvement."
Project #P&R25101
Justification
Expansion and/or Level of Service
Useful LifeProject Name Braemar Park & Arena Category Buildings
Type Expand or enhance
Total Project Cost:$47,140,000
Total2025 2026 2027 2028 2029Expenditures 2030
47,140,00011,850,000 17,320,000 15,820,000 2,150,000Planning and Design
11,850,000 17,320,000 15,820,000 2,150,000 47,140,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
47,140,00011,850,000 17,320,000 15,820,000 2,150,000Local Option Sales Tax
11,850,000 17,320,000 15,820,000 2,150,000 47,140,000Total
212
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Tom Swenson
2025 2030thru Department Park & Recreation
Description
This project involves the replacement of Highland Park shelter building. Highlands Park was the city's first implemented park improvement
project. Fields and landscaping were completed in 1960 and the shelter facility was built in the 1970s. This shelter is in poor condition and no
longer meets resident's needs. This building is poorly insulated, and lacks windows, making it unwelcoming, therefore serving limited functions.
Project #P&R25102
Justification
Asset Functionality","Expansion and/or Level of Service
Sustainability - New shelter would exceed sustainability goals and initiatives.
Stewardship - Replacing the shelter reduces future costs of maintenance.
Useful LifeProject Name Highlands Park Shelter Replacement Category Parks
Type Replace or repair
Total Project Cost:$1,250,000
Total2025 2026 2027 2028 2029Expenditures 2030
1,250,000Installation/Maintenance 1,250,000
1,250,000Total1,250,000
Total2025 2026 2027 2028 2029Funding Sources 2030
1,250,000Construction Fund: CIP Levy 1,250,000
1,250,000Total1,250,000
213
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Rachel Finberg
2025 2030thru Department Park & Recreation
Description
Yorktown Park located in the Promenade neighborhood bordering Richfield is one of Edina's smallest parks. With the relocation of Fire Station 2,
currently house on this parkland, this small area park requires a study to determine vision and future needs. This study would evaluate existing
recreational features including skate park, community gardens, and regional trail link. This would require collaboration with Three Rivers and City
of Richfield to incorporate trail needs and recreational linkages to Adams Hill Park.
Project #P&R25103
Justification
Expansion and/or Level of Service
Sustainability - Master Plan process ensures sustainability and project longevity by reducing project waste. This process promotes smart and
strategic growth.
Community Engagement - This project would engage community on collaboration level to create park infrastructure and amenities that support
community needs.
Useful LifeProject Name Yorktown Park Master Plan Category Parks
Type Expand or enhance
Total Project Cost:$790,000
Total2025 2026 2027 2028 2029Expenditures 2030
790,00040,000Planning and Design 750,000
40,000 790,000Total750,000
Total2025 2026 2027 2028 2029Funding Sources 2030
790,00040,000Construction Fund: CIP Levy 750,000
40,000 790,000Total750,000
214
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Rachel Finberg
2025 2030thru Department Park & Recreation
Description
This is a project to replace the existing playground structure and safety surface at Chowen Park.
Project #P&R25104
Justification
Asset Functionality
Stewardship - Replacing the playground equipment will reduce staff time spent on repairs and improve safety.
Useful LifeProject Name Chowen Park Playground Improvement Category Parks
Type Replace or repair
Total Project Cost:$350,000
Total2025 2026 2027 2028 2029Expenditures 2030
350,000Installation/Maintenance 350,000
350,000Total350,000
Total2025 2026 2027 2028 2029Funding Sources 2030
350,000Construction Fund: CIP Levy 350,000
350,000Total350,000
215
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Rachel Finberg
2025 2030thru Department Park & Recreation
Description
This is a project to replace the existing playground structure and safety surface at Countryside Park.
Project #P&R25105
Justification
Expansion and/or Level of Service","Asset Functionality
Stewardship - Replacing the playground equipment will reduce staff time spent on repairs and improve safety.
Useful LifeProject Name Countryside Playground Replacement Category Parks
Type Replace or repair
Total Project Cost:$315,000
Total2025 2026 2027 2028 2029Expenditures 2030
315,000315,000Vehicles and Equipment
315,000 315,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
315,000315,000Construction Fund: CIP Levy
315,000 315,000Total
216
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Tom Swenson
2025 2030thru Department Park & Recreation
Description
Pathway and parking replacement and enhancements for park projects. These projects will evaluate capacity, site conditions, and accessibility
needs for parks.
Project #P&R25106
Justification
Expansion and/or Level of Service","Asset Functionality
Useful LifeProject Name Park Pathways and Parking Project Improvements Category Parks
Type Replace or repair
Total Project Cost:$525,000
Total2025 2026 2027 2028 2029Expenditures 2030
525,00025,000 100,000 100,000 100,000 100,000Construction 100,000
25,000 100,000 100,000 100,000 100,000 525,000Total100,000
Total2025 2026 2027 2028 2029Funding Sources 2030
525,00025,000 100,000 100,000 100,000 100,000Construction Fund: CIP Levy 100,000
25,000 100,000 100,000 100,000 100,000 525,000Total100,000
217
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Perry Vetter
2025 2030thru Department Park & Recreation
Description
Continue to evaluate and identify accessibility barriers within parks and recreational programming. Improvements may include surfacing,
pathways, signage, and other needs.
Project #P&R25107
Justification
Health, Safety & Regulatory Compliance
Useful LifeProject Name Parks Accessibility Improvements Category Parks
Type Expand or enhance
Total Project Cost:$525,000
Total2025 2026 2027 2028 2029Expenditures 2030
525,00025,000 100,000 100,000 100,000 100,000Planning and Design 100,000
25,000 100,000 100,000 100,000 100,000 525,000Total100,000
Total2025 2026 2027 2028 2029Funding Sources 2030
525,00025,000 100,000 100,000 100,000 100,000Construction Fund: CIP Levy 100,000
25,000 100,000 100,000 100,000 100,000 525,000Total100,000
218
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Rachel Finberg
2025 2030thru Department Park & Recreation
Description
Project includes replacement and enhancement of existing picnic shelter to accommodate user needs and accessibility.
Project #P&R25108
Justification
Asset Functionality
Useful LifeProject Name Utley Park Shelter Replacement Category Parks
Type Replace or repair
Total Project Cost:$60,000
Total2025 2026 2027 2028 2029Expenditures 2030
60,00060,000Installation/Maintenance
60,000 60,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
60,00060,000Construction Fund: CIP Levy
60,000 60,000Total
219
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Rachel Finberg
2025 2030thru Department Park & Recreation
Description
Replacement of existing Picnic Pavilion and garden gathering space. Maintenance and repairs have extended useful life of exiting shelter but a
new structure would increase accessibility and useful functions. Design and accommodations will include integration of community, garden
council, and historic society needs.
Project #P&R25110
Justification
Asset Functionality
Useful LifeProject Name Arneson Park Shelter Replacement Category Parks
Type Replace or repair
Total Project Cost:$75,000
Total2025 2026 2027 2028 2029Expenditures 2030
75,00075,000Installation/Maintenance
75,000 75,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
75,00075,000Construction Fund: CIP Levy
75,000 75,000Total
220
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Rachel Finberg
2025 2030thru Department Park & Recreation
Description
Rosland Park located off crosstown in the heart of Edina embodies the profile of a special use park. Home of the Edina Aquatic Center and Edina
Art Center it provides vital services to Edina and the community as a whole. With changes to the Art Center and identified upgrades for the
Aquatic Center, this park requires evaluation and community input for its long term goals and vision. This park contains one of a kind Edina
offering such as an inclusive playground, disc golf course, fishing pier, pickleball courts, and sand volleyball. A study would help determine how
community and recreational trends can be incorporated into future project plans.
Project #P&R25111
Justification
Expansion and/or Level of Service
Sustainability - The most recent park plan was done in 1958 and project and amenities have been added beyond these features. To ensure park
sustainability and longevity it is important to assess existing needs and incorporate future needs. Planning helps eliminate waste in the form of
both materials and time, reducing disturbances to residents and natural resources.
Community Engagement - This project allow for a full community engagement and full collaboration on the future of Rosland Park. Engagement
would include neighbors, residents, users, commissioners, and city council. Engagement will ensure features meet needs and are accessible.
Health in all policies - A long term plan for Rosland Park will help to maximize its recreational potential as well as its health benefits. Features
that maximize physical and mental health can be incorporated, as well as natural resource benefits.
Race & Equity - This plan will review and evaluate all barriers to the current Rosland Park programming and also integrate opportunities in a new
design.
Stewardship - This projects plan will allow for long term growth and decision making within the park. It will accommodate phasing and smart
growth.
Useful LifeProject Name Rosland Park Master Plan Category Parks
Type Expand or enhance
Total Project Cost:$100,000
Total2025 2026 2027 2028 2029Expenditures 2030
100,000100,000Planning and Design
100,000 100,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
100,000100,000Construction Fund: CIP Levy
100,000 100,000Total
221
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Rachel Finberg
2025 2030thru Department Park & Recreation
Description
This project includes the replacement of the picnic shelter for Fox Meadow Park. The existing structure will need to be removed and a new
structure installed that meet community and site needs.
Project #P&R25113
Justification
Asset Functionality
Useful LifeProject Name Fox Meadow Shelter Replacement Category Parks
Type Replace or repair
Total Project Cost:$55,000
Total2025 2026 2027 2028 2029Expenditures 2030
55,00055,000Construction
55,000 55,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
55,00055,000Special Park Improvement
Levy
55,000 55,000Total
222
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Patty McGrath
2025 2030thru Department Parks: Aquatic Center
Description
2025 - Furniture Replacement, Electronic Signage Replacement
Every year the Edina Aquatic Center has nearly 100,000 member and guest visits. For their comfort, we provide chaise lounge chairs on both sides
of the 50 meter pool and surrounding the zero depth pool. Previously, there were 380 lounge chairs and in recent years we have had to discard 5-7
chairs per season because they were beyond repair, leaving us with about 350 lounge chairs. The capacity of the facility is 1,000 people and
frequently, every chair we have is in use. The current chairs are made of a steel frame and thick vinyl straps and range from 15-20 years old. Given
the high volume of patrons and as the chairs age, more and more straps are breaking and are not able to be repaired. We have systematically
removed lounge chairs from the deck when two or more straps are broken to ensure the safety of our guests. In addition, many of our older guests
have difficulty sitting down and getting up from the chairs because they are so low to the ground and have requested more upright chairs to be
available for their use. Complete replacement would take place over a three year period.
We are missing a valuable opportunity to promote our facility to the high volume of traffic in the 66th Street and Valley View area and an
electronic sign would provide that.
2026 - Pool Painting & Concession Equipment
Main pool and zero depth pool painting.The main pool and zero depth pool require painting every 3 years. Replace aging concession equipment to
improve operational efficiency and reduce energy costs.
2029 - Pool Painting
Project #P&R25117
Justification
Expansion and/or Level of Service
Sustainability - Current equipment is more than 18 years old and new equipment will use less energy.
Community Engagement - Fast, efficient concession sales are critical to a positive patron experience and to achieving the budget of the Aquatic
Center.
Race and Equity - Everyone will benefit when the operation runs smoothly and the wait time is shorter.
Useful LifeProject Name Aquatic Center Pool Paint, Equip & Signage Rplcmnt Category Equipment and Vehicles
Type Replace or repair
Total Project Cost:$558,100
Total2025 2026 2027 2028 2029Expenditures 2030
558,100172,100 286,000 100,000Vehicles and Equipment
172,100 286,000 100,000 558,100Total
Total2025 2026 2027 2028 2029Funding Sources 2030
558,100172,100 286,000 100,000CIP Bonds
172,100 286,000 100,000 558,100Total
223
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Rachel Finberg
2025 2030thru Department Parks: Aquatic Center
Description
Based off an existing conditions assessment, initiated after a critical electrical failure and shutdown, the pool pump house facility has extensive
repairs needed. To accommodate code upgrades and energy efficiency upgrades a 15% larger facility is required. Project needs include pump
apparatus, electrical supply and distribution, new surge tanks, water treatment system, and code compliance upgrades.
Project #P&R25119
Justification
Asset Functionality
Sustainabilty - Upgrades to facility would include energy efficiencies. A solar study will also be initiated.
Useful LifeProject Name Aquatic Center Filter Room Category Buildings
Type Replace or repair
Total Project Cost:$4,000,000
Total2025 2026 2027 2028 2029Expenditures 2030
4,000,0004,000,000Installation/Maintenance
4,000,000 4,000,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
4,000,0004,000,000CIP Bonds
4,000,000 4,000,000Total
224
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Jesse Buchholz
2025 2030thru Department Parks: Arena
Description
New zambonis for Braemar Arena. The renovation and expansion will provide for one but the arena has multiple zambonis that are well beyond
their useful life.
ENVIRONMENTAL CONSIDERATIONS:
The Zamboni is powered by a lithium ion battery. This is the most green technology in the ice resurfacing business. In addition, a self leveling
system would be included that would reduce the amount of ice thus reducing the energy used to freeze the ice.
Project #17-028
Justification
Zamboni's are a necessity to ice arena operations. When a Zamboni ages you will start to see imperfections in the ice due to the machine not
operating properly. During the winter months and the Backyard Rink is in operation we use all four Zamboni's, therefore it is very important that
all machines are in proper working condition.
Useful LifeProject Name Braemar Arena Zamboni Category Equipment and Vehicles
Type Replace or repair
Total Project Cost:$400,000
Total2025 2026 2027 2028 2029Expenditures 2030
400,000200,000 200,000Vehicles and Equipment
200,000 200,000 400,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
400,000200,000 200,000Construction Fund: Equipment
Levy
200,000 200,000 400,000Total
225
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Jesse Buchholz
2025 2030thru Department Parks: Braemar Field
Description
Replace sports turf and dome fabric shell at Braemar Field. The existing turf is experiencing issues due to stormwater managemennt design and turf
is having to be replaced in sections due to this. This will shorten the useful life of the turf.
Project #P&R25125
Justification
Asset Functionality
Sustainability - New turf and fabric shell would provide energy efficiencies.
Community Engagement - Field surface and structure will be safe for users.
Health in all policies - Safe turf and building envelope will allow users of all ages, youth athletic associations, adults and others to continue to
utilize the space for physical activity, community and socialization.
Race and equity - Space would be inclusive for all users and continue to be a high-use facility for all of the community.
Stewardship - A new turf field and shell allows for efficiencies in maintenance and provide another 15-20 years of use for the facility.
Useful LifeProject Name Braemar Field Turf & Shell Replacement Category Land
Type Replace or repair
Total Project Cost:$2,300,000
Total2025 2026 2027 2028 2029Expenditures 2030
2,300,0002,300,000Installation/Maintenance
2,300,000 2,300,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
2,300,0002,300,000Braemar Field Fund
2,300,000 2,300,000Total
226
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Jesse Buchholz
2025 2030thru Department Parks: Braemar Field
Description
Purchase and install a second coiled heater for Braemar Field. The existing insulation had to be discarded. In order to maintain a comfortable user
temp and to provide a backup, a second coiled heater is recommended. The existing heater is not adequate for the space and is undersized for our
dome size.
Project #P&R25126
Justification
Asset Functionality
Sustainability: Adding a second coiled heater would provide a more comfortable environmennt for users and be more energy efficient.
Community Engagement: During the winter months, the temp for users and guests would allow for a better overall experience
Health in All Policies: A more comfortable temperature inside the dome would provide more opportunities and access for use. The community's
older demographic would feel safer in a better temp controlled environment.
Race & Equity: A warmer and safer space would allow for great accessiblity and use for walkers, renters, guests and program participants.
Stewardship: A second heater would provide a backup if we had a failure with the existing heater and also provide for savings in service and
maintenance.
Useful LifeProject Name Braemar Field Heater Category Equipment and Vehicles
Type Expand or enhance
Total Project Cost:$400,000
Total2025 2026 2027 2028 2029Expenditures 2030
400,000400,000Vehicles and Equipment
400,000 400,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
200,000200,000Construction Fund:
Grants/Donations
200,000200,000Braemar Field Fund
400,000 400,000Total
227
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Jesse Buchholz
2025 2030thru Department Parks: Braemar Field
Description
The Braemar Field Turf is experiencing numerous sink holes due to the design of the stormwater management system below the field surface. Turf
is getting comprised and has been non-usable for weeks at a time due to these issues. A redesign of the system is needed to continue to have safe
and playable surface at this site.
Project #P&R25127
Justification
Asset Functionality, Health, Safety & Regulatory Compliance
Sustainability: Stormwater needs to be rerouted so as not to impede underlying system for drainage.
Community Engagement: Turf needs to be level and safe for users to be able to utilize. A redesign of the sub surface stormwater system allows the
city to continue to provide a year-round facility for play and physical activity.
Health in All Policies: Turf surface is needed in order to be able to provide a year-round facility for exercise, play and programming.
Race & Equity: Braemar Field provides a community location for all ages and abilities to exercise, play and socialize on a safe surface
Stewardship: Providing a long-term solution to the stormwater issue will allow the city to keep a synthetic turf facility available to the public and
users on a year-round basis for years to come.
Useful LifeProject Name Braemar Field Stormwater Design Category Parks
Type New
Total Project Cost:$75,000
Total2025 2026 2027 2028 2029Expenditures 2030
75,00075,000Planning and Design
75,000 75,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
75,00075,000Braemar Field Fund
75,000 75,000Total
228
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Tiffany Bushland
2025 2030thru Department Parks: Centennial Lakes Park
Description
The 2005 Chevrolet pickup truck at Centennial Lakes was originally scheduled to be replaced in 2015 and again in 2018 but was removed due to
funding constraints. Under the vehicle scoring criteria used by the Public Works mechanics, this vehicle is due for replacement. This vehicle is
used for plowing the park pathways and ice skating rink in the winter months and for general hauling in the other months.
ENVIRONMENTAL CONSIDERATIONS:
A new vehicle would offer lower emissions which would help to achieve the City goal of a 25% reduction in emissions by 2025. We would
consider both an electric vehicle as well as a hybrid vehicle for this replacement.
Project #17-039
Justification
As outlined in Vision Edina it is the mission of the City Council to provide effective and valued public services and maintain a sound public
infrastructure.
Useful LifeProject Name Centennial Lakes Vehicle Replacement Category Equipment and Vehicles
Type Replace or repair
Total Project Cost:$40,000
Total2025 2026 2027 2028 2029Expenditures 2030
40,00040,000Vehicles and Equipment
40,000 40,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
40,00040,000Construction Fund: Equipment
Levy
40,000 40,000Total
229
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Tiffany Bushland
2025 2030thru Department Parks: Centennial Lakes Park
Description
Add free public Wi-Fi in center portion of Centennial Lakes Park.
Project #P&R25130
Justification
Expansion and/or Level of Service
Race and Equity - Provide free service to public in highly populated, diverse area of City
Stewardship - Contributes to a better connected society.
Useful LifeProject Name Centennial Lakes Park Public Wi-Fi Category Parks
Type Expand or enhance
Total Project Cost:$40,000
Total2025 2026 2027 2028 2029Expenditures 2030
40,00040,000Vehicles and Equipment
40,000 40,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
40,00040,000Construction Fund: CIP Levy
40,000 40,000Total
230
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Derik Otten
2025 2030thru Department Parks: Centennial Lakes Park
Description
Centennial Lakes Park has a large artistic fountain (seasonal) that greats visitors to the park. The fountain has suffered damaged to its internal
components and needs repairs and cleaning to make it operational.
Project #P&R25145
Justification
Asset Functionality
Stewardship - By providing preventative maintenance and scheduled repairs and replacement the city is able to extend the useful life of equipment
and structures thus extending the useful life of the buildings ensuring their use by future generations. This includes minor maintenance like
cleaning carpets and painting and major maintenance such as replacement of HVAC, plumbing, and electrical service equipment.
Useful LifeProject Name Centennial Lakes Entrance Fountain Repair Category Parks
Type Replace or repair
Total Project Cost:$150,000
Total2025 2026 2027 2028 2029Expenditures 2030
150,000150,000Installation/Maintenance
150,000 150,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
150,000150,000Construction Fund: CIP Levy
150,000 150,000Total
231
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Perry Vetter
2025 2030thru Department Parks: Centennial Lakes Park
Description
Centennial Lakes Park improvements as needed.
Project #P&R25147
Justification
The upkeep of City infrastructure is a key component of the Vision Edina document.
Useful LifeProject Name Centennial Lakes Improvements Category Parks
Type Expand or enhance
Total Project Cost:$800,000
Total2025 2026 2027 2028 2029Expenditures 2030
800,000Construction800,000
800,000Total800,000
Total2025 2026 2027 2028 2029Funding Sources 2030
800,000Construction Fund: CIP Levy 800,000
800,000Total800,000
232
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Patty McGrath
2025 2030thru Department Parks: Edinborough Park
Description
The track is an area with cardio and strength training equipment that is not air conditioned. It is surrounded by windows that can't be opened. Air
conditioning is a basic expectation in this type of space and the lack of air conditioning presents a health and safety concern.
Project #15-069
Justification
When Edinborough Park was built more than 30 years ago, air conditioning was not installed in the track area. The track is surrounded by windows
that cannot be opened. During the summer months temperatures can exceed 90 degrees. Air conditioning in an exercise area is a basic expectation
of anyone working out indoors. As noted in Vision Edina one of the strategic actions is "to continue to prioritize amenities that meet the needs of
residents of all ages." Exercising at these temperatures can become a safety and health issue for anyone, especially senior citizens using the area.
The addition of air conditioning to the track will make the facility a more appealing alternative for the community to enjoy year round.
Useful LifeProject Name Edinborough Park Track Air Conditioning Category Buildings
Type New
Total Project Cost:$81,000
Total2025 2026 2027 2028 2029Expenditures 2030
81,00081,000Vehicles and Equipment
81,000 81,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
81,00081,000Edinborough Fund
81,000 81,000Total
233
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Patty McGrath
2025 2030thru Department Parks: Edinborough Park
Description
Edinborough Park has 15 pieces of fitness equipment that are in need of replacement. The treadmills, ellipticals, rowers and strength equipment is
out of date. Parts and service for these old machines is becoming much more expensive and difficult to find.
The track is used by our association partners (Corporate Center, Brookdale Senior Living, Marriott Residence Inn, and Edinborough Townhomes)
as well as the Edina Swim Club, our annual members and guests who purchase a daily admission.
To maximize the impact of this project, it should be coordinated with replacing the track flooring.
Project #P&R21012
Justification
Replacing the fitness equipment at Edinborough Park is needed because the equipment is beyond useful life and requires constant maintenance.
Marketing Pool & Track memberships at this time is difficult due to the lack of equipment.
The Marriott Residence Inn is one of our association partners that pays park maintenance fees and they do not have exercise equipment or a
swimming pool. Our agreement with them includes pool and track privileges for their guests. Currently, the selection, condition and availability of
the equipment does not meet our standards for quality. In addition, our other association partners also have privileges to use this equipment.
With Brookdale Senior Living as another association partner, we could better serve their residents with updated equipment specifically geared
towards older adults.
Useful LifeProject Name Edinborough Park Fitness Equipment Replacement Category Equipment and Vehicles
Type Replace or repair
Total Project Cost:$26,000
Total2025 2026 2027 2028 2029Expenditures 2030
26,00026,000Vehicles and Equipment
26,000 26,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
26,00026,000Edinborough Fund
26,000 26,000Total
234
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Patty McGrath
2025 2030thru Department Parks: Edinborough Park
Description
The project would replace the original track surface that is from 1986. The surface is worn down and has areas that are tripping hazards.
Project #P&R25148
Justification
Health, Safety & Regulatory Compliance, Asset Functionality
Health in All Policies: The track provides a safe place for exercise and attracts many senior citizens. Keeping the integrity of the surface is
important to reduce trips and falls.
Useful LifeProject Name Edinborough Park Track Surface Replacement Category Parks
Type Replace or repair
Total Project Cost:$90,000
Total2025 2026 2027 2028 2029Expenditures 2030
90,00090,000Construction
90,000 90,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
90,00090,000Edinborough Fund
90,000 90,000Total
235
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Patty McGrath
2025 2030thru Department Parks: Edinborough Park
Description
The project will replace exterior landscaping that is 38 years old and is esthetically unattractive. It does not represent the first impression that is
expected of a City of Edina Facility
Project #P&R25149
Justification
Expansion and/or Level of Service
Useful LifeProject Name Edinborough Park Replace Exterior Landscaping Category Parks
Type Replace or repair
Total Project Cost:$75,000
Total2025 2026 2027 2028 2029Expenditures 2030
75,00075,000Construction
75,000 75,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
75,00075,000Edinborough Fund
75,000 75,000Total
236
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Patty McGrath
2025 2030thru Department Parks: Edinborough Park
Description
Replace aging concession equipment to improve operational efficiency and reduce energy costs.
Project #P&R25151
Justification
Asset Functionality
Useful LifeProject Name Edinborough Park Concession Replacement Category Parks
Type Replace or repair
Total Project Cost:$24,000
Total2025 2026 2027 2028 2029Expenditures 2030
24,00024,000Construction
24,000 24,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
24,00024,000Edinborough Fund
24,000 24,000Total
237
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Patty McGrath
2025 2030thru Department Parks: Edinborough Park
Description
Replace sound and lighting systems for performances. Blue tooth connectivity is an expectation for most performers and we do not have that. The
lighting gets extremely hot, making it uncomfortable for performers.
Project #P&R25152
Justification
Asset Functionality
Sustainability: Replacing current lighting with LED would realize energy cost savings.
Community Engagement: Performances are well attended and upgrading the sounds and lighting would improve the patron experience.
Stewardship: The Amphitheater has a long history of community performances and keeping up with modern technology is expected at a City
facility.
Useful LifeProject Name Edinborough Park Amphitheater Upgrades Category Parks
Type Replace or repair
Total Project Cost:$23,500
Total2025 2026 2027 2028 2029Expenditures 2030
23,50023,500Construction
23,500 23,500Total
Total2025 2026 2027 2028 2029Funding Sources 2030
23,50023,500Edinborough Fund
23,500 23,500Total
238
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Patty McGrath
2025 2030thru Department Parks: Edinborough Park
Description
Temporary concrete was installed during the plaza reconstruction project and it needs to be replaced with permanent concrete.
Project #P&R25153
Justification
Health, Safety & Regulatory Compliance
Community Engagement: Replacing the concrete ensures the integrity of the walkway and safety for everyone entering the facility.
Health in All Policies: Replacing the concrete ensures the integrity of the walkway and safety for everyone entering the facility.
Stewardship: This is the main entry to our facility and will ensure safety for everyone entering the facility.
Useful LifeProject Name Edinborough Park SE Entry Concrete Replacement Category Parks
Type Replace or repair
Total Project Cost:$27,000
Total2025 2026 2027 2028 2029Expenditures 2030
27,00027,000Construction
27,000 27,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
27,00027,000Edinborough Fund
27,000 27,000Total
239
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Patty McGrath
2025 2030thru Department Parks: Edinborough Park
Description
Replace all lockers in locker room and in the playpark to ensure patrons can safely secure their personal belongings while they are using the
facility. Existing lockers do not lock properly and are rusty on the inside leaving residue on patrons belongings.
Project #P&R25154
Justification
Asset Functionality
Health in All Policies: Replacing the locker will provide patrons with a sense of security and safety for their belongings while they are using the
facility.
Stewardship: The lockers are so old, it's difficult to find replacement parts to make them operational. It tis frustrating to patrons that we have an
asset doesn't work. Replacing the metal existing lockers with plastic lockers will increase their useful life.
Useful LifeProject Name Edinborough Park Locker Replacement Category Parks
Type Replace or repair
Total Project Cost:$31,000
Total2025 2026 2027 2028 2029Expenditures 2030
31,00031,000Construction
31,000 31,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
31,00031,000Edinborough Fund
31,000 31,000Total
240
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Patty McGrath
2025 2030thru Department Parks: Edinborough Park
Description
Replacing the 2008 Chevy Silverado (with Tommy Gate) vehicle allows staff to navigate the Edinborough Park campus, as well as hauling items
for projects and trips for supplies.
Project #P&R25155
Justification
Asset Functionality
Sustainability: New vehicle will be more fuel efficient than the 2008 model.
Community Enagagement: The vehicle will represent the City in a positive and professional manner.
Useful LifeProject Name Edinborough Park Truck Replacement Category Parks
Type Replace or repair
Total Project Cost:$50,000
Total2025 2026 2027 2028 2029Expenditures 2030
50,00050,000Vehicles and Equipment
50,000 50,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
50,00050,000Edinborough Fund
50,000 50,000Total
241
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Patty McGrath
2025 2030thru Department Parks: Edinborough Park
Description
To continue to meet Health Code requirements, the pool filter needs to be replaced. The pool filter was installed in 2004 and has exceeded its
useful life. Parts are no longer available for the model we have.
Project #P&R25156
Justification
Asset Functionality
Sustainability: A new filter could use regenerative media, reducing the frequency of backwashing and saves water.
Community Engagement: Replacing the filter ensures that the water will be clean and safe for community members to swim in.
Health In All Policies: Replacing the filter ensures that the water will be clean and safe for community members to swim in.
Race & Equity: Everyone will benefit from swimming in a clean, safe pool.
Stewardship: The filter replacement ensures ongoing operations for our members, community members, swim clubs and other rental groups.
Useful LifeProject Name Edinborough Park Pool Filter Replacement Category Parks
Type Replace or repair
Total Project Cost:$70,000
Total2025 2026 2027 2028 2029Expenditures 2030
70,00070,000Construction
70,000 70,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
70,00070,000Edinborough Fund
70,000 70,000Total
242
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Patty McGrath
2025 2030thru Department Parks: Edinborough Park
Description
The Camus boiler heats the entire facility and has exceeded its useful life.
Project #P&R25157
Justification
Asset Functionality
Sustainability: The existing boiler is 20 years old and replacing it with a high efficiency model will reduce energy costs.
Health In All Policies: The park will be comfortable for all patrons when the boiler is working consistently.
Useful LifeProject Name Edinborough Park Replace Camus Boiler Category Parks
Type Replace or repair
Total Project Cost:$70,000
Total2025 2026 2027 2028 2029Expenditures 2030
70,00070,000Construction
70,000 70,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
70,00070,000CIP Bonds
70,000 70,000Total
243
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Joe Abood
2025 2030thru Department Parks: Golf Course
Description
The Braemar Clubhouse Lower Level is presently under-utilized because of its floor plan as well as its condition. Restrooms and shower facilities
as well as the plumbing infrastructure need to be repaired and renovated.
Project #17-031
Justification
Renovation is needed to keep facility up to acceptable standards for a premier facility. National Golf Foundation (NGF) reports golf courses are
"living and breathing" assets that will deteriorate over time, and significant reductions in capital expenditures eventually will catch up to the system.
Useful LifeProject Name Braemar Golf Clubhouse Lower Level Category Buildings
Type Expand or enhance
Total Project Cost:$100,000
Total2025 2026 2027 2028 2029Expenditures 2030
100,000Construction100,000
100,000Total100,000
Total2025 2026 2027 2028 2029Funding Sources 2030
100,000Golf Course Fund 100,000
100,000Total100,000
244
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Joe Abood
2025 2030thru Department Parks: Golf Course
Description
A second sprayer to help spray fairways and greens. Spraying fairways with the one sprayer we have can take one full week to complete. Ideally,
when spraying you want to get it done in two days or less. Would like to be able to spray growth regulator on the fairways to help out with
seedheads and slow the growth rate down to possibly mow once a week only. Not only to slow the vertical growth but it also helps horizontal
growth to help fill in thinner areas. This smaller sprayer would be better on greens as well with less weight with the tire marks across the greens.
ENVIRONMENTAL CONSIDERATIONS:
Getting everything sprayed in one or two days rather than a week, the perception would be more ideal not seeing the sprayer out there all the time
for a week straight.
Project #P&R21028
Justification
A visual by the customers not seeing the sprayer out there for a week straight and also better for the consistency of the way the golf course plays.
Useful LifeProject Name Toro 300 Gal Sprayer Category Equipment and Vehicles
Type Expand or enhance
Total Project Cost:$85,000
Total2025 2026 2027 2028 2029Expenditures 2030
85,00085,000Vehicles and Equipment
85,000 85,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
85,00085,000Golf Course Fund
85,000 85,000Total
245
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Joe Abood
2025 2030thru Department Parks: Golf Course
Description
Addition of cart paths on holes #6 and #11. This will complete the continuous loop of the 18-hole golf course.
Project #P&R21043
Justification
In strategic alignment with Edina’s mission statement to "offer premier public facilities".
Useful LifeProject Name Cart Path Addition Hole #6 & #11 Category Infrastructure
Type Expand or enhance
Total Project Cost:$150,000
Total2025 2026 2027 2028 2029Expenditures 2030
150,000150,000Installation/Maintenance
150,000 150,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
150,000150,000Golf Course Fund
150,000 150,000Total
246
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Joe Abood
2025 2030thru Department Parks: Golf Course
Description
The netting that protects the Golf Dome fabric is in disrepair due to the high volume of golf balls that are hit on a daily basis. We have made
repairs to the netting each of the last three years. Cost of repairs have ranged between $5,000 and $8,500. A new net design is required to
alleviate the constant repairs.Replacement needed to keep facility up to acceptable standards for a premier facility. In strategic alignment with
Edina’s mission statement to ""offer premier public facilities"".The National Golf Foundation (NGF) report also confirms justification ""NGF has
observed declining investment in in the golf courses as revenues declined. Golf courses are ""living and breathing"" assets that will deteriorate
over time, and significant reductions in capital expenditures eventually will catch up to the system
Project #P&R25160
Justification
Asset Functionality
Useful LifeProject Name Golf Dome Netting Repairs Category Parks
Type Replace or repair
Total Project Cost:$250,000
Total2025 2026 2027 2028 2029Expenditures 2030
250,000100,000 150,000Construction
100,000 150,000 250,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
250,000100,000 150,000Golf Course Fund
100,000 150,000 250,000Total
247
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Joe Abood
2025 2030thru Department Parks: Golf Course
Description
Replace existing gas mowers for tees and approaches with Hybrid model. Mowers are critical to the overall golf operation and need to be replaced
on regularly scheduled basis. As these machines age they require more maintenance and develop hydraulic oil leaks which is detrimental to the
turf. Existing 4 Workman’s are reaching the end of their useful lifespan.
Existing 4 Workman’s are reaching the end of their useful lifespan.
Kubota or a John Deere tractor with a front end loader would be used year round by removing snow in the winter and other projects throughout the
course and in the summer it could be used daily with loading topdressing sand or divot mix and other projects. These tractors are ideal for tractor
mounted aerators and we have two of those for only one tractor at the present. With the construction of the new golf course there are many areas
that are compacted and these machines could be running spring and fall yearly.
Replace fairway mower. Fairway mowers are critical to the overall golf operation and need to be replaced on regularly scheduled basis. As these
machines age they require more maintenance and develop hydraulic oil leaks which is detrimental to the turf.
Replace large rough mower. Rough mowers are critical to the overall golf operation and need to be replaced on regularly scheduled basis. As these
machines age they require more maintenance and develop hydraulic oil leaks which is detrimental to the turf.
2025 - Toro 4500 Rough Mower
2026 - Kubota or John Deere Tractor, Toro 3555 Fairway Mowers (2), Toro 4500 Rough Mower
2027 - Toro 3320 Hybrid Triplex Mowers (2), Toro Workman
2028 - Toro Workman
2029 - Toro Workman
Project #P&R25162
Justification
Asset Functionality. By adding an additional tractor we will be able to save money in the long run. It will also add to the efficiency of golf course
operations. Lots of acreage to mow with not much time to stay ahead of play. Adding this mower would help to dedicate one of our older mowers
for the practice areas and Academy 9.
Sustainability: Braemar Golf Course is recognized for its Environmental Excellence as a “Certified Audubon Cooperative Sanctuary” through the
Audubon Cooperative Sanctuary Program for Golf Courses, an Audubon International program.
Braemar is one of 900 courses in the world to receive this honor for maintaining a high degree of environmental quality and natural resources in
areas including wildlife and habitat management, chemical use reduction and safety, water quality management and environmental planning.
Braemar was first certified in 2005 and has been able to retain the honor every three years during the recertification process.
Braemar’s Championship 18 opened in May 2019 after being transformed into a 6,884-yard regulation18-hole golf course. The redesign included a
significant environmental statement by restoring 4.37 acres of wetlands and enhancing a bit over a half-acre of additional wetlands, creating 32.11
acres of wetland buffer and introducing 33.85 acres of Oak Savanna throughout the course.
Community Engagement: At the heart of Braemar Golf Course lies a sense of camaraderie and social interaction. Braemar brings people together,
providing a platform for its patrons to connect, bond, and forge friendships. Braemar becomes a place where golfers of all skill levels, ages and
abilities can come together, share experiences, and create a welcoming atmosphere that extends beyond the fairways. It's this sense of belonging
that enhances the overall golfing experience and makes it truly special.
Health in All Policies: Golf is a great way to enjoy regular exercise, develop social connections, and manage stress.
Race & Equity: Braemar Golf Course is committed to being welcoming and inclusive to all who patronize the facility. To support and foster
inclusivity, Braemar staff members are dedicated to acknowledging, seeking out and celebrating the diversity of its customers and proactively
working together to eliminate systemic and institutional barriers to ensure all people have the opportunity to participate in golf at its facilities.
Stewardship: Braemar Golf Course is committed to maintaining the golf course to the highest standard while preserving and enhancing the
Useful LifeProject Name Golf Course Tractor & Mower Replacements Category Equipment and Vehicles
Type Replace or repair
Total Project Cost:$705,000
248
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Joe Abood
2025 2030thru Department Parks: Golf Course
surrounding wildlife environment. Braemar demonstrates a high degree of environmental quality in a number of areas including environmental
planning, wildlife & habitat management, outreach & education, integrated pest management, water conservation, and water quality management.
Total2025 2026 2027 2028 2029Expenditures 2030
705,000100,000 295,000 160,000 50,000 100,000Vehicles and Equipment
100,000 295,000 160,000 50,000 100,000 705,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
705,000100,000 295,000 160,000 50,000 100,000Golf Course Fund
100,000 295,000 160,000 50,000 100,000 705,000Total
249
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Joe Abood
2025 2030thru Department Parks: Golf Course
Description
Pre-construction costs to design new clubhouse at Braemar Golf Course. The existing clubhouse has exceeded its useful lifespan and is in need of
replacement. Evaluation of programming and space needs will be included to determine required square footage. Design will be driven by city
goals and values. $2,000,000
Construction costs to build new clubhouse at Braemar Golf Course. The existing clubhouse has exceeded its useful lifespan and is in need of
replacement. Evaluation of programming and space needs will be included to determine required square footage. Design will be driven by city
goals and values. $25,000,000
Project #P&R25163
Justification
Expansion and/or Level of Service
Sustainability: Braemar Golf Course is recognized for its Environmental Excellence as a “Certified Audubon Cooperative Sanctuary” through the
Audubon Cooperative Sanctuary Program for Golf Courses, an Audubon International program.
Braemar is one of 900 courses in the world to receive this honor for maintaining a high degree of environmental quality and natural resources in
areas including wildlife and habitat management, chemical use reduction and safety, water quality management and environmental planning.
Braemar was first certified in 2005 and has been able to retain the honor every three years during the recertification process.
Braemar’s Championship 18 opened in May 2019 after being transformed into a 6,884-yard regulation18-hole golf course. The redesign included a
significant environmental statement by restoring 4.37 acres of wetlands and enhancing a bit over a half-acre of additional wetlands, creating 32.11
acres of wetland buffer and introducing 33.85 acres of Oak Savanna throughout the course.
Community Engagement: At the heart of Braemar Golf Course lies a sense of camaraderie and social interaction. Braemar brings people together,
providing a platform for its patrons to connect, bond, and forge friendships. Braemar becomes a place where golfers of all skill levels, ages and
abilities can come together, share experiences, and create a welcoming atmosphere that extends beyond the fairways. It's this sense of belonging
that enhances the overall golfing experience and makes it truly special.
Health in All Policies: Golf is a great way to enjoy regular exercise, develop social connections, and manage stress.
Race & Equity: Braemar Golf Course is committed to being welcoming and inclusive to all who patronize the facility. To support and foster
inclusivity, Braemar staff members are dedicated to acknowledging, seeking out and celebrating the diversity of its customers and proactively
working together to eliminate systemic and institutional barriers to ensure all people have the opportunity to participate in golf at its facilities.
Stewardship: Braemar Golf Course is committed to maintaining the golf course to the highest standard while preserving and enhancing the
surrounding wildlife environment. Braemar demonstrates a high degree of environmental quality in a number of areas including environmental
planning, wildlife & habitat management, outreach & education, integrated pest management, water conservation, and water quality management.
Useful LifeProject Name New Golf Course Clubhouse Category Buildings
Type New
Total Project Cost:$27,000,000
Total2025 2026 2027 2028 2029Expenditures 2030
2,000,000Planning and Design 2,000,000
25,000,000Construction25,000,000
27,000,000Total27,000,000
Total2025 2026 2027 2028 2029Funding Sources 2030
27,000,000CIP Bonds 27,000,000
27,000,000Total27,000,000
250
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Joe Abood
2025 2030thru Department Parks: Golf Course
Description
Add irrigation to areas of the course that were not irrigated in the Master Plan Project. These areas are heavily trafficked and require staff to
manually pull around hoses and sprinkler bases which eliminates other tasks needed to be accomplished.
Project #P&R25164
Justification
Expansion and/or Level of Service
Sustainability: Braemar Golf Course is recognized for its Environmental Excellence as a “Certified Audubon Cooperative Sanctuary” through the
Audubon Cooperative Sanctuary Program for Golf Courses, an Audubon International program.
Braemar is one of 900 courses in the world to receive this honor for maintaining a high degree of environmental quality and natural resources in
areas including wildlife and habitat management, chemical use reduction and safety, water quality management and environmental planning.
Braemar was first certified in 2005 and has been able to retain the honor every three years during the recertification process.
Braemar’s Championship 18 opened in May 2019 after being transformed into a 6,884-yard regulation18-hole golf course. The redesign included a
significant environmental statement by restoring 4.37 acres of wetlands and enhancing a bit over a half-acre of additional wetlands, creating 32.11
acres of wetland buffer and introducing 33.85 acres of Oak Savanna throughout the course.
Community Engagement: At the heart of Braemar Golf Course lies a sense of camaraderie and social interaction. Braemar brings people together,
providing a platform for its patrons to connect, bond, and forge friendships. Braemar becomes a place where golfers of all skill levels, ages and
abilities can come together, share experiences, and create a welcoming atmosphere that extends beyond the fairways. It's this sense of belonging
that enhances the overall golfing experience and makes it truly special.
Health in All Policies: Golf is a great way to enjoy regular exercise, develop social connections, and manage stress.
Race & Equity: Braemar Golf Course is committed to being welcoming and inclusive to all who patronize the facility. To support and foster
inclusivity, Braemar staff members are dedicated to acknowledging, seeking out and celebrating the diversity of its customers and proactively
working together to eliminate systemic and institutional barriers to ensure all people have the opportunity to participate in golf at its facilities.
Stewardship: Braemar Golf Course is committed to maintaining the golf course to the highest standard while preserving and enhancing the
surrounding wildlife environment. Braemar demonstrates a high degree of environmental quality in a number of areas including environmental
planning, wildlife & habitat management, outreach & education, integrated pest management, water conservation, and water quality management.
Useful LifeProject Name Golf Course Irrigation Upgrade Category Parks
Type Expand or enhance
Total Project Cost:$225,000
Total2025 2026 2027 2028 2029Expenditures 2030
225,000225,000Construction
225,000 225,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
225,000225,000Golf Course Fund
225,000 225,000Total
251
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Joe Abood
2025 2030thru Department Parks: Golf Course
Description
Replacement of 6 utility carts. Existing carts are at the end of their useful lifespan.
Project #P&R25166
Justification
Asset Functionality
Sustainability: Braemar Golf Course is recognized for its Environmental Excellence as a “Certified Audubon Cooperative Sanctuary” through the
Audubon Cooperative Sanctuary Program for Golf Courses, an Audubon International program.
Braemar is one of 900 courses in the world to receive this honor for maintaining a high degree of environmental quality and natural resources in
areas including wildlife and habitat management, chemical use reduction and safety, water quality management and environmental planning.
Braemar was first certified in 2005 and has been able to retain the honor every three years during the recertification process.
Braemar’s Championship 18 opened in May 2019 after being transformed into a 6,884-yard regulation18-hole golf course. The redesign included a
significant environmental statement by restoring 4.37 acres of wetlands and enhancing a bit over a half-acre of additional wetlands, creating 32.11
acres of wetland buffer and introducing 33.85 acres of Oak Savanna throughout the course.
Community Engagement: At the heart of Braemar Golf Course lies a sense of camaraderie and social interaction. Braemar brings people together,
providing a platform for its patrons to connect, bond, and forge friendships. Braemar becomes a place where golfers of all skill levels, ages and
abilities can come together, share experiences, and create a welcoming atmosphere that extends beyond the fairways. It's this sense of belonging
that enhances the overall golfing experience and makes it truly special.
Health in All Policies: Golf is a great way to enjoy regular exercise, develop social connections, and manage stress.
Race & Equity: Braemar Golf Course is committed to being welcoming and inclusive to all who patronize the facility. To support and foster
inclusivity, Braemar staff members are dedicated to acknowledging, seeking out and celebrating the diversity of its customers and proactively
working together to eliminate systemic and institutional barriers to ensure all people have the opportunity to participate in golf at its facilities.
Stewardship: Braemar Golf Course is committed to maintaining the golf course to the highest standard while preserving and enhancing the
surrounding wildlife environment. Braemar demonstrates a high degree of environmental quality in a number of areas including environmental
planning, wildlife & habitat management, outreach & education, integrated pest management, water conservation, and water quality management.
Useful LifeProject Name Club Car Utility Carts Category Equipment and Vehicles
Type Replace or repair
Total Project Cost:$78,000
Total2025 2026 2027 2028 2029Expenditures 2030
78,00026,000 26,000 26,000Vehicles and Equipment
26,000 26,000 26,000 78,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
78,00026,000 26,000 26,000Golf Course Fund
26,000 26,000 26,000 78,000Total
252
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Joe Abood
2025 2030thru Department Parks: Golf Course
Description
Replace existing lift table. The current one continues to leak hydraulic fluid even after the cylinders have been replaced a few years back. Used
daily.
Project #P&R25167
Justification
Asset Functionality
Sustainability: Braemar Golf Course is recognized for its Environmental Excellence as a “Certified Audubon Cooperative Sanctuary” through the
Audubon Cooperative Sanctuary Program for Golf Courses, an Audubon International program.
Braemar is one of 900 courses in the world to receive this honor for maintaining a high degree of environmental quality and natural resources in
areas including wildlife and habitat management, chemical use reduction and safety, water quality management and environmental planning.
Braemar was first certified in 2005 and has been able to retain the honor every three years during the recertification process.
Braemar’s Championship 18 opened in May 2019 after being transformed into a 6,884-yard regulation18-hole golf course. The redesign included a
significant environmental statement by restoring 4.37 acres of wetlands and enhancing a bit over a half-acre of additional wetlands, creating 32.11
acres of wetland buffer and introducing 33.85 acres of Oak Savanna throughout the course.
Community Engagement: At the heart of Braemar Golf Course lies a sense of camaraderie and social interaction. Braemar brings people together,
providing a platform for its patrons to connect, bond, and forge friendships. Braemar becomes a place where golfers of all skill levels, ages and
abilities can come together, share experiences, and create a welcoming atmosphere that extends beyond the fairways. It's this sense of belonging
that enhances the overall golfing experience and makes it truly special.
Health in All Policies: Golf is a great way to enjoy regular exercise, develop social connections, and manage stress.
Race & Equity: Braemar Golf Course is committed to being welcoming and inclusive to all who patronize the facility. To support and foster
inclusivity, Braemar staff members are dedicated to acknowledging, seeking out and celebrating the diversity of its customers and proactively
working together to eliminate systemic and institutional barriers to ensure all people have the opportunity to participate in golf at its facilities.
Stewardship: Braemar Golf Course is committed to maintaining the golf course to the highest standard while preserving and enhancing the
surrounding wildlife environment. Braemar demonstrates a high degree of environmental quality in a number of areas including environmental
planning, wildlife & habitat management, outreach & education, integrated pest management, water conservation, and water quality management.
Useful LifeProject Name Golf Maintenance Facility Lift Table Category Equipment and Vehicles
Type Replace or repair
Total Project Cost:$20,000
Total2025 2026 2027 2028 2029Expenditures 2030
20,00020,000Vehicles and Equipment
20,000 20,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
20,00020,000Golf Course Fund
20,000 20,000Total
253
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Joe Abood
2025 2030thru Department Parks: Golf Course
Description
Comfort station located on hole #15 requires painting, siding replacement and roof repairs.
Project #P&R25168
Justification
Asset Functionality
Sustainability: Braemar Golf Course is recognized for its Environmental Excellence as a “Certified Audubon Cooperative Sanctuary” through the
Audubon Cooperative Sanctuary Program for Golf Courses, an Audubon International program.
Braemar is one of 900 courses in the world to receive this honor for maintaining a high degree of environmental quality and natural resources in
areas including wildlife and habitat management, chemical use reduction and safety, water quality management and environmental planning.
Braemar was first certified in 2005 and has been able to retain the honor every three years during the recertification process.
Braemar’s Championship 18 opened in May 2019 after being transformed into a 6,884-yard regulation18-hole golf course. The redesign included a
significant environmental statement by restoring 4.37 acres of wetlands and enhancing a bit over a half-acre of additional wetlands, creating 32.11
acres of wetland buffer and introducing 33.85 acres of Oak Savanna throughout the course.
Community Engagement: At the heart of Braemar Golf Course lies a sense of camaraderie and social interaction. Braemar brings people together,
providing a platform for its patrons to connect, bond, and forge friendships. Braemar becomes a place where golfers of all skill levels, ages and
abilities can come together, share experiences, and create a welcoming atmosphere that extends beyond the fairways. It's this sense of belonging
that enhances the overall golfing experience and makes it truly special.
Health in All Policies: Golf is a great way to enjoy regular exercise, develop social connections, and manage stress.
Race & Equity: Braemar Golf Course is committed to being welcoming and inclusive to all who patronize the facility. To support and foster
inclusivity, Braemar staff members are dedicated to acknowledging, seeking out and celebrating the diversity of its customers and proactively
working together to eliminate systemic and institutional barriers to ensure all people have the opportunity to participate in golf at its facilities.
Stewardship: Braemar Golf Course is committed to maintaining the golf course to the highest standard while preserving and enhancing the
surrounding wildlife environment. Braemar demonstrates a high degree of environmental quality in a number of areas including environmental
planning, wildlife & habitat management, outreach & education, integrated pest management, water conservation, and water quality management.
Useful LifeProject Name Golf Course Restroom Renovation Category Parks
Type Replace or repair
Total Project Cost:$40,000
Total2025 2026 2027 2028 2029Expenditures 2030
40,00040,000Construction
40,000 40,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
40,00040,000Golf Course Fund
40,000 40,000Total
254
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Joe Abood
2025 2030thru Department Parks: Golf Course
Description
Insulate the cold storage building that is connected to the main shop to keep it warmer during the winter months so more work can be done out
there and also help with longevity of equipment
Project #P&R25169
Justification
Expansion and/or Level of Service
Sustainability: Braemar Golf Course is recognized for its Environmental Excellence as a “Certified Audubon Cooperative Sanctuary” through the
Audubon Cooperative Sanctuary Program for Golf Courses, an Audubon International program.
Braemar is one of 900 courses in the world to receive this honor for maintaining a high degree of environmental quality and natural resources in
areas including wildlife and habitat management, chemical use reduction and safety, water quality management and environmental planning.
Braemar was first certified in 2005 and has been able to retain the honor every three years during the recertification process.
Braemar’s Championship 18 opened in May 2019 after being transformed into a 6,884-yard regulation18-hole golf course. The redesign included a
significant environmental statement by restoring 4.37 acres of wetlands and enhancing a bit over a half-acre of additional wetlands, creating 32.11
acres of wetland buffer and introducing 33.85 acres of Oak Savanna throughout the course.
Community Engagement: At the heart of Braemar Golf Course lies a sense of camaraderie and social interaction. Braemar brings people together,
providing a platform for its patrons to connect, bond, and forge friendships. Braemar becomes a place where golfers of all skill levels, ages and
abilities can come together, share experiences, and create a welcoming atmosphere that extends beyond the fairways. It's this sense of belonging
that enhances the overall golfing experience and makes it truly special.
Health in All Policies: Golf is a great way to enjoy regular exercise, develop social connections, and manage stress.
Race & Equity: Braemar Golf Course is committed to being welcoming and inclusive to all who patronize the facility. To support and foster
inclusivity, Braemar staff members are dedicated to acknowledging, seeking out and celebrating the diversity of its customers and proactively
working together to eliminate systemic and institutional barriers to ensure all people have the opportunity to participate in golf at its facilities.
Stewardship: Braemar Golf Course is committed to maintaining the golf course to the highest standard while preserving and enhancing the
surrounding wildlife environment. Braemar demonstrates a high degree of environmental quality in a number of areas including environmental
planning, wildlife & habitat management, outreach & education, integrated pest management, water conservation, and water quality management.
Useful LifeProject Name Golf Course Cold Storage Insulation Category Buildings
Type Expand or enhance
Total Project Cost:$60,000
Total2025 2026 2027 2028 2029Expenditures 2030
60,00060,000Construction
60,000 60,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
60,00060,000Golf Course Fund
60,000 60,000Total
255
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Joe Abood
2025 2030thru Department Parks: Golf Course
Description
Tear down and rebuild. The walls are rotting and have holes in them. Could be used for more storage as well for accessories during the winter
months.
Project #P&R25170
Justification
Asset Functionality
Useful LifeProject Name Update Well House #2 on Hole #13 Category Parks
Type Replace or repair
Total Project Cost:$75,000
Total2025 2026 2027 2028 2029Expenditures 2030
75,00075,000Construction
75,000 75,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
75,00075,000Golf Course Fund
75,000 75,000Total
256
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Joe Abood
2025 2030thru Department Parks: Golf Course
Description
The existing practice green is too small for the number of Juniors and Academy 9 players. The plan is to rebuild and enlarge the green. Also, build
a pavilion in the area for people waiting to pick up their children as well as a gathering point for the Academy 9.
Project #P&R25171
Justification
Expansion and/or Level of Service
Sustainability: Braemar Golf Course is recognized for its Environmental Excellence as a “Certified Audubon Cooperative Sanctuary” through the
Audubon Cooperative Sanctuary Program for Golf Courses, an Audubon International program.
Braemar is one of 900 courses in the world to receive this honor for maintaining a high degree of environmental quality and natural resources in
areas including wildlife and habitat management, chemical use reduction and safety, water quality management and environmental planning.
Braemar was first certified in 2005 and has been able to retain the honor every three years during the recertification process.
Braemar’s Championship 18 opened in May 2019 after being transformed into a 6,884-yard regulation18-hole golf course. The redesign included a
significant environmental statement by restoring 4.37 acres of wetlands and enhancing a bit over a half-acre of additional wetlands, creating 32.11
acres of wetland buffer and introducing 33.85 acres of Oak Savanna throughout the course.
Community Engagement: At the heart of Braemar Golf Course lies a sense of camaraderie and social interaction. Braemar brings people together,
providing a platform for its patrons to connect, bond, and forge friendships. Braemar becomes a place where golfers of all skill levels, ages and
abilities can come together, share experiences, and create a welcoming atmosphere that extends beyond the fairways. It's this sense of belonging
that enhances the overall golfing experience and makes it truly special.
Health in All Policies: Golf is a great way to enjoy regular exercise, develop social connections, and manage stress.
Race & Equity: Braemar Golf Course is committed to being welcoming and inclusive to all who patronize the facility. To support and foster
inclusivity, Braemar staff members are dedicated to acknowledging, seeking out and celebrating the diversity of its customers and proactively
working together to eliminate systemic and institutional barriers to ensure all people have the opportunity to participate in golf at its facilities.
Stewardship: Braemar Golf Course is committed to maintaining the golf course to the highest standard while preserving and enhancing the
surrounding wildlife environment. Braemar demonstrates a high degree of environmental quality in a number of areas including environmental
planning, wildlife & habitat management, outreach & education, integrated pest management, water conservation, and water quality management.
Useful LifeProject Name Practice Green Enlargement / Academy 9 Pavilion Category Parks
Type Expand or enhance
Total Project Cost:$75,000
Total2025 2026 2027 2028 2029Expenditures 2030
75,00075,000Construction
75,000 75,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
75,00075,000Golf Course Fund
75,000 75,000Total
257
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Joe Abood
2025 2030thru Department Parks: Golf Course
Description
Driving Range Safety Netting is needed to protect golfers on hole #9 of the Championship Golf Course and hole #1 of the Academy 9 Golf Course
from errant shots coming from the driving range.
Project #P&R25172
Justification
Health, Safety & Regulatory Compliance
Sustainability: Braemar Golf Course is recognized for its Environmental Excellence as a “Certified Audubon Cooperative Sanctuary” through the
Audubon Cooperative Sanctuary Program for Golf Courses, an Audubon International program.
Braemar is one of 900 courses in the world to receive this honor for maintaining a high degree of environmental quality and natural resources in
areas including wildlife and habitat management, chemical use reduction and safety, water quality management and environmental planning.
Braemar was first certified in 2005 and has been able to retain the honor every three years during the recertification process.
Braemar’s Championship 18 opened in May 2019 after being transformed into a 6,884-yard regulation18-hole golf course. The redesign included a
significant environmental statement by restoring 4.37 acres of wetlands and enhancing a bit over a half-acre of additional wetlands, creating 32.11
acres of wetland buffer and introducing 33.85 acres of Oak Savanna throughout the course.
Community Engagement: At the heart of Braemar Golf Course lies a sense of camaraderie and social interaction. Braemar brings people together,
providing a platform for its patrons to connect, bond, and forge friendships. Braemar becomes a place where golfers of all skill levels, ages and
abilities can come together, share experiences, and create a welcoming atmosphere that extends beyond the fairways. It's this sense of belonging
that enhances the overall golfing experience and makes it truly special.
Health in All Policies: Golf is a great way to enjoy regular exercise, develop social connections, and manage stress.
Race & Equity: Braemar Golf Course is committed to being welcoming and inclusive to all who patronize the facility. To support and foster
inclusivity, Braemar staff members are dedicated to acknowledging, seeking out and celebrating the diversity of its customers and proactively
working together to eliminate systemic and institutional barriers to ensure all people have the opportunity to participate in golf at its facilities.
Stewardship: Braemar Golf Course is committed to maintaining the golf course to the highest standard while preserving and enhancing the
surrounding wildlife environment. Braemar demonstrates a high degree of environmental quality in a number of areas including environmental
planning, wildlife & habitat management, outreach & education, integrated pest management, water conservation, and water quality management.
Useful LifeProject Name Driving Range Safety Netting Category Parks
Type Replace or repair
Total Project Cost:$200,000
Total2025 2026 2027 2028 2029Expenditures 2030
200,000200,000Construction
200,000 200,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
200,000200,000Golf Course Fund
200,000 200,000Total
258
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Joe Abood
2025 2030thru Department Parks: Golf Course
Description
To be more sustainable and environmentally friendly, we are proposing to add native areas that would save water and enhance wildlife and the use
of less emissions.
Project #P&R25175
Justification
Expansion and/or Level of Service
Sustainability: Braemar Golf Course is recognized for its Environmental Excellence as a “Certified Audubon Cooperative Sanctuary” through the
Audubon Cooperative Sanctuary Program for Golf Courses, an Audubon International program.
Braemar is one of 900 courses in the world to receive this honor for maintaining a high degree of environmental quality and natural resources in
areas including wildlife and habitat management, chemical use reduction and safety, water quality management and environmental planning.
Braemar was first certified in 2005 and has been able to retain the honor every three years during the recertification process.
Braemar’s Championship 18 opened in May 2019 after being transformed into a 6,884-yard regulation18-hole golf course. The redesign included a
significant environmental statement by restoring 4.37 acres of wetlands and enhancing a bit over a half-acre of additional wetlands, creating 32.11
acres of wetland buffer and introducing 33.85 acres of Oak Savanna throughout the course.
Community Engagement: At the heart of Braemar Golf Course lies a sense of camaraderie and social interaction. Braemar brings people together,
providing a platform for its patrons to connect, bond, and forge friendships. Braemar becomes a place where golfers of all skill levels, ages and
abilities can come together, share experiences, and create a welcoming atmosphere that extends beyond the fairways. It's this sense of belonging
that enhances the overall golfing experience and makes it truly special.
Health in All Policies: Golf is a great way to enjoy regular exercise, develop social connections, and manage stress.
Race & Equity: Braemar Golf Course is committed to being welcoming and inclusive to all who patronize the facility. To support and foster
inclusivity, Braemar staff members are dedicated to acknowledging, seeking out and celebrating the diversity of its customers and proactively
working together to eliminate systemic and institutional barriers to ensure all people have the opportunity to participate in golf at its facilities.
Stewardship: Braemar Golf Course is committed to maintaining the golf course to the highest standard while preserving and enhancing the
surrounding wildlife environment. Braemar demonstrates a high degree of environmental quality in a number of areas including environmental
planning, wildlife & habitat management, outreach & education, integrated pest management, water conservation, and water quality management.
Useful LifeProject Name Golf Course Additional Native Areas Category Land
Type Expand or enhance
Total Project Cost:$65,000
Total2025 2026 2027 2028 2029Expenditures 2030
65,00065,000Construction
65,000 65,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
65,00065,000Golf Course Fund
65,000 65,000Total
259
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Joe Abood
2025 2030thru Department Parks: Golf Course
Description
Build a new nursery green that has the same USGA specs that the existing greens have.
Project #P&R25176
Justification
Expansion and/or Level of Service
Sustainability: Braemar Golf Course is recognized for its Environmental Excellence as a “Certified Audubon Cooperative Sanctuary” through the
Audubon Cooperative Sanctuary Program for Golf Courses, an Audubon International program.
Braemar is one of 900 courses in the world to receive this honor for maintaining a high degree of environmental quality and natural resources in
areas including wildlife and habitat management, chemical use reduction and safety, water quality management and environmental planning.
Braemar was first certified in 2005 and has been able to retain the honor every three years during the recertification process.
Braemar’s Championship 18 opened in May 2019 after being transformed into a 6,884-yard regulation18-hole golf course. The redesign included a
significant environmental statement by restoring 4.37 acres of wetlands and enhancing a bit over a half-acre of additional wetlands, creating 32.11
acres of wetland buffer and introducing 33.85 acres of Oak Savanna throughout the course.
Community Engagement: At the heart of Braemar Golf Course lies a sense of camaraderie and social interaction. Braemar brings people together,
providing a platform for its patrons to connect, bond, and forge friendships. Braemar becomes a place where golfers of all skill levels, ages and
abilities can come together, share experiences, and create a welcoming atmosphere that extends beyond the fairways. It's this sense of belonging
that enhances the overall golfing experience and makes it truly special.
Health in All Policies: Golf is a great way to enjoy regular exercise, develop social connections, and manage stress.
Race & Equity: Braemar Golf Course is committed to being welcoming and inclusive to all who patronize the facility. To support and foster
inclusivity, Braemar staff members are dedicated to acknowledging, seeking out and celebrating the diversity of its customers and proactively
working together to eliminate systemic and institutional barriers to ensure all people have the opportunity to participate in golf at its facilities.
Stewardship: Braemar Golf Course is committed to maintaining the golf course to the highest standard while preserving and enhancing the
surrounding wildlife environment. Braemar demonstrates a high degree of environmental quality in a number of areas including environmental
planning, wildlife & habitat management, outreach & education, integrated pest management, water conservation, and water quality management.
Useful LifeProject Name Golf Course New Nursery Green Category Land
Type New
Total Project Cost:$100,000
Total2025 2026 2027 2028 2029Expenditures 2030
100,000100,000Construction
100,000 100,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
100,000100,000Golf Course Fund
100,000 100,000Total
260
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Joe Abood
2025 2030thru Department Parks: Golf Course
Description
Fill in gaps in cart path to make a continuous loop.
Project #P&R25178
Justification
Expansion and/or Level of Service
Sustainability: Braemar Golf Course is recognized for its Environmental Excellence as a “Certified Audubon Cooperative Sanctuary” through the
Audubon Cooperative Sanctuary Program for Golf Courses, an Audubon International program.
Braemar is one of 900 courses in the world to receive this honor for maintaining a high degree of environmental quality and natural resources in
areas including wildlife and habitat management, chemical use reduction and safety, water quality management and environmental planning.
Braemar was first certified in 2005 and has been able to retain the honor every three years during the recertification process.
Braemar’s Championship 18 opened in May 2019 after being transformed into a 6,884-yard regulation18-hole golf course. The redesign included a
significant environmental statement by restoring 4.37 acres of wetlands and enhancing a bit over a half-acre of additional wetlands, creating 32.11
acres of wetland buffer and introducing 33.85 acres of Oak Savanna throughout the course.
Community Engagement: At the heart of Braemar Golf Course lies a sense of camaraderie and social interaction. Braemar brings people together,
providing a platform for its patrons to connect, bond, and forge friendships. Braemar becomes a place where golfers of all skill levels, ages and
abilities can come together, share experiences, and create a welcoming atmosphere that extends beyond the fairways. It's this sense of belonging
that enhances the overall golfing experience and makes it truly special.
Health in All Policies: Golf is a great way to enjoy regular exercise, develop social connections, and manage stress.
Race & Equity: Braemar Golf Course is committed to being welcoming and inclusive to all who patronize the facility. To support and foster
inclusivity, Braemar staff members are dedicated to acknowledging, seeking out and celebrating the diversity of its customers and proactively
working together to eliminate systemic and institutional barriers to ensure all people have the opportunity to participate in golf at its facilities.
Stewardship: Braemar Golf Course is committed to maintaining the golf course to the highest standard while preserving and enhancing the
surrounding wildlife environment. Braemar demonstrates a high degree of environmental quality in a number of areas including environmental
planning, wildlife & habitat management, outreach & education, integrated pest management, water conservation, and water quality management.
Useful LifeProject Name Cart Path Addition Academy 9 Category Parks
Type Expand or enhance
Total Project Cost:$150,000
Total2025 2026 2027 2028 2029Expenditures 2030
150,000150,000Construction
150,000 150,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
150,000150,000Golf Course Fund
150,000 150,000Total
261
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Joe Abood
2025 2030thru Department Parks: Golf Course
Description
Utilize the Braemar property just south of John Harris Drive (Old #21) to create an Academy Training Facility. Short Course, Teaching Bays,
Practice Greens and Instruction area.
Project #P&R25180
Justification
Expansion and/or Level of Service
Sustainability: Braemar Golf Course is recognized for its Environmental Excellence as a “Certified Audubon Cooperative Sanctuary” through the
Audubon Cooperative Sanctuary Program for Golf Courses, an Audubon International program.
Braemar is one of 900 courses in the world to receive this honor for maintaining a high degree of environmental quality and natural resources in
areas including wildlife and habitat management, chemical use reduction and safety, water quality management and environmental planning.
Braemar was first certified in 2005 and has been able to retain the honor every three years during the recertification process.
Braemar’s Championship 18 opened in May 2019 after being transformed into a 6,884-yard regulation18-hole golf course. The redesign included a
significant environmental statement by restoring 4.37 acres of wetlands and enhancing a bit over a half-acre of additional wetlands, creating 32.11
acres of wetland buffer and introducing 33.85 acres of Oak Savanna throughout the course.
Community Engagement: At the heart of Braemar Golf Course lies a sense of camaraderie and social interaction. Braemar brings people together,
providing a platform for its patrons to connect, bond, and forge friendships. Braemar becomes a place where golfers of all skill levels, ages and
abilities can come together, share experiences, and create a welcoming atmosphere that extends beyond the fairways. It's this sense of belonging
that enhances the overall golfing experience and makes it truly special.
Health in All Policies: Golf is a great way to enjoy regular exercise, develop social connections, and manage stress.
Race & Equity: Braemar Golf Course is committed to being welcoming and inclusive to all who patronize the facility. To support and foster
inclusivity, Braemar staff members are dedicated to acknowledging, seeking out and celebrating the diversity of its customers and proactively
working together to eliminate systemic and institutional barriers to ensure all people have the opportunity to participate in golf at its facilities.
Stewardship: Braemar Golf Course is committed to maintaining the golf course to the highest standard while preserving and enhancing the
surrounding wildlife environment. Braemar demonstrates a high degree of environmental quality in a number of areas including environmental
planning, wildlife & habitat management, outreach & education, integrated pest management, water conservation, and water quality management.
Useful LifeProject Name Academy Training Facility Category Buildings
Type New
Total Project Cost:$500,000
Total2025 2026 2027 2028 2029Expenditures 2030
500,000500,000Construction
500,000 500,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
500,000500,000Golf Course Fund
500,000 500,000Total
262
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Joe Abood
2025 2030thru Department Parks: Golf Course
Description
As planned in the Braemar Park Master Plan, reconfigure and replace asphalt to make ADA accessible.
Project #P&R25181
Justification
Expansion and/or Level of Service
Sustainability: Braemar Golf Course is recognized for its Environmental Excellence as a “Certified Audubon Cooperative Sanctuary” through the
Audubon Cooperative Sanctuary Program for Golf Courses, an Audubon International program.
Braemar is one of 900 courses in the world to receive this honor for maintaining a high degree of environmental quality and natural resources in
areas including wildlife and habitat management, chemical use reduction and safety, water quality management and environmental planning.
Braemar was first certified in 2005 and has been able to retain the honor every three years during the recertification process.
Braemar’s Championship 18 opened in May 2019 after being transformed into a 6,884-yard regulation18-hole golf course. The redesign included a
significant environmental statement by restoring 4.37 acres of wetlands and enhancing a bit over a half-acre of additional wetlands, creating 32.11
acres of wetland buffer and introducing 33.85 acres of Oak Savanna throughout the course.
Community Engagement: At the heart of Braemar Golf Course lies a sense of camaraderie and social interaction. Braemar brings people together,
providing a platform for its patrons to connect, bond, and forge friendships. Braemar becomes a place where golfers of all skill levels, ages and
abilities can come together, share experiences, and create a welcoming atmosphere that extends beyond the fairways. It's this sense of belonging
that enhances the overall golfing experience and makes it truly special.
Health in All Policies: Golf is a great way to enjoy regular exercise, develop social connections, and manage stress.
Race & Equity: Braemar Golf Course is committed to being welcoming and inclusive to all who patronize the facility. To support and foster
inclusivity, Braemar staff members are dedicated to acknowledging, seeking out and celebrating the diversity of its customers and proactively
working together to eliminate systemic and institutional barriers to ensure all people have the opportunity to participate in golf at its facilities.
Stewardship: Braemar Golf Course is committed to maintaining the golf course to the highest standard while preserving and enhancing the
surrounding wildlife environment. Braemar demonstrates a high degree of environmental quality in a number of areas including environmental
planning, wildlife & habitat management, outreach & education, integrated pest management, water conservation, and water quality management.
Useful LifeProject Name Golf Course Parking Lot Upgrade Category Parks
Type Replace or repair
Total Project Cost:$1,000,000
Total2025 2026 2027 2028 2029Expenditures 2030
1,000,0001,000,000Construction
1,000,000 1,000,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
1,000,0001,000,000Local Option Sales Tax
1,000,000 1,000,000Total
263
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Joe Abood
2025 2030thru Department Parks: Golf Course
Description
Drainage upgrades on fairways #6, #11 and #16. Drainage lines to be installed to move water from low laying areas.
Project #P&R25182
Justification
Asset Functionality
Sustainability: Braemar Golf Course is recognized for its Environmental Excellence as a “Certified Audubon Cooperative Sanctuary” through the
Audubon Cooperative Sanctuary Program for Golf Courses, an Audubon International program.
Braemar is one of 900 courses in the world to receive this honor for maintaining a high degree of environmental quality and natural resources in
areas including wildlife and habitat management, chemical use reduction and safety, water quality management and environmental planning.
Braemar was first certified in 2005 and has been able to retain the honor every three years during the recertification process.
Braemar’s Championship 18 opened in May 2019 after being transformed into a 6,884-yard regulation18-hole golf course. The redesign included a
significant environmental statement by restoring 4.37 acres of wetlands and enhancing a bit over a half-acre of additional wetlands, creating 32.11
acres of wetland buffer and introducing 33.85 acres of Oak Savanna throughout the course.
Community Engagement: At the heart of Braemar Golf Course lies a sense of camaraderie and social interaction. Braemar brings people together,
providing a platform for its patrons to connect, bond, and forge friendships. Braemar becomes a place where golfers of all skill levels, ages and
abilities can come together, share experiences, and create a welcoming atmosphere that extends beyond the fairways. It's this sense of belonging
that enhances the overall golfing experience and makes it truly special.
Health in All Policies: Golf is a great way to enjoy regular exercise, develop social connections, and manage stress.
Race & Equity: Braemar Golf Course is committed to being welcoming and inclusive to all who patronize the facility. To support and foster
inclusivity, Braemar staff members are dedicated to acknowledging, seeking out and celebrating the diversity of its customers and proactively
working together to eliminate systemic and institutional barriers to ensure all people have the opportunity to participate in golf at its facilities.
Stewardship: Braemar Golf Course is committed to maintaining the golf course to the highest standard while preserving and enhancing the
surrounding wildlife environment. Braemar demonstrates a high degree of environmental quality in a number of areas including environmental
planning, wildlife & habitat management, outreach & education, integrated pest management, water conservation, and water quality management.
Useful LifeProject Name Golf Course Drainage Upgrade Category Parks
Type Expand or enhance
Total Project Cost:$40,000
Total2025 2026 2027 2028 2029Expenditures 2030
40,00040,000Construction
40,000 40,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
40,00040,000Golf Course Fund
40,000 40,000Total
264
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Joe Abood
2025 2030thru Department Parks: Golf Course
Description
Re-Grass and add irrigation system to the Academy 9 Clubhouse.
Project #P&R25183
Justification
Expansion and/or Level of Service
Sustainability: Braemar Golf Course is recognized for its Environmental Excellence as a “Certified Audubon Cooperative Sanctuary” through the
Audubon Cooperative Sanctuary Program for Golf Courses, an Audubon International program.
Braemar is one of 900 courses in the world to receive this honor for maintaining a high degree of environmental quality and natural resources in
areas including wildlife and habitat management, chemical use reduction and safety, water quality management and environmental planning.
Braemar was first certified in 2005 and has been able to retain the honor every three years during the recertification process.
Braemar’s Championship 18 opened in May 2019 after being transformed into a 6,884-yard regulation18-hole golf course. The redesign included a
significant environmental statement by restoring 4.37 acres of wetlands and enhancing a bit over a half-acre of additional wetlands, creating 32.11
acres of wetland buffer and introducing 33.85 acres of Oak Savanna throughout the course.
Community Engagement: At the heart of Braemar Golf Course lies a sense of camaraderie and social interaction. Braemar brings people together,
providing a platform for its patrons to connect, bond, and forge friendships. Braemar becomes a place where golfers of all skill levels, ages and
abilities can come together, share experiences, and create a welcoming atmosphere that extends beyond the fairways. It's this sense of belonging
that enhances the overall golfing experience and makes it truly special.
Health in All Policies: Golf is a great way to enjoy regular exercise, develop social connections, and manage stress.
Race & Equity: Braemar Golf Course is committed to being welcoming and inclusive to all who patronize the facility. To support and foster
inclusivity, Braemar staff members are dedicated to acknowledging, seeking out and celebrating the diversity of its customers and proactively
working together to eliminate systemic and institutional barriers to ensure all people have the opportunity to participate in golf at its facilities.
Stewardship: Braemar Golf Course is committed to maintaining the golf course to the highest standard while preserving and enhancing the
surrounding wildlife environment. Braemar demonstrates a high degree of environmental quality in a number of areas including environmental
planning, wildlife & habitat management, outreach & education, integrated pest management, water conservation, and water quality management.
Useful LifeProject Name Academy 9 Re-Grass & Irrigation Category Parks
Type Expand or enhance
Total Project Cost:$40,000
Total2025 2026 2027 2028 2029Expenditures 2030
40,00040,000Construction
40,000 40,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
40,00040,000Golf Course Fund
40,000 40,000Total
265
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Joe Abood
2025 2030thru Department Parks: Golf Course
Description
The drainage underneath the green on hole #8 sits lower than the pond so water has a really hard time exiting the green. Also, there is a large bird
bath where water can’t exit the surface of the green. When you cut a cup, you can notice the difference in the greens mix compared to other
greens. Propose to move the green on the other side of the pond to make it a true par 5. All this work can be completed without disrupting play.
You could build the green then once you close in the fall, remove existing green and base and sod it with fairway grass and add fairway to the right
of the pond leading up to green.
Project #P&R25184
Justification
Asset Functionality
Useful LifeProject Name Green Renovation/Relocation Hole #8 Category Parks
Type Expand or enhance
Total Project Cost:$500,000
Total2025 2026 2027 2028 2029Expenditures 2030
500,000500,000Construction
500,000 500,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
500,000500,000Golf Course Fund
500,000 500,000Total
266
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Joe Abood
2025 2030thru Department Parks: Golf Dome
Description
Upgrade electrical capacity at Golf Dome. In future operations, this will facilitate offering an enhanced experience for the golf dome customers
including the addition of television monitors to each bay.
Project #P&R21036
Justification
In strategic alignment with Edina’s mission statement to "offer premier public facilities".
Useful LifeProject Name Dome Electrical Update Category Buildings
Type Expand or enhance
Total Project Cost:$25,000
Total2025 2026 2027 2028 2029Expenditures 2030
25,00025,000Installation/Maintenance
25,000 25,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
25,00025,000Golf Course Fund
25,000 25,000Total
267
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Joe Abood
2025 2030thru Department Parks: Golf Dome
Description
Expand the Golf Dome building to include enhanced Food & Beverage offerings.
Project #P&R25185
Justification
Expansion and/or Level of Service
Sustainability: Braemar Golf Course is recognized for its Environmental Excellence as a “Certified Audubon Cooperative Sanctuary” through the
Audubon Cooperative Sanctuary Program for Golf Courses, an Audubon International program.
Braemar is one of 900 courses in the world to receive this honor for maintaining a high degree of environmental quality and natural resources in
areas including wildlife and habitat management, chemical use reduction and safety, water quality management and environmental planning.
Braemar was first certified in 2005 and has been able to retain the honor every three years during the recertification process.
Braemar’s Championship 18 opened in May 2019 after being transformed into a 6,884-yard regulation18-hole golf course. The redesign included a
significant environmental statement by restoring 4.37 acres of wetlands and enhancing a bit over a half-acre of additional wetlands, creating 32.11
acres of wetland buffer and introducing 33.85 acres of Oak Savanna throughout the course.
Community Engagement: At the heart of Braemar Golf Course lies a sense of camaraderie and social interaction. Braemar brings people together,
providing a platform for its patrons to connect, bond, and forge friendships. Braemar becomes a place where golfers of all skill levels, ages and
abilities can come together, share experiences, and create a welcoming atmosphere that extends beyond the fairways. It's this sense of belonging
that enhances the overall golfing experience and makes it truly special.
Health in All Policies: Golf is a great way to enjoy regular exercise, develop social connections, and manage stress.
Race & Equity: Braemar Golf Course is committed to being welcoming and inclusive to all who patronize the facility. To support and foster
inclusivity, Braemar staff members are dedicated to acknowledging, seeking out and celebrating the diversity of its customers and proactively
working together to eliminate systemic and institutional barriers to ensure all people have the opportunity to participate in golf at its facilities.
Stewardship: Braemar Golf Course is committed to maintaining the golf course to the highest standard while preserving and enhancing the
surrounding wildlife environment. Braemar demonstrates a high degree of environmental quality in a number of areas including environmental
planning, wildlife & habitat management, outreach & education, integrated pest management, water conservation, and water quality management.
Useful LifeProject Name Golf Dome Building Expansion Category Buildings
Type Expand or enhance
Total Project Cost:$3,000,000
Total2025 2026 2027 2028 2029Expenditures 2030
3,000,0003,000,000Construction
3,000,000 3,000,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
3,000,0003,000,000Golf Course Fund
3,000,000 3,000,000Total
268
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Derik Otten
2025 2030thru Department Parks: Liquor Stores
Description
Each building component was evaluated to determine needed maintenance and replacements to extend the buildings lifespan. The funding will be
used for project design and planning, roof, electrical system repairs, exterior envelope repairs, interior finishes repairs, plumbing system repairs,
and replacement of furniture, fixtures and equipment at the three liquor stores.
Project #FAC23110
Justification
This is a part of our City Work plan to maintain optimum facility operations.
Useful LifeProject Name Liquor Stores Facility Improvements Category Buildings
Type Replace or repair
Total Project Cost:$901,600
Total2025 2026 2027 2028 2029Expenditures 2030
57,60029,600 28,000Planning and Design
71,00071,000Vehicles and Equipment
773,000197,000 296,000 280,000Installation/Maintenance
297,600 324,000 280,000 901,600Total
Total2025 2026 2027 2028 2029Funding Sources 2030
901,600297,600 324,000 280,000Liquor Fund
297,600 324,000 280,000 901,600Total
269
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Aaron White
2025 2030thru Department Police
Description
Replacement of E911 Call Handling System.
Project #POL21005
Justification
Between 2014-2016 Edina partnered with Hennepin County, Minneapolis, HCMC, and Allina to deploy a state of the art shared E911 call handling
system. The system was forecast to have a service life of approximately 10 years. While it is hoped that ongoing upgrades will extend the service
life of this system it is important we plan for potential replacement in 2026. A major system refresh is being completed in 2022 so this replacement
has been deferred until 2027. This was previously funded split between both E911 and Equipment Replacement.
Useful LifeProject Name Dispatch E911 Call Handling System Category Technology
Type Replace or repair
Total Project Cost:$550,000
Total2025 2026 2027 2028 2029Expenditures 2030
550,000550,000Software
550,000 550,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
550,000550,000E911
550,000 550,000Total
270
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Aaron White
2025 2030thru Department Police
Description
Replacement of equipment according to the equipment replacement schedule. This includes essential equipment such as squads, safety equipment
and technology, among other items.
2025 Equipment Levy:
2018 Dodge Durango
2018 Dodge Durango
2018 Chevrolet Traverse
2018 Jeep Grand Cherokee
2018 Jeep Grand Cherokee
Ford Interceptor AWD K8A S 26-215
2025 Public Safety Aid:
Mobile Pro Defender Camera System
License Plate Readers (ALPR/2017-2020)
2026 Equipment Levy:
Speed Measurement Radar Equipment (Stalker Radar)
SWAT Team Rifles
2019 Ford Interceptor Utility - Black/Ebony
2019 Toyota RAV4
2019 Toyota Highlander LE Hybrid - Model 6964
2021 Ford F-150 Hybrid
2021 Ford F-150 Hybrid
2026 E911:
Dispatch Radio Consoles
2027 Equipment Levy:
Computer Forensics Analysis Workstation
StarChase Pursuit Intervention System
2020 Ford Explorer
2018 Dodge Grand Caravan
2022 Ford Interceptor Utility
2022 Ford Interceptor Utility
2022 Ford Lightning EV
2020 Ford Explorer (Unmarked)
2020 Toyota Rav4 Hybrid XLE (Unmarked)
2023 Ford Lightning
2023 Ford Lightning
2023 Police Interceptor Utility Vehicle
2023 Police Interceptor Utility Vehicle
2023 Police Interceptor Utility Vehicle
2023 Police Interceptor Utility Vehicle
2027 E911:
E911 Call Handling System (CHS-1)
2028 Equipment Levy:
License Plate Readers (ALPR/2021)
StarChase Pursuit Intervention System
2017 Harley Davidson Motorcycle
2017 Harley Davidson Motorcycle
Project #POL23200 Useful LifeProject Name Police Equipment Replacement Category Equipment and Vehicles
Type Replace or repair
Total Project Cost:$4,215,300
271
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Aaron White
2025 2030thru Department Police
2024 Ford Explorer Utility
2024 Ford Explorer Utility
2024 Ford Explorer Utility
2024 Ford Explorer Utility
2024 Chevy Blazer PPV EV
2024 Chevy Blazer PPV EV
2028 E911:
911 Logging System
2029 Equipment Levy:
Patrol Rifles
Tasers
2022 Ford Mach E - EV
2022 Toyota Rav4 Hybrid
2022 Toyota Highlander Hybrid
2022 Toyota Highlander Hybrid
2024 Ford Explorer Utility
2024 Dodge Durango Squad
2030 Equipment Levy:
Tasers Replacement Program
SWAT Vests
2023 Hyundai Santa Fe Hybrid
Justification
As outlined in Vision Edina, it is the mission of the City Council to provide effective and valued public services and maintain a sound public
infrastructure. Regular replacement of police safety equipment,technology and vehicles allows the city to maintain a high level of quality service
provided to the residents of the City of Edina. Timely replacement of equipment also ensures equipment reliability while keeping maintenance
costs low.
Total2025 2026 2027 2028 2029Expenditures 2030
4,215,300440,000 833,000 1,417,800 616,000 690,000Vehicles and Equipment 218,500
440,000 833,000 1,417,800 616,000 690,000 4,215,300Total218,500
Total2025 2026 2027 2028 2029Funding Sources 2030
3,052,300330,000 358,000 867,800 588,000 690,000Construction Fund: Equipment
Levy
218,500
1,053,000475,000 550,000 28,000E911
110,000110,000Public Safety Aid
440,000 833,000 1,417,800 616,000 690,000 4,215,300Total218,500
272
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Aaron White
2025 2030thru Department Police
Description
This will add a fully marked patrol squad to the police fleet. A total of (4) patrol officers are being added to the department between 2024-25. An
additional squad car is required to accommodate this increased staffing. The cost includes the vehicle, emergency equipment, and upfitting costs.
Costs are higher for the initial build of this squad car due to systems that are typically purchased for the entire fleet under other projects. This build
includes a mobile radio, radar/LIDAR, first aid/AED equipment, mobile computer, squad mounted weapons, and the in squad video system.
***May be eligible for Public Safety Grant Funding***
Project #POL25101
Justification
Expansion and/or Level of Service
Sustainability: The Police Department continues to incorporate fully electric (EV) and hybrid vehicles into our fleet. Vehicle procurement for
police squads has become very difficult in recent years and the final selection will be based on vehicle availability and balancing the fleet
appropriately to assure maximum availability of emergency response vehicles.
Community Engagement: Fully marked police vehicles are a highly visible and provide a sense of safety and security in the community.
Health in All Policies: An adequate and reliable fleet of emergency response vehicles is essential for our police officers to carry out their job duties.
Race & Equity: Promotes accessibility of police services to all members of the community.
Stewardship: The police department continues to responsibly manage our fleet to maximize efficiency and minimize cost while prioritizing public
safety and employee safety.
Useful LifeProject Name Patrol Squad Car Addition Category Equipment and Vehicles
Type New
Total Project Cost:$130,000
Total2025 2026 2027 2028 2029Expenditures 2030
130,00070,000 60,000Vehicles and Equipment
70,000 60,000 130,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
60,00060,000Construction Fund: Equipment
Levy
70,00070,000Public Safety Aid
70,000 60,000 130,000Total
273
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Aaron White
2025 2030thru Department Police
Description
Purchase (4) rifle-rated ballistic shields for Police operations. Police Officers are facing an unprecedented number of threats involving firearms.
This continues to evolve to include rifle fire including tragic incidents in 2024 in Burnsville and Minnetonka. Police body armor and existing
ballistic shields are not rated to protect against rifle threats. This is essential equipment to protect Police Officers responding to active shooter
situations and other firearm threats. Two shields will be placed in our SWAT vehicle and two shields will be deployed in our Patrol Sergeant
squads to assure rapid availability in the field. ***May be eligible for Public Safety Grant Funding***
Project #POL25103
Justification
Health, Safety & Regulatory Compliance, Expansion and/or Level of Service
Sustainability: This project has no immediate sustainability impacts.
Community Engagement: The community expects Police Officers to be equipped to immediately respond to violent acts including active shooters
and other armed threats that have unfortunately become more common. This equipment assures our officers will be better equipped to intervene
more quickly and safely when encountering rifle threats.
Health in All Policies: We have an obligation to our employees to provide the equipment necessary to keep them safe. Technology, tactics, and
threats rapidly evolve and this investment is critical to keep us properly equipped.
Race & Equity: Promotes accessibility of police services to all members of the community.
Stewardship: This is a direct investment in officer safety and wellness as our staff faces increasing hazards in their work.
Useful LifeProject Name Rifle-Rated Ballistic Shields Category Equipment and Vehicles
Type New
Total Project Cost:$40,000
Total2025 2026 2027 2028 2029Expenditures 2030
40,00040,000Vehicles and Equipment
40,000 40,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
40,00040,000Public Safety Aid
40,000 40,000Total
274
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Aaron White
2025 2030thru Department Police
Description
Replace the bi-directional amplifier (BDA) system installed in City Hall. The BDA allows ARMER portable radios used by Police, Fire, and
Public Works to function inside of City Hall / Police Department. These systems are critical for public safety and required by code. ARMER
radios do not function in several areas of City Hall/Police without an operational BDA. The current BDA was installed in 2016 and is reaching the
end of it's useful life. The original infrastructure used by this system including coaxial cables and antennas dates back to 2004. This project will
replace the BDA device and replace any antenna/cable infrastructure that does not meet current standards.
Project #POL25107
Justification
Asset Functionality, Health, Safety & Regulatory Compliance
Sustainability: Existing electronic equipment will be recycled properly.
Community Engagement: This equipment allows public safety personnel to operate safely and efficiently. This includes protection of City staff and
assets.
Health in All Policies: This project replaces critical life safety equipment in City Hall/Police Department that is required by code.
Race & Equity: Promotes accessibility of police services to all members of the community.
Stewardship: When the original ARMER BDA system (2004) failed in 2016 the department was able to repurpose infrastructure from an
abandoned system for legacy cellular devices to significantly reduce the project cost by over $60,000. Proper maintenance has provided a longer
than expected service life for the 2016 system. This investment maintains a critical system while continuing to minimize cost.
Useful LifeProject Name PS Radio Bi-Directional Amplifier (BDA) Rplcmt Category Equipment and Vehicles
Type Replace or repair
Total Project Cost:$25,000
Total2025 2026 2027 2028 2029Expenditures 2030
25,00025,000Vehicles and Equipment
25,000 25,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
25,00025,000Public Safety Aid
25,000 25,000Total
275
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Dave Goergen
2025 2030thru Department Public Works
Description
This project would include the rehabilitation of Well # 7 by repairing or replacing the well pump, motor, and other worn equipment.
ENVIRONMENTAL CONSIDERATIONS:
Motor and pump assembly are premium efficient rated and controlled by Variable Frequency Drives (VFD) that optimize energy use and pump
efficiency.
Project #19-913
Justification
Our Vision Edina mission statement is to provide effective and valued public services and to maintain a sound public infrastructure. Specifically,
the Comprehensive Plan identifies a goal to provide the City’s water customers with safe, reliable, high quality potable water supply. In order to
provide a reliable, sound infrastructure, the Public Works Department has implemented a well rehabilitation schedule based on one billion gallons
pumped.
Useful LifeProject Name Well #7 Rehabilitation Category Infrastructure
Type Replace or repair
Total Project Cost:$300,000
Total2025 2026 2027 2028 2029Expenditures 2030
300,000180,000 120,000Installation/Maintenance
180,000 120,000 300,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
300,000180,000 120,000Utility Fund: Water
180,000 120,000 300,000Total
276
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Dave Goergen
2025 2030thru Department Public Works
Description
This project would include the rehabilitation of Well # 11 by repairing or replacing the well pump, motor, and other worn equipment. It would also
inlcude replacing:
2023 - Exterior doors and Interior doors, roof replacement, painting, gas unit heaters, controls, lighting fixtures, crackfilling/ sealing stucco walls,
fire alarm system and sprinklers.
ENVIRONMENTAL CONSIDERATIONS:
Motor and pump assembly are premium efficient rated and controlled by Variable Frequency Drives (VFD) that optimize energy use and pump
efficiency.
Project #19-915
Justification
Our Vision Edina mission statement is to provide effective and valued public services and to maintain a sound public infrastructure. Specifically,
the Comprehensive Plan identifies a goal to provide the City’s water customers with safe, reliable, high quality potable water supply. In order to
provide a reliable, sound infrastructure, the Public Works Department has implemented a well rehabilitation schedule based on one billion gallons
pumped.
Useful LifeProject Name Well #11 Rehabilitation and Facility Improvements Category Infrastructure
Type Replace or repair
Total Project Cost:$240,000
Total2025 2026 2027 2028 2029Expenditures 2030
240,000120,000Construction 120,000
120,000 240,000Total120,000
Total2025 2026 2027 2028 2029Funding Sources 2030
240,000120,000Utility Fund: Water 120,000
120,000 240,000Total120,000
277
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Dave Goergen
2025 2030thru Department Public Works
Description
This project would include the rehabilitation of Well #20 by repairing or replacing the well pump, motor, and other worn equipment.
ENVIRONMENTAL CONSIDERATIONS:
Motor and pump assembly are premium efficient rated and controlled by Variable Frequency Drives (VFD) that optimize energy use and pump
efficiency.
Project #19-918
Justification
Our Vision Edina mission statement is to provide effective and valued public services and to maintain a sound public infrastructure. Specifically,
the Comprehensive Plan identifies a goal to Provide the City’s water customers with safe, reliable, high quality potable water supply. In order to
provide a reliable, sound infrastructure, the Public Works Department has implemented a well rehabilitation schedule based on one billion gallons
pumped.
Useful LifeProject Name Well #20 Rehabilitation Category Infrastructure
Type Replace or repair
Total Project Cost:$180,000
Total2025 2026 2027 2028 2029Expenditures 2030
180,000180,000Construction
180,000 180,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
180,000180,000Utility Fund: Water
180,000 180,000Total
278
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Ryan Browning
2025 2030thru Department Public Works
Description
A fiber connection is required to replace the existing wireless connection. This new fiber connection will improve the speed and reliability allowing
improvements for computer use and security in the building.
Project #ITS25100
Justification
Expansion and/or Level of Service
Sustainability: This connection will require less network hardware replacement and less power.
Stewardship: This connection will cost less over its lifetime and provide better service than the existing wireless connection
Useful LifeProject Name CLP Maintenance Fiber Category Technology
Type New
Total Project Cost:$30,000
Total2025 2026 2027 2028 2029Expenditures 2030
30,00030,000Construction
30,000 30,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
30,00030,000Construction Fund: CIP Levy
30,000 30,000Total
279
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Ryan Browning
2025 2030thru Department Public Works
Description
We are nearly out of fiber strands heading north from City Hall to St. Louis Park. Additional strands will be needed for fiber projects in the north
end of town as well as projects that need to connect to LOGIS or Hennepin County. This would install a new fiber optic cable with plenty of
strands to support operations well into the future.
Project #ITS25101
Justification
Expansion and/or Level of Service
Sustainability: Fiber connections are often the network backbone that supports many types of projects.
Stewardship: Fiber connections offer speed and security to all sorts of City projects. Fiber also offers a long service life.
Useful LifeProject Name Increase Fiber Capacity to SLP Category Technology
Type New
Total Project Cost:$60,000
Total2025 2026 2027 2028 2029Expenditures 2030
60,00060,000Construction
60,000 60,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
60,00060,000Construction Fund: CIP Levy
60,000 60,000Total
280
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Brian Olson
2025 2030thru Department Public Works
Description
Replacing larger retaining walls citywide. We have a list of needed improvements.
Project #PW22002
Justification
Retaining wall failures for larger walls completely exhaust our budget and often need to be funded by our bridge maintenance budget causing
significant deferred maintenance on our bridges
Useful LifeProject Name Annual Deferred Retaining Wall Replacements Category Infrastructure
Type Replace or repair
Total Project Cost:$750,000
Total2025 2026 2027 2028 2029Expenditures 2030
750,00050,000 100,000 200,000 200,000Construction 200,000
50,000 100,000 200,000 200,000 750,000Total200,000
Total2025 2026 2027 2028 2029Funding Sources 2030
750,00050,000 100,000 200,000 200,000Construction Fund: CIP Levy 200,000
50,000 100,000 200,000 200,000 750,000Total200,000
281
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Brian Olson
2025 2030thru Department Public Works
Description
This project would include the rehabilitation of Well #15 by repairing and replacing the well pump, motor and other worn equipment.
ENVIRONMENTAL CONSIDERATIONS:
Motor and Pump Assembly efficiency are controlled by Variable Frequency Drives (VFD) that optimize energy use and pump efficiency. The more
efficent the pump the less energy used.
Project #PW23002
Justification
Our Vision Edina mission statement is to provide efficient and valued public services and to maintain sound public infrastructure. Specifically, our
Comprehgensive Plan identifies a goal to provide the City's water customers with safe, reliable, high quality potable water supply. In order to
provide a reliable, sound infrastructure, the Public Works Department has implemented a well rehabilitation schedule based on one billion gallons
water pumped.
Useful LifeProject Name Well #15 Rehabilitation and Facility Improvements Category Infrastructure
Type Replace or repair
Total Project Cost:$140,000
Total2025 2026 2027 2028 2029Expenditures 2030
140,000Construction140,000
140,000Total140,000
Total2025 2026 2027 2028 2029Funding Sources 2030
140,000Utility Fund: Water 140,000
140,000Total140,000
282
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Brian Olson
2025 2030thru Department Public Works
Description
This project would include the rehabilitation of Well #10 by repairing and replacing the well pump, motor and other worn equipment.
ENVIRONMENTAL CONSIDERATIONS:
Motor and Pump Assembly efficiency are controlled by Variable Frequency Drives (VFD) that optimize energy use and pump efficiency. The more
efficent the pump the less energy used.
Project #PW23004
Justification
Our Vision Edina mission statement is to provide efficient and valued public services and to maintain sound public infrastructure. Specifically, our
Comprehgensive Plan identifies a goal to provide the City's water customers with safe, reliable, high quality potable water supply. In order to
provide a reliable, sound infrastructure, the Public Works Department has implemented a well rehabilitation schedule based on one billion gallons
water pumped.
Useful LifeProject Name Well #10 Rehabilitation and Facility Improvements Category Infrastructure
Type Replace or repair
Total Project Cost:$120,000
Total2025 2026 2027 2028 2029Expenditures 2030
120,000Construction120,000
120,000Total120,000
Total2025 2026 2027 2028 2029Funding Sources 2030
120,000Utility Fund: Water 120,000
120,000Total120,000
283
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Brian Olson
2025 2030thru Department Public Works
Description
This project would include the rehabilitation of Well #12 by repairing and replacing the well pump, motor and other worn equipment.
ENVIRONMENTAL CONSIDERATIONS:
Motor and Pump Assembly efficiency are controlled by Variable Frequency Drives (VFD) that optimize energy use and pump efficiency. The more
efficent the pump the less energy used.
Project #PW23005
Justification
Our Vision Edina mission statement is to provide efficient and valued public services and to maintain sound public infrastructure. Specifically, our
Comprehgensive Plan identifies a goal to provide the City's water customers with safe, reliable, high quality potable water supply. In order to
provide a reliable, sound infrastructure, the Public Works Department has implemented a well rehabilitation schedule based on one billion gallons
water pumped.
Useful LifeProject Name Well #12 Rehabilitation and Facility Improvements Category Infrastructure
Type Replace or repair
Total Project Cost:$180,000
Total2025 2026 2027 2028 2029Expenditures 2030
180,000180,000Construction
180,000 180,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
180,000180,000Utility Fund: Water
180,000 180,000Total
284
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Brian Olson
2025 2030thru Department Public Works
Description
This project would include the rehabilitation of Well #20 by repairing and replacing the well pump, motor and other worn equipment.
ENVIRONMENTAL CONSIDERATIONS:
Motor and Pump Assembly efficiency are controlled by Variable Frequency Drives (VFD) that optimize energy use and pump efficiency. The more
efficent the pump the less energy used.
Project #PW23006
Justification
Our Vision Edina mission statement is to provide efficient and valued public services and to maintain sound public infrastructure. Specifically, our
Comprehgensive Plan identifies a goal to provide the City's water customers with safe, reliable, high quality potable water supply. In order to
provide a reliable, sound infrastructure, the Public Works Department has implemented a well rehabilitation schedule based on one billion gallons
water pumped.
Useful LifeProject Name Well #13 Rehabilitation and Facility Improvements Category Infrastructure
Type Replace or repair
Total Project Cost:$180,000
Total2025 2026 2027 2028 2029Expenditures 2030
180,000180,000Construction
180,000 180,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
180,000180,000Utility Fund: Water
180,000 180,000Total
285
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Brian Olson
2025 2030thru Department Public Works
Description
This project would include the rehabilitation of Well #2 by repairing and replacing the well pump, motor and other worn equipment.
ENVIRONMENTAL CONSIDERATIONS:
Motor and Pump Assembly efficiency are controlled by Variable Frequency Drives (VFD) that optimize energy use and pump efficiency. The more
efficent the pump the less energy used.
Project #PW23007
Justification
Our Vision Edina mission statement is to provide efficient and valued public services and to maintain sound public infrastructure. Specifically, our
Comprehgensive Plan identifies a goal to provide the City's water customers with safe, reliable, high quality potable water supply. In order to
provide a reliable, sound infrastructure, the Public Works Department has implemented a well rehabilitation schedule based on one billion gallons
water pumped.
Useful LifeProject Name Well #2 Rehabilitation and Facility Improvements Category Infrastructure
Type Replace or repair
Total Project Cost:$170,000
Total2025 2026 2027 2028 2029Expenditures 2030
170,000170,000Construction
170,000 170,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
170,000170,000Utility Fund: Water
170,000 170,000Total
286
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Brian Olson
2025 2030thru Department Public Works
Description
This project would include the rehabilitation of Well #6 by repairing and replacing the well pump, motor and other worn equipment.
ENVIRONMENTAL CONSIDERATIONS:
Motor and Pump Assembly efficiency are controlled by Variable Frequency Drives (VFD) that optimize energy use and pump efficiency. The more
efficent the pump the less energy used.
Project #PW23008
Justification
Our Vision Edina mission statement is to provide efficient and valued public services and to maintain sound public infrastructure. Specifically, our
Comprehgensive Plan identifies a goal to provide the City's water customers with safe, reliable, high quality potable water supply. In order to
provide a reliable, sound infrastructure, the Public Works Department has implemented a well rehabilitation schedule based on one billion gallons
water pumped.
Useful LifeProject Name Well #6 Rehabilitation and Facility Improvements Category Infrastructure
Type Replace or repair
Total Project Cost:$180,000
Total2025 2026 2027 2028 2029Expenditures 2030
180,000180,000Construction
180,000 180,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
180,000180,000Utility Fund: Water
180,000 180,000Total
287
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Brian Olson
2025 2030thru Department Public Works
Description
This project would include the annual rehabilitation of a Lift Station by repairing and replacing the well pump, motor and other worn equipment.
ENVIRONMENTAL CONSIDERATIONS:
Motor and Pump Assembly efficiency are controlled by Variable Frequency Drives (VFD) that optimize energy use and pump efficiency. The more
efficent the pump the less energy used.
Project #PW23009
Justification
Our Vision Edina mission statement is to provide efficient and valued public services and to maintain sound public infrastructure. Specifically, our
Comprehgensive Plan identifies a goal to provide the City's sewer customers with safe, reliable, and efficient removal of wastewater for residents
and customers in the City of Edina, while eliminating risk of inflow, infiltration, and backflow to protectthe health, safety, and welfare of our
citizens now and into the future.
Useful LifeProject Name Lift Station Pump and VFD Renewal Category Infrastructure
Type Replace or repair
Total Project Cost:$180,000
Total2025 2026 2027 2028 2029Expenditures 2030
180,00030,000 30,000 30,000 30,000 30,000Construction 30,000
30,000 30,000 30,000 30,000 30,000 180,000Total30,000
Total2025 2026 2027 2028 2029Funding Sources 2030
180,00030,000 30,000 30,000 30,000 30,000Utility Fund: Sewer 30,000
30,000 30,000 30,000 30,000 30,000 180,000Total30,000
288
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Brian Olson
2025 2030thru Department Public Works
Description
Replace equipment according to the equipment replacement schedule. The Public Works Department has almost $10 million of equipment covered
under this program. Types of equipment include small machinery, passenger vehicles and heavy equipment. Most of this equipment has an
estimated useful life of between 10-20 years.
2025 Equipment Levy:
2013 GMC Sierra
2013 GMC Sierra
2004 Clark C25C
51" SnoQuip XX Blower
Patch King 6 Ton Patch Box
2015 Ford F350
7433S Case Loader
2026 Equipment Levy:
Used 2010 TR MT6 Trackless Tractor
L8500 Sterling
MT6 Trackless
2027 Equipment Levy:
Weiler TT500 Tack Trailer
2027 CIP Bonds - Equip Cert:
MT6 Trackless MT1963
2012 International 7400 4x2 Truck
Weiler P385 Paver
2015 Western Star 4700SB
2028 Equipment Levy:
Equip Cert Payment
CAT SW345B 3" Wheel Saw
Crafco SS125 Diesel Melter
2002 Allu SM3-23
2018 Ford F550
2016 Ford F550
2017 Ford F350
2029 Equipment Levy:
Equip Cert Payment
Towmaster T14DT Trailer
2014 Caterpillar 272D Skid Steer
MT6 Trackless Sidewalk Machine
2017 Western Star Tandem Axle Truck
Hypac C747 Roller
2030 Equipment Levy:
Equip Cert Payment
Gilcrest Asphalt Tailgate Paver
2017 Caterpillar Skid Steer
2017 Ford F350
2020 Kenworth K370 Truck w/Velocity Patcher
Asphalt Trailer
Project #PWK23200 Useful LifeProject Name Public Works Equipment Replacement Category Equipment and Vehicles
Type Replace or repair
Total Project Cost:$4,214,107
289
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Brian Olson
2025 2030thru Department Public Works
Justification
As outlined in Vision Edina, it is the mission of the City Council is to provide effective and valued public services and maintain a sound public
infrastructure. Regular updates to equipment helps to keep maintenance costs low but most importantly allows us to keep maintaining our snow
removal in an efficient manner. Breakdowns delay performance. We are being fiscally responsible with our fleet as is outlined in our IQS and we
cannot perform the functions of a Public Works Department without a reliable fleet.
Total2025 2026 2027 2028 2029Expenditures 2030
4,214,107583,500 830,000 23,000 767,684 1,089,000Vehicles and Equipment 920,923
583,500 830,000 23,000 767,684 1,089,000 4,214,107Total920,923
Total2025 2026 2027 2028 2029Funding Sources 2030
4,214,107583,500 830,000 23,000 767,684 1,089,000Construction Fund: Equipment
Levy
920,923
583,500 830,000 23,000 767,684 1,089,000 4,214,107Total920,923
290
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Brian Olson
2025 2030thru Department Public Works
Description
Replace equipment according to the equipment replacement schedule. The Public Works and Parks maintenance Department has almost $10
million of equipment covered under this program. Types of equipment include small machinery, passenger vehicles and heavy equipment. Most of
this equipment has an estimated useful life of between 10-20 years.
2025:
2005 Kohler 300REOZVW
2015 Ford F250
2018 Volvo ECR88D
2026:
1996 Towmaster T12DD Trailer
2006 Thompson 6" water pump
2016 Ford F550
2027:
2007 Bluestar 175 Kw generator
2007 Multiquip Light Plant
2016 Westernstar 4700 Vaccon
2017 Ford F250
2028:
2017 Ford F350
2002 Speco easment machine
2013 Ford F550
2017 GMC Serri
2018 F150
2018 F150
2029:
2004 Katolight D300FJ4
2004 Cat 3456
2003 Cat 400Kw generator
2006 Bluestar BSJ300 300KW generator
2009 Cat 80Kw generator
2019 Ford F150
2019 Ford F150
2030:
2005 Kohler 300 kW generator
2020 Dulevo Sweeper
2020 F150
Project #PWK23201
Justification
As outlined in Vision Edina, it is the mission of the City Council is to provide effective and valued public services and maintain a sound public
infrastructure. Regular updates to equipment helps to keep maintenance costs lower but most importantly allows us to keep maintaining our snow
removal in an efficient manner. Breakdowns delay performance. We are being fiscally responsible with our fleet as is outlined in our IQS and we
cannot perform the functions of a Public Works Department without a reliable fleet.
Useful LifeProject Name Utilities Equipment Replacement Category Equipment and Vehicles
Type Replace or repair
Total Project Cost:$2,735,000
291
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Brian Olson
2025 2030thru Department Public Works
Total2025 2026 2027 2028 2029Expenditures 2030
2,735,000355,000 200,000 677,000 297,000 642,000Vehicles and Equipment 564,000
355,000 200,000 677,000 297,000 642,000 2,735,000Total564,000
Total2025 2026 2027 2028 2029Funding Sources 2030
2,735,000355,000 200,000 677,000 297,000 642,000Utility Fund 564,000
355,000 200,000 677,000 297,000 642,000 2,735,000Total564,000
292
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Nathan Kaderlik
2025 2030thru Department Public Works
Description
This for water meter reading migration from AMR to AMI(drive by reading vs. push button real-time). We will be focusing on replacing
commercial meters 1 1/2" and bigger in years 1 and 2, as these meters have the most potential for water lost. Years 2-5 will include replacement of
residential meters. The replacement of these meters will allow us to fully utilize the AMI system.
Project #PWK25101
Justification
Expansion and/or Level of Service
Sustainability: No fuel consumption for driving meter reading routes.
Community Engagement: Expansion/upgrade of existing meter reading network allows for real-time monitoring and control of utility assets.
Health in All Policies: Provide the City’s water customers with safe, reliable, high quality potable water supply
Stewardship: "The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer
premier public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and
uncommonly high quality of life enjoyed by our residents and businesses.”
The City’s Budget Work Plan Goals 1 and 3 are: Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable Development.
Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient operations that lessen the City’s
carbon footprint and reduce energy costs.
"
Useful LifeProject Name Water Meter Radio Receivers Category Technology
Type Expand or enhance
Total Project Cost:$4,970,000
Total2025 2026 2027 2028 2029Expenditures 2030
4,970,0001,300,000 880,000 900,000 930,000 960,000Construction
1,300,000 880,000 900,000 930,000 960,000 4,970,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
4,970,0001,300,000 880,000 900,000 930,000 960,000Utility Fund: Water
1,300,000 880,000 900,000 930,000 960,000 4,970,000Total
293
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Nathan Kaderlik
2025 2030thru Department Public Works
Description
Inspect and evaluate existing filter media for possible replacement at Water Treatment Plants #2, #3 and #4.
Project #PWK25102
Justification
Asset Functionality
Sustainability: Proper media depths and material are crucial for efficient water filtration.
Health In All Policies: Provide the City’s water customers with safe, reliable, high quality potable water supply
Stewardship: "The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer
premier public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and
uncommonly high quality of life enjoyed by our residents and businesses.”
The City’s Budget Work Plan Goals 1 and 3 are: Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable Development.
Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient operations that lessen the City’s
carbon footprint and reduce energy costs.
"
Useful LifeProject Name Filter Media Replacement Category Infrastructure
Type Replace or repair
Total Project Cost:$450,000
Total2025 2026 2027 2028 2029Expenditures 2030
450,000450,000Construction
450,000 450,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
450,000450,000Utility Fund: Water
450,000 450,000Total
294
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Nathan Kaderlik
2025 2030thru Department Public Works
Description
Extend Fiber network to Van Valkenburg Water Tower(4949 Malibu Dr)
Project #PWK25103
Justification
Expansion and/or Level of Service
Sustainability: Fiber expansion would eliminate the use of current radio communication, lessening electrical load.
Community Engagement: Expansion of existing fiber network allows for real-time monitoring and control of utility assets.
Health in All Policies: This project will help provide the City’s water customers with safe, reliable, high quality potable water supply.
Stewardship: "The City’s mission statement “is to provide effective and valued public services, maintain a sound public infrastructure, offer
premier public facilities, and guide the development and redevelopment of lands, all in a manner that sustains and improves the health and
uncommonly high quality of life enjoyed by our residents and businesses.”
The City’s Budget Work Plan Goals 1 and 3 are: Maintain Physical Assets & Infrastructure and Plan for Connected & Sustainable Development.
Properly maintained streets, water main, sanitary sewer and storm sewer systems provide reliable and efficient operations that lessen the City’s
carbon footprint and reduce energy costs.
"
Useful LifeProject Name Fiber Installation, Van Valkenburg Tower Category Infrastructure
Type Expand or enhance
Total Project Cost:$160,000
Total2025 2026 2027 2028 2029Expenditures 2030
160,000160,000Construction
160,000 160,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
160,000160,000Utility Fund: Water
160,000 160,000Total
295
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Derik Otten
2025 2030thru Department Public Works
Description
This project will support Edina’s Climate Action Plan by introducing a dedicated 100 percent biodiesel fueling system to support the city’s heavy-
duty fleet. The new fuel will require the acquisition of a containment vessel and distribution pumps that will be located at Public Works near
existing fuel islands. Modifications to the site including concrete pad and bollards to support the system and electrical infrastructure upgrades.
Project #PWK25104
Justification
Expansion and/or Level of Service
Sustainability: Converting heavy-duty fleet to biodiesel is a key strategy to achieving our Climate Action Plan (CAP) goals to reduce greenhouse
gas emission for city operations. This project specifically supports CAP strategy TL-5.
Community Engagement: These projects encourage people to interact with staff to understand the importance of biodiesel. Focusing on city fleet,
this project does not contain an engagement component but provides the community an opportunity to see the city lead by example.
Health in All Policies: Biodiesel vehicles are low-emission vehicles, meaning they have lower harmful tailpipe emissions that negatively impact air
quality. This project will result in the consumption of B100 fuel, which has no tailpipe emissions.
Race & Equity: Lowering or removing tailpipe emissions from our heavy-duty fleet improves tailpipe emissions which negatively impact low-
income and under-served communities at a higher rate.
Stewardship: The fueling tank and vehicle retrofit systems will be used by existing heavy-duty vehicles, removing the need to purchase new
replacement vehicles, and prolonging the useful life of our existing heavy-duty fleet.
Useful LifeProject Name Public Works Fleet - Bio Diesel Storage Tanks Category Equipment and Vehicles
Type Expand or enhance
Total Project Cost:$375,000
Total2025 2026 2027 2028 2029Expenditures 2030
375,000375,000Vehicles and Equipment
375,000 375,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
375,000375,000CAS Fund: Utility Franchise
Fees
375,000 375,000Total
296
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Ryan Browning
2025 2030thru Department Technology
Description
Replacement of equipment according to the equipment replacement schedule. This includes essential equipment such as copiers and printers,
servers, camera systems and switch batches, among other items.
2025:
Citywide Switch Batch 2
IT Storage Replacement
Server Replacements ESX
2026:
Fire Control Systems at City Hall and PW
Ricoh MFP - Building
Cisco Access Points Batch 2 (25)
2027:
PD & CH Surveillance Cameras
City Hall UPS System - Full Replacement
Citywide Switch Batch 3
Ricoh MFP - Admin
Ricoh MFP - P&R
Citywide Switch Batch 4
Squad Car Technology Upgrades
City Hall UPS System (Batteries Only)
Server Replacements ESX
2028:
Cisco Phone System
Cisco Access Point batch 3 (21)
Citywide Switch Batch 5
Fire Apparatus Tech (TB, iPad & Install)
PW UPS (Batteries Only)
Cisco Access Point batch 3 (21)
Citywide Switch Batch 5
2029:
Fire Station 1 Security
Fire Station 2 Security
Fire Station Camera System
Ricoh MFP - Police (1st Floor and 2nd Floor)
Citywide Switch Batch 1 (Core and FW)
Citywide Access Point Batch 1 (50)
2030:
Ricoh MFP - PW
Citywide Switch Batch 2
IT Storage Replacement
Project #ITS23100 Useful LifeProject Name IT Equipment Replacement Category Equipment and Vehicles
Type Replace or repair
Total Project Cost:$2,340,000
297
Capital Improvement Plan - FUNDED
City of Edina, Minnesota Contact Ryan Browning
2025 2030thru Department Technology
Justification
As outlined in Vision Edina, it is the mission of the City Council to provide effective and valued public services and maintain a sound public
infrastructure. Regular replacement of copiers and printers, servers, camera systems and other technology equipment allows the city to maintain a
high level of quality service provided to the residents of the City of Edina. Timely replacement of equipment also ensures equipment reliability
while keeping maintenance costs low.
Total2025 2026 2027 2028 2029Expenditures 2030
2,340,000440,000 95,000 633,000 500,000 294,000Vehicles and Equipment 378,000
440,000 95,000 633,000 500,000 294,000 2,340,000Total378,000
Total2025 2026 2027 2028 2029Funding Sources 2030
2,340,000440,000 95,000 633,000 500,000 294,000Construction Fund: Equipment
Levy
378,000
440,000 95,000 633,000 500,000 294,000 2,340,000Total378,000
298
FUNDING TBD PROJECTS BY
DEPARTMENT
299
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota
PROJECTS BY FUNDING SOURCE
2025 2030thru
Total2026202720282029Source2030Project # 2025
Funding TBD
15-049Lewis Park Shelter Building Replacement 900,000900,000
19-946Walnut Ridge Park Facility Improvements 24,00024,000
DEV25104HRA Grandview Commons public space.2,500,0002,500,000
DEV25105HIA Funding 5,000,0002,500,000 2,500,000
DEV25106Cahill Area New District Plan 250,000200,000 50,000
DEV25108HRA Land Acquisition - Affordable
Housing
8,000,0005,000,000 3,000,000
ENG21048Yancey Park 22,00022,000
FAC25100City Hall Space Needs Design 56,300,0001,800,000 2,000,000 2,500,000 50,000,000
FAC25102City Hall Deferred Maintenance 12,196,2915,109,023 1,304,651 88,663 5,693,954
FAC25104Golf Course Deferred Maintenance 4,155,7312,025,000 631,000 156,000 8,600 1,335,131
FAC25106Public Works Building Deferred
Maintenance
43,918,7112,123,546 1,945,892 38,929,958 919,315
FAC25107Edinborough Park Asset Preservation 13,326,4389,597,163 3,152,615 576,660
FAC25112Fire Station #1 Deferred Maintenance 2,510,3311,251,082 14,525 1,181,490 63,234
FAC25116Edinborough Pool Mechanical and Filter
Equipment
250,000125,000 125,000
P&R21052CLP Central Park Trellis 450,000150,000 150,000 150,000
P&R21053CLP Rebuild Retaining Walls 400,000200,000 200,000
P&R23106Aquatic Center Deferred Maintenance 1,261,304600,000 452,000 141,988 5,880 61,436
P&R23116Centennial Lakes Park Deferred
Maintenance
1,960,393800,000 956,606 21,732 182,055
P&R25109Trailer Crash Attenuators 35,00035,000
P&R25115Aquatic Center User Feature 2,795,000500,000 470,000 75,000 150,000 100,000 1,500,000
P&R25116Edinborough Pool Resurfacing & Painting 125,000125,000
P&R25120Aquatic Center Changing House
Expansion
6,000,0006,000,000
P&R25122Braemar Arena Pickup Truck 50,00050,000
P&R25124Edina Art Center Design, Fixtures, & Equipment 1,300,000250,000 1,050,000
P&R25128Centennial Lakes Park Paddleboat Replacement 40,00020,000 20,000
P&R25129CLP Golf Course Planting & Pond
Replacement
210,000150,000 60,000
P&R25131Centennial Lakes Park Outdoor Sound
System
150,000150,000
P&R25132Centennial Lakes Park Signage 200,000200,000
P&R25133CLP Amphitheater Maintenance & Bathroom Addition 1,280,00030,000 500,000 750,000
P&R25135Centennial Lakes Park Railings
Replacement
200,000100,000 50,000 50,000
P&R25137Centennial Lakes Park Skating Mats 20,00020,000
P&R25138CLP Main Entrance Paver Replacement 100,000100,000
P&R25140Centennial Lakes Park Clubhouse
Replacement
750,000750,000
300
Total20252026202720282029Source2030Project #
P&R25141CLP Irrigation and Planting Bed
Replacement
200,00050,000 50,000 50,000 50,000
P&R25142CLP Walking Path Repair 600,000100,000 100,000 100,000 100,000 100,000 100,000
P&R25143CLP Lawn Game Replacement/Seating Enhancement 50,00050,000
P&R25144Centennial Lakes Park Site Amenities Replacement 80,00040,000 40,000
P&R25146Centennial Lakes Site and Hardscapes
Repairs
25,925,2007,000,000 13,500,000 5,425,200
P&R25150Edinborough Park Loading Dock 75,00075,000
P&R25158Edinborough Park Locker Room Upgrade 300,000300,000
P&R25159Edinborough Park Entrance & Visitor 1st
Experience
600,000100,000 500,000
P&R25161Permanent Restroom Academy 9 400,000400,000
P&R25173Golf Chemical Fill Station Building/ Wash
Pad
300,000300,000
P&R25179Golf Course Maintenance Building Additions/Upgrade 300,000300,000
POL25102Detective Vehicle Addition 55,00055,000
POL25104Special Operations Radio Headsets 20,00020,000
POL25105Special Operations Night Vision Equipment 80,00080,000
POL25106Preliminary Alcohol Breath Test Devices 20,00020,000
POL25108Special Operations Ballistic Helmet
Replacement
21,00021,000
Funding TBD Total 195,706,39946,840,814 21,793,289 3,832,988 55,336,323 9,661,785 58,241,200
GRAND TOTAL 195,706,39946,840,814 21,793,289 3,832,988 55,336,323 9,661,785 58,241,200
301
FUNDING TBD PROJECTS IN
DETAIL SORTED BY DEPARTMENT
302
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Bill Neuendorf
2025 2030thru Department Comm. Dev. and HRA
Description
Development of the public space at the old public works site.
Project #DEV25104
Justification
Justification - Expansion and/or Level of Service
Sustainability - Adds a passive park in the area.
Community engagement - Aligns with existing approved plans.
Health in all policies - Outdoor walking...social recreation. Pedestrian connectivity.
Race and Equity - Public space open for all.
Useful LifeProject Name HRA Grandview Commons public space.Category Land
Type New
Total Project Cost:$2,500,000
Total2025 2026 2027 2028 2029Expenditures 2030
2,500,0002,500,000Planning and Design
2,500,000 2,500,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
2,500,0002,500,000Funding TBD
2,500,000 2,500,000Total
303
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Stephanie Hawkinson
2025 2030thru Department Comm. Dev. and HRA
Description
Funding source for homeowners association repairs in townhomes/condominium development. (Like the Edina West). These monies get paid back
through assessments.
Project #DEV25105
Justification
Health, Safety & Regulatory Compliance
Sustainability - Helps preserve existing buildngs
Race & Equity - Helps preserve affordable housing
Stewardship - Assists affordable housing with repairs.
Useful LifeProject Name HIA Funding Category Land
Type New
Total Project Cost:$5,000,000
Total2025 2026 2027 2028 2029Expenditures 2030
5,000,0002,500,000 2,500,000Land Acquisition
2,500,000 2,500,000 5,000,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
5,000,0002,500,000 2,500,000Funding TBD
2,500,000 2,500,000 5,000,000Total
304
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Cary Teague
2025 2030thru Department Comm. Dev. and HRA
Description
New/revised study of the Cahill Area office/industrial park.
Project #DEV25106
Justification
Health, Safety & Regulatory Compliance
Justification - Study to determine the future land use in the district. Included goals would be sustainability, built environment, pedestrian movement.
Community Engagement - To be determined, but likely would be extensive.
Health in all policies - Project will look at pedestrian and bike movement throughout the district to provide better connections.
Race & Equity - Examination of appropriate land uses.
Stewardship - Project will help shape development and land use in the area for the next 50 years
Useful LifeProject Name Cahill Area New District Plan Category Land
Type New
Total Project Cost:$250,000
Total2025 2026 2027 2028 2029Expenditures 2030
250,000200,000 50,000Planning and Design
200,000 50,000 250,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
250,000200,000 50,000Funding TBD
200,000 50,000 250,000Total
305
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Stephanie Hawkinson
2025 2030thru Department Comm. Dev. and HRA
Description
Creation of affordable housing to assist the City in meeting its established affordable housing goals with the Metropolitan Council.
Project #DEV25108
Justification
Health, Safety & Regulatory Compliance
Sustainability: Will incorporate per the sustainable buildings policy.
Commnunity Enagagement: Alignment with housing chapter in the Comprehensive Plan & the Housing Strategy Task Force.
Health in All Policies: Healthy homes criteria with access to transit and local amenities.
Race & Equity: Increases the mix of housing options in the City to address diverse housing needs.
Stewardship: Additional housing helps toward the issue of an overall lack of housing options in the Twin Cities, especially affordable housing.
Useful LifeProject Name HRA Land Acquisition - Affordable Housing Category Land
Type New
Total Project Cost:$8,000,000
Total2025 2026 2027 2028 2029Expenditures 2030
8,000,0005,000,000 3,000,000Land Acquisition
5,000,000 3,000,000 8,000,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
8,000,0005,000,000 3,000,000Funding TBD
5,000,000 3,000,000 8,000,000Total
306
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Derik Otten
2025 2030thru Department Engineering
Description
Each building component was evaluated to determine needed maintenance and replacements to extend the buildings lifespan. Maintenance needs
and costs increase as buildings age and are required to avoid unnecessary interruptions in operations due to breakdowns of critical components.
The following components are recommended for service:
2030 - Interior doors, sealed concrete, water fountain, furnace
Stain, restroom accessories, paint, ceramic tile, water htrs, exhaust systems, keyless entry, exit signs, batteries, casework
Wooden wall panelsStain, partitions, toilets, exit signs and batteries
Project #19-946
Justification
See Summary of Facilities Improvements - Funding TBD.
Useful LifeProject Name Walnut Ridge Park Facility Improvements Category Buildings
Type Replace or repair
Total Project Cost:$134,000
Total2025 2026 2027 2028 2029Expenditures 2030
24,000Construction24,000
24,000Total24,000
Total2025 2026 2027 2028 2029Funding Sources 2030
24,000Funding TBD 24,000
24,000Total24,000
307
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Derik Otten
2025 2030thru Department Engineering
Description
Each building component was evaluated to determine needed maintenance and replacements to extend the buildings lifespan. Maintenance needs
and costs increase as buildings age and are required to avoid unnecessary interruptions in operations due to breakdowns of critical components.
The following components are recommended for service:
2030 - Ext wood panel, restroom accessories, ceramic tile carpet tile, paint, exhst system, keyless entry, stain, Janitor sink, plumbing fixtures,
electrical feed, ext stain
Project #ENG21048
Justification
See Summary of Facilities Improvements - Funding TBD.
Useful LifeProject Name Yancey Park Category Buildings
Type Replace or repair
Total Project Cost:$45,000
Total2025 2026 2027 2028 2029Expenditures 2030
22,000Construction22,000
22,000Total22,000
Total2025 2026 2027 2028 2029Funding Sources 2030
22,000Funding TBD 22,000
22,000Total22,000
308
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Derik Otten
2025 2030thru Department Facilities
Description
City Hall Phased Renovations
This project continues the work outlined in the 2019 & 2023 City Hall Space Needs Study and includes projects to renovate and expand areas of
the building that no longer meet the needs of city services.
A phased approach for a project of this size and complexity is needed to minimize the impact on building occupants and public.
2024/5 –Design & Pre-Construction $300K—17-790
Meet with user groups ideas and needs outlined in 2023 space needs document. Work would include design services for phase 1 & 2 of projects
outlined below.
Phase 1 2025-26--Renovation $1.5M
Project would renovate the 2nd floor Administration area, utilizing opportunities created by relocation of election equipment to new storage space
in the building basement. This would allow departments currently scattered around in building to be consolidated to new grouping areas and
provide much needed spaces of various sizes to conduct meetings, prayer and meditative spaces, and nursing areas.
Phase 1a-2025/26 Pre-Construction $500K
Perform investigative testing and site fit services for a new Civic Campus. Proposed project would encompass new Fire Station %233 and
expansion of Police Department & Administrative services.
Budget & schedule for proposed building could be set at this phase.
Phase 2 2026/27—Renovation $2.5M
Continuation of Phase 1 consolidation of departments would allow current office Parks and Rec. area to be converted into flexible meeting &
conference rooms. These rooms would be available to both staff and public for use and a recommendation of the 2019 Space Needs Study.
Police-renovation to both 1st & 2nd floor for better operational flow & staffing additions.
Phase 3a 2029/30 Horizon TBD
Minor expansion near current Mayors Conference room for additional meeting spaces.
Phase 3b 2029/30-Horizon TBD
Civic Campus Design Phase. Build upon information gathered in phase 1a.
Project #FAC25100
Justification
Expansion and/or Level of Service
Sustainability: By providing preventative maintenance and scheduled repairs and replacement the city is able to extend the useful life of equipment
and structures thus eliminating items from the waste stream. This includes minor maintenance like cleaning carpets and painting and major
maintenance such as replacement of HVAC, plumbing, and electrical service equipment.
Community Engagement: Additional conference room space would add options for community gathering not currently available in the space.
Health in All Policies: Gender inclusive restrooms, lactation space are health policies.
Race & Equity: Inclusion elements such as gender inclusive restrooms, prayer and lactation space for the public would be proposed in the project.
Stewardship: By providing preventative maintenance and scheduled repairs and replacement the city is able to extend the useful life of equipment
and structures thus extending the useful life of the buildings ensuring their use by future generations. This includes minor maintenance like
cleaning carpets and painting and major maintenance such as replacement of HVAC, plumbing, and electrical service equipment.
Useful LifeProject Name City Hall Space Needs Design Category Buildings
Type Expand or enhance
Total Project Cost:$56,300,000
Total2025 2026 2027 2028 2029Expenditures 2030
56,300,0001,800,000 2,000,000 2,500,000Planning and Design 50,000,000
1,800,000 2,000,000 2,500,000 56,300,000Total50,000,000
309
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Derik Otten
2025 2030thru Department Facilities
Total2025 2026 2027 2028 2029Funding Sources 2030
56,300,0001,800,000 2,000,000 2,500,000Funding TBD 50,000,000
1,800,000 2,000,000 2,500,000 56,300,000Total50,000,000
310
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Derik Otten
2025 2030thru Department Facilities
Description
"In 2018, the City completed a three-year review process of 117 buildings to create a master replacement schedule for the components of each
physical building. This extensive list includes repairs and replacements of Mechanical Electrical & Plumbing Systems (MEP), Furniture Fixtures
and Equipment (FFE), and the building envelope components like roofing and glazing. Maintaining assets aligns with the following city
goals.Strong Foundation: Maintain Physical Assets and InfrastructureReliable Service: Maintain service levels and best meet the
community needs. to optimize long-term financial resources and meet sustainability goals. Continued reinvestment into the building portfolio
ensures their use by current and future generations. Values entered into 2025 include all outstanding deferred maintenance costs from 2017-
2025"
Project #FAC25102
Justification
Asset Functionality
Sustainability - By providing preventative maintenance and scheduled repairs and replacement the city is able to extend the useful life of equipment
and structures thus eliminating items from the waste stream. This includes minor maintenance like cleaning carpets and painting and major
maintenance such as replacement of HVAC, plumbing, and electrical service equipment.
Community Engagement - Additional conference room space would add options for community gathering not currently available in the space.
Health in All Policies - Gender inclusive restrooms, lactation space are health policies.
Race & Equity - Inclusion elements such as gender inclusive restrooms, prayer and lactation space for the public would be proposed in the project.
Stewardship - By providing preventative maintenance and scheduled repairs and replacement the city is able to extend the useful life of equipment
and structures thus extending the useful life of the buildings ensuring their use by future generations. This includes minor maintenance like
cleaning carpets and painting and major maintenance such as replacement of HVAC, plumbing, and electrical service equipment.
Useful LifeProject Name City Hall Deferred Maintenance Category Buildings
Type Replace or repair
Total Project Cost:$12,196,291
Total2025 2026 2027 2028 2029Expenditures 2030
12,196,2915,109,023 1,304,651 88,663 5,693,954Installation/Maintenance
5,109,023 1,304,651 88,663 5,693,954 12,196,291Total
Total2025 2026 2027 2028 2029Funding Sources 2030
12,196,2915,109,023 1,304,651 88,663 5,693,954Funding TBD
5,109,023 1,304,651 88,663 5,693,954 12,196,291Total
311
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Derik Otten
2025 2030thru Department Facilities
Description
"In 2018, the City completed a three-year review process of 117 buildings to create a master replacement schedule for the components of each
physical building. This extensive list includes repairs and replacements of Mechanical Electrical & Plumbing Systems (MEP), Furniture Fixtures
and Equipment (FFE), and the building envelope components like roofing and glazing. Maintaining assets aligns with the following city
goals.Strong Foundation: Maintain Physical Assets and InfrastructureReliable Service: Maintain service levels and best meet the
community needs. to optimize long-term financial resources and meet sustainability goals. Continued reinvestment into the building portfolio
ensures their use by current and future generations. Values entered into 2025 include all outstanding deferred maintenance costs from 2017-
2025"
Project #FAC25104
Justification
Asset Functionality
Sustainability - By providing preventative maintenance and scheduled repairs and replacement the city is able to extend the useful life of equipment
and structures thus eliminating items from the waste stream. This includes minor maintenance like cleaning carpets and painting and major
maintenance such as replacement of HVAC, plumbing, and electrical service equipment.
Stewardship - By providing preventative maintenance and scheduled repairs and replacement the city is able to extend the useful life of equipment
and structures thus extending the useful life of the buildings ensuring their use by future generations. This includes minor maintenance like
cleaning carpets and painting and major maintenance such as replacement of HVAC, plumbing, and electrical service equipment.
Useful LifeProject Name Golf Course Deferred Maintenance Category Buildings
Type Replace or repair
Total Project Cost:$4,155,731
Total2025 2026 2027 2028 2029Expenditures 2030
4,155,7312,025,000 631,000 156,000 8,600 1,335,131Installation/Maintenance
2,025,000 631,000 156,000 8,600 1,335,131 4,155,731Total
Total2025 2026 2027 2028 2029Funding Sources 2030
4,155,7312,025,000 631,000 156,000 8,600 1,335,131Funding TBD
2,025,000 631,000 156,000 8,600 1,335,131 4,155,731Total
312
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Derik Otten
2025 2030thru Department Facilities
Description
"In 2018, the City completed a three-year review process of 117 buildings to create a master replacement schedule for the components of each
physical building. This extensive list includes repairs and replacements of Mechanical Electrical & Plumbing Systems (MEP), Furniture Fixtures
and Equipment (FFE), and the building envelope components like roofing and glazing. Maintaining assets aligns with the following city
goals.Strong Foundation: Maintain Physical Assets and InfrastructureReliable Service: Maintain service levels and best meet the
community needs. to optimize long-term financial resources and meet sustainability goals. Continued reinvestment into the building portfolio
ensures their use by current and future generations. "
Project #FAC25106
Justification
Asset Functionality
Sustainability - By providing preventative maintenance and scheduled repairs and replacement the city is able to extend the useful life of equipment
and structures thus eliminating items from the waste stream. This includes minor maintenance like cleaning carpets and painting and major
maintenance such as replacement of HVAC, plumbing, and electrical service equipment.
Stewardship - By providing preventative maintenance and scheduled repairs and replacement the city is able to extend the useful life of equipment
and structures thus extending the useful life of the buildings ensuring their use by future generations. This includes minor maintenance like
cleaning carpets and painting and major maintenance such as replacement of HVAC, plumbing, and electrical service equipment.
Useful LifeProject Name Public Works Building Deferred Maintenance Category Buildings
Type Replace or repair
Total Project Cost:$43,918,711
Total2025 2026 2027 2028 2029Expenditures 2030
43,918,7112,123,546 1,945,892 38,929,958 919,315Installation/Maintenance
2,123,546 1,945,892 38,929,958 919,315 43,918,711Total
Total2025 2026 2027 2028 2029Funding Sources 2030
43,918,7112,123,546 1,945,892 38,929,958 919,315Funding TBD
2,123,546 1,945,892 38,929,958 919,315 43,918,711Total
313
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Derik Otten
2025 2030thru Department Facilities
Description
"In 2018, the City completed a three-year review process of 117 buildings to create a master replacement schedule for the components of each
physical building. This extensive list includes repairs and replacements of Mechanical Electrical & Plumbing Systems (MEP), Furniture Fixtures
and Equipment (FFE), and the building envelope components like roofing and glazing. Maintaining assets aligns with the following city
goals.Strong Foundation: Maintain Physical Assets and InfrastructureReliable Service: Maintain service levels and best meet the
community needs. to optimize long-term financial resources and meet sustainability goals. Continued reinvestment into the building portfolio
ensures their use by current and future generations. Values entered into 2025 include all outstanding deferred maintenance costs from 2017-
2025"
Project #FAC25107
Justification
Asset Functionality
Sustainability - By providing preventative maintenance and scheduled repairs and replacement the city is able to extend the useful life of equipment
and structures thus eliminating items from the waste stream. This includes minor maintenance like cleaning carpets and painting and major
maintenance such as replacement of HVAC, plumbing, and electrical service equipment.
Stewardship - By providing preventative maintenance and scheduled repairs and replacement the city is able to extend the useful life of equipment
and structures thus extending the useful life of the buildings ensuring their use by future generations. This includes minor maintenance like
cleaning carpets and painting and major maintenance such as replacement of HVAC, plumbing, and electrical service equipment.
Useful LifeProject Name Edinborough Park Asset Preservation Category Equipment and Vehicles
Type Replace or repair
Total Project Cost:$13,326,438
Total2025 2026 2027 2028 2029Expenditures 2030
13,326,4389,597,163 3,152,615 576,660Installation/Maintenance
9,597,163 3,152,615 576,660 13,326,438Total
Total2025 2026 2027 2028 2029Funding Sources 2030
13,326,4389,597,163 3,152,615 576,660Funding TBD
9,597,163 3,152,615 576,660 13,326,438Total
314
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Derik Otten
2025 2030thru Department Facilities
Description
"In 2018, the City completed a three-year review process of 117 buildings to create a master replacement schedule for the components of each
physical building. This extensive list includes repairs and replacements of Mechanical Electrical & Plumbing Systems (MEP), Furniture Fixtures
and Equipment (FFE), and the building envelope components like roofing and glazing. Maintaining assets aligns with the following city
goals.Strong Foundation: Maintain Physical Assets and InfrastructureReliable Service: Maintain service levels and best meet the
community needs. to optimize long-term financial resources and meet sustainability goals. Continued reinvestment into the building portfolio
ensures their use by current and future generations. Values entered into 2025 include all outstanding deferred maintenance costs from 2017-
2025"
Project #FAC25112
Justification
Asset Functionality
Sustainability - By providing preventative maintenance and scheduled repairs and replacement the city is able to extend the useful life of equipment
and structures thus eliminating items from the waste stream. This includes minor maintenance like cleaning carpets and painting and major
maintenance such as replacement of HVAC, plumbing, and electrical service equipment.
Stewardship - By providing preventative maintenance and scheduled repairs and replacement the city is able to extend the useful life of equipment
and structures thus extending the useful life of the buildings ensuring their use by future generations. This includes minor maintenance like
cleaning carpets and painting and major maintenance such as replacement of HVAC, plumbing, and electrical service equipment.
Useful LifeProject Name Fire Station #1 Deferred Maintenance Category Buildings
Type Replace or repair
Total Project Cost:$2,510,331
Total2025 2026 2027 2028 2029Expenditures 2030
2,510,3311,251,082 14,525 1,181,490 63,234Installation/Maintenance
1,251,082 14,525 1,181,490 63,234 2,510,331Total
Total2025 2026 2027 2028 2029Funding Sources 2030
2,510,3311,251,082 14,525 1,181,490 63,234Funding TBD
1,251,082 14,525 1,181,490 63,234 2,510,331Total
315
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Derik Otten
2025 2030thru Department Facilities
Description
"Assessment, preventative maintenance, and planned replacement to equipment critical to indoor pool operations,. Strong Foundation:
Maintain Physical Assets and InfrastructureReliable Service: Maintain service levels and best meet the community needs. to optimize long-term
financial resources and meet sustainability goals. Continued reinvestment into the building portfolio ensures their use by current and future
generations.
Project #FAC25116
Justification
Asset Functionality
Sustainability - By providing preventative maintenance and scheduled repairs and replacement the city is able to extend the useful life of equipment
and structures thus eliminating items from the waste stream. This includes minor maintenance like cleaning carpets and painting and major
maintenance such as replacement of HVAC, plumbing, and electrical service equipment.
Stewardship - By providing preventative maintenance and scheduled repairs and replacement the city is able to extend the useful life of equipment
and structures thus extending the useful life of the buildings ensuring their use by future generations. This includes minor maintenance like
cleaning carpets and painting and major maintenance such as replacement of HVAC, plumbing, and electrical service equipment.
Useful LifeProject Name Edinborough Pool Mechanical and Filter Equipment Category Equipment and Vehicles
Type Replace or repair
Total Project Cost:$250,000
Total2025 2026 2027 2028 2029Expenditures 2030
250,000125,000 125,000Installation/Maintenance
125,000 125,000 250,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
250,000125,000 125,000Funding TBD
125,000 125,000 250,000Total
316
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Perry Vetter
2025 2030thru Department Park & Recreation
Description
Replacement of the Lewis Park shelter building based on space needs and community engagement. Evaluation of programming and space needs
will be included to determine required square footage. Design will be driven by city goals and values. "
Project #15-049
Justification
The Lewis Park shelter building was designed and built in the 1970's and no longer meets residents' needs. The building requires extensive
maintenance and is recommended for scheduled replacement.
Useful LifeProject Name Lewis Park Shelter Building Replacement Category Buildings
Type Replace or repair
Total Project Cost:$900,000
Total20252026202720282029Expenditures2030
900,000900,000Construction
900,000 900,000Total
Total20252026202720282029Funding Sources 2030
900,000900,000Funding TBD
900,000 900,000Total
317
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Perry Vetter
2025 2030thru Department Park & Recreation
Description
Trailer crash attenuators can reduce the impact due to an accident that could occur while work vehicles are performing tasks on roadways. Trailer
mounted attenuators can be towed by a variety of vehicles in Park Maintenance an Public Works.
Project #P&R25109
Justification
Health, Safety & Regulatory Compliance
Useful LifeProject Name Trailer Crash Attenuators Category Equipment and Vehicles
Type New
Total Project Cost:$35,000
Total2025 2026 2027 2028 2029Expenditures 2030
35,00035,000Vehicles and Equipment
35,000 35,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
35,00035,000Funding TBD
35,000 35,000Total
318
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Derik Otten
2025 2030thru Department Parks: Aquatic Center
Description
In 2018, the City completed a three-year review process of 117 buildings to create a master replacement schedule for the components of each
physical building. This extensive list includes repairs and replacements of Mechanical Electrical & Plumbing Systems (MEP), Furniture Fixtures
and Equipment (FFE), and the building envelope components like roofing and glazing. Maintaining assets aligns with the following city goals.
Project #P&R23106
Justification
See Summary of Facilities Improvements.
Useful LifeProject Name Aquatic Center Deferred Maintenance Category Infrastructure
Type Replace or repair
Total Project Cost:$1,261,304
Total2025 2026 2027 2028 2029Expenditures 2030
1,261,304600,000 452,000 141,988 5,880 61,436Installation/Maintenance
600,000 452,000 141,988 5,880 61,436 1,261,304Total
Total2025 2026 2027 2028 2029Funding Sources 2030
1,261,304600,000 452,000 141,988 5,880 61,436Funding TBD
600,000 452,000 141,988 5,880 61,436 1,261,304Total
319
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Patty McGrath
2025 2030thru Department Parks: Aquatic Center
Description
"Existing user feature require refurbishment and replacement. These features are unique to the Edina Aquatic Center and used to draw visitors to
the park. Replace Shipwreck Zipline & Diving boards $500,000Site User Amenities $470,000Flow-rider Surf Simulator $100,000Slide
Tower Stairs Painting $75,000Water Slide repainting--gel coating $150,000Site User Amenities $470,000Replace Zero Depth Play Structure
$1,500,000"
Project #P&R25115
Justification
Asset Functionality
Sustainability - By providing preventative maintenance and scheduled repairs and replacement the city is able to extend the useful life of equipment
and structures thus eliminating items from the waste stream. This includes minor maintenance like cleaning carpets and painting and major
maintenance such as replacement of HVAC, plumbing, and electrical service equipment.
Stewardship - By providing preventative maintenance and scheduled repairs and replacement the city is able to extend the useful life of equipment
and structures thus extending the useful life of the buildings ensuring their use by future generations. This includes minor maintenance like
cleaning carpets and painting and major maintenance such as replacement of HVAC, plumbing, and electrical service equipment.
Useful LifeProject Name Aquatic Center User Feature Category Parks
Type Replace or repair
Total Project Cost:$2,795,000
Total2025 2026 2027 2028 2029Expenditures 2030
2,795,000500,000 470,000 75,000 150,000 100,000Installation/Maintenance 1,500,000
500,000 470,000 75,000 150,000 100,000 2,795,000Total1,500,000
Total2025 2026 2027 2028 2029Funding Sources 2030
2,795,000500,000 470,000 75,000 150,000 100,000Funding TBD 1,500,000
500,000 470,000 75,000 150,000 100,000 2,795,000Total1,500,000
320
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Patty McGrath
2025 2030thru Department Parks: Aquatic Center
Description
Re-surfacing and painting of indoor pool to maintain surface and integrity of pool.
Project #P&R25116
Justification
Asset Functionality
Sustainability - By providing preventative maintenance and scheduled repairs and replacement the city is able to extend the useful life of equipment
and structures thus eliminating items from the waste stream. This includes minor maintenance like cleaning carpets and painting and major
maintenance such as replacement of HVAC, plumbing, and electrical service equipment.
Stewardship - By providing preventative maintenance and scheduled repairs and replacement the city is able to extend the useful life of equipment
and structures thus extending the useful life of the buildings ensuring their use by future generations. This includes minor maintenance like
cleaning carpets and painting and major maintenance such as replacement of HVAC, plumbing, and electrical service equipment.
Useful LifeProject Name Edinborough Pool Resurfacing & Painting Category Parks
Type Replace or repair
Total Project Cost:$125,000
Total2025 2026 2027 2028 2029Expenditures 2030
125,000125,000Installation/Maintenance
125,000 125,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
125,000125,000Funding TBD
125,000 125,000Total
321
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Rachel Finberg
2025 2030thru Department Parks: Aquatic Center
Description
This project request is for funding modern amenity upgrades for user experience and services. Facility upgrades would include a new admissions
and entry, concessions area, ADA pathway upgrades, expanded pool deck and group area, gender neutral and family restroom upgrades. This
project would increase safety, accessibility, and user experience.
Project #P&R25120
Justification
Expansion and/or Level of Service
Sustainability - Upgrades to mechanical and plumbing systems would be included. This renovation would be subject to Edina Sustainable
Building Policy. Solar feasibility would be included.
Community Engagement - The Aquatic center sees 75,000 visitors a day. Project upgrades would allow for better wayfinding and experience.
Upgrades would increase regional and youth exposure to water safety.
Health in all polilcies - Improvements such as shade structures and healthier concession options would provide health benefits.
Race and equity - Increased accessibility and wayfinding would promote use by public transit and pedestrian access.
Useful LifeProject Name Aquatic Center Changing House Expansion Category Buildings
Type Expand or enhance
Total Project Cost:$6,000,000
Total2025 2026 2027 2028 2029Expenditures 2030
6,000,0006,000,000Construction
6,000,000 6,000,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
6,000,0006,000,000Funding TBD
6,000,000 6,000,000Total
322
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Jesse Buchholz
2025 2030thru Department Parks: Arena
Description
Replace 2009 pickup truck
Project #P&R25122
Justification
Asset Functionality
Sustainability: Current vehicle is not fuel efficient.
Community Engagement: Vehicle allows staff to use throughout the arena, dome and parking areas as well as for hauling, projects and trips for
supplies if needed.
Health in All Policies: New vehicle allows staff to be more efficient in job functions and improve customer service for users and guests.
Race & Equity: New vehicles allows for the city to maintain play spaces that are safe, accessible and welcoming for all.
Stewardship: New vehicle reduces maintenance, fuel and staff time.
Useful LifeProject Name Braemar Arena Pickup Truck Category Equipment and Vehicles
Type Replace or repair
Total Project Cost:$50,000
Total2025 2026 2027 2028 2029Expenditures 2030
50,00050,000Vehicles and Equipment
50,000 50,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
50,00050,000Funding TBD
50,000 50,000Total
323
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Tiffany Bushland
2025 2030thru Department Parks: Centennial Lakes Park
Description
Remove dying trees and stumps and replacing with a pergola system and seating. Trees are currently a hazard.
Project #P&R21052
Justification
The upkeep of City infrastructure is a key component of the Vision Edina document. This trellis system would replace an area that is on the decline
and turn it into an asset.
Useful LifeProject Name CLP Central Park Trellis Category Equipment and Vehicles
Type Expand or enhance
Total Project Cost:$450,000
Total2025 2026 2027 2028 2029Expenditures 2030
450,000150,000 150,000Construction 150,000
150,000 150,000 450,000Total150,000
Total2025 2026 2027 2028 2029Funding Sources 2030
450,000150,000 150,000Funding TBD 150,000
150,000 150,000 450,000Total150,000
324
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Tiffany Bushland
2025 2030thru Department Parks: Centennial Lakes Park
Description
Centennial Lakes Park has over two dozen stone retaining walls of various lengths and heights, all of which are over 20 years old. Many of these
walls are in need of restoration beyond the normal repairs we are able to do ourselves. There is about 1,200 square feet of wall throughout the park
that needs to be restored. The project would involve demolition of existing wall sections, restoration of the wall using existing and new stone, and
adding new landscape fabric and backfill for drainage.
ENVIRONMENTAL CONSIDERATIONS:
We will be reusing as much of our existing natural stone as possible as we rebuild the walls.
Project #P&R21053
Justification
The upkeep of City infrastructure is a key component of Vision Edina. The walls are showing signs of stress and will need to be repaired or will
eventually collapse.
Useful LifeProject Name CLP Rebuild Retaining Walls Category Parks
Type Replace or repair
Total Project Cost:$400,000
Total2025 2026 2027 2028 2029Expenditures 2030
400,000200,000 200,000Construction
200,000 200,000 400,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
400,000200,000 200,000Funding TBD
200,000 200,000 400,000Total
325
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Derik Otten
2025 2030thru Department Parks: Centennial Lakes Park
Description
In 2018, the City completed a three-year review process of 117 buildings to create a master replacement schedule for the components of each
physical building. This extensive list includes repairs and replacements of Mechanical Electrical & Plumbing Systems (MEP), Furniture Fixtures
and Equipment (FFE), and the building envelope components like roofing and glazing. Maintaining assets aligns with the following city goals.
Project #P&R23116
Justification
See Summary of Facilities Improvements.
Useful LifeProject Name Centennial Lakes Park Deferred Maintenance Category Infrastructure
Type Replace or repair
Total Project Cost:$1,960,393
Total2025 2026 2027 2028 2029Expenditures 2030
1,960,393800,000 956,606 21,732 182,055Installation/Maintenance
800,000 956,606 21,732 182,055 1,960,393Total
Total2025 2026 2027 2028 2029Funding Sources 2030
1,960,393800,000 956,606 21,732 182,055Funding TBD
800,000 956,606 21,732 182,055 1,960,393Total
326
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Tiffany Bushland
2025 2030thru Department Parks: Centennial Lakes Park
Description
Replace six paddleboats purchased in 2007-2015.
Project #P&R25128
Justification
Asset Functionality
Health in all policies - Encourage exercise and socialization
Useful LifeProject Name Centennial Lakes Park Paddleboat Replacement Category Parks
Type Replace or repair
Total Project Cost:$40,000
Total2025 2026 2027 2028 2029Expenditures 2030
40,00020,000 20,000Vehicles and Equipment
20,000 20,000 40,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
40,00020,000 20,000Funding TBD
20,000 20,000 40,000Total
327
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Tiffany Bushland
2025 2030thru Department Parks: Centennial Lakes Park
Description
2028 - Repair four ponds along the golf course that are leaking.
2029 - Replace Boulder Pond along south end of the Park.
Project #P&R25129
Justification
Asset Functionality
Sustainability - Reduce water use. Replace current water feature with landscape elements to reduce water use.
Community Engagement - Feature will be safe for enjoyment by all park visitors
Race & Equity - Space would be inclusive for all users of the community.
Health in all policies - Ponds are on putting course and encourage exercise and socialization. Provide space for socialization and gathering.
Stewardship - Reduce maintenance costs to repair amenities.
Useful LifeProject Name CLP Golf Course Planting & Pond Replacement Category Parks
Type Replace or repair
Total Project Cost:$210,000
Total2025 2026 2027 2028 2029Expenditures 2030
210,000150,000 60,000Installation/Maintenance
150,000 60,000 210,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
210,000150,000 60,000Funding TBD
150,000 60,000 210,000Total
328
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Tiffany Bushland
2025 2030thru Department Parks: Centennial Lakes Park
Description
Replace outdoor speakers throughout the Park.
Project #P&R25131
Justification
Asset Functionality
Community Engagement: Entire system would function, providing music throughout park for people to enjoy
Stewardship: Patrons often comment on the uniqueness of having music throughout the park. Specific to Centennial Lakes Park
Useful LifeProject Name Centennial Lakes Park Outdoor Sound System Category Parks
Type Replace or repair
Total Project Cost:$150,000
Total2025 2026 2027 2028 2029Expenditures 2030
150,000Construction150,000
150,000Total150,000
Total2025 2026 2027 2028 2029Funding Sources 2030
150,000Funding TBD 150,000
150,000Total150,000
329
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Tiffany Bushland
2025 2030thru Department Parks: Centennial Lakes Park
Description
Finish replacement of outdoor signage throughout park. $150,000 of ARPA Funds were allocated in 2023-2024 and design was completed along
with some replacement.
Project #P&R25132
Justification
Health, Safety & Regulatory Compliance
Community Engagement - Finish updating wayfinding signage throughout park to provide better user experience.
Race and Equity - Updated signage to serve entire population using the park.
Useful LifeProject Name Centennial Lakes Park Signage Category Parks
Type Replace or repair
Total Project Cost:$200,000
Total2025 2026 2027 2028 2029Expenditures 2030
200,000200,000Vehicles and Equipment
200,000 200,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
200,000200,000Funding TBD
200,000 200,000Total
330
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Tiffany Bushland
2025 2030thru Department Parks: Centennial Lakes Park
Description
2026 - Exterior Envelope Repairs and Replacements
2028 - Addition of bathrooms at the amphitheater
2030 - Replace, repair and paint amphitheater roof and structure. Replace A/V equipment
Project #P&R25133
Justification
Expansion and/or Level of Service, Asset Functionality
Community Engagement: Provide restroom for park users utilizing the amphitheater. Feature will be safe for enjoyment by all park visitors
Race & Equity: Provide enhancement of service at park with diverse audience.
Useful LifeProject Name CLP Amphitheater Maintenance & Bathroom Addition Category Parks
Type Replace or repair
Total Project Cost:$1,280,000
Total2025 2026 2027 2028 2029Expenditures 2030
500,000500,000Construction
780,00030,000Installation/Maintenance 750,000
30,000 500,000 1,280,000Total750,000
Total2025 2026 2027 2028 2029Funding Sources 2030
1,280,00030,000 500,000Funding TBD 750,000
30,000 500,000 1,280,000Total750,000
331
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Tiffany Bushland
2025 2030thru Department Parks: Centennial Lakes Park
Description
Replace railings throughout park in poor condition
Project #P&R25135
Justification
Health, Safety & Regulatory Compliance","Asset Functionality
Community Engagement - Replacement of broken and worn railings will provide safer walking experience for 500,000 visitors
Stewardship - Reduce maintenance costs to repair worn railings.
Useful LifeProject Name Centennial Lakes Park Railings Replacement Category Parks
Type Replace or repair
Total Project Cost:$200,000
Total2025 2026 2027 2028 2029Expenditures 2030
200,000100,000 50,000 50,000Installation/Maintenance
100,000 50,000 50,000 200,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
200,000100,000 50,000 50,000Funding TBD
100,000 50,000 50,000 200,000Total
332
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Tiffany Bushland
2025 2030thru Department Parks: Centennial Lakes Park
Description
Replace rubber flooring used during skating season.
Project #P&R25137
Justification
Asset Functionality
Useful LifeProject Name Centennial Lakes Park Skating Mats Category Parks
Type Replace or repair
Total Project Cost:$20,000
Total2025 2026 2027 2028 2029Expenditures 2030
20,000Vehicles and Equipment 20,000
20,000Total20,000
Total2025 2026 2027 2028 2029Funding Sources 2030
20,000Funding TBD 20,000
20,000Total20,000
333
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Tiffany Bushland
2025 2030thru Department Parks: Centennial Lakes Park
Description
Replace pavers in main park entry.
Project #P&R25138
Justification
Health, Safety & Regulatory Compliance, Asset Functionality
Community Engagement: Replacement of worn pavers and concrete will provide safer walking experience for 500,000 visitors
Health in All Policies: Replacement of worn pavers and concrete will provide safer walking experience for 500,000 visitors
Useful LifeProject Name CLP Main Entrance Paver Replacement Category Parks
Type Replace or repair
Total Project Cost:$100,000
Total2025 2026 2027 2028 2029Expenditures 2030
100,000Construction100,000
100,000Total100,000
Total2025 2026 2027 2028 2029Funding Sources 2030
100,000Funding TBD 100,000
100,000Total100,000
334
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Tiffany Bushland
2025 2030thru Department Parks: Centennial Lakes Park
Description
Replace and enhance the clubhouse at Centennial Lakes Park. Add restrooms and outdoor seating area to the structure.
Project #P&R25140
Justification
Asset Functionality","Health, Safety & Regulatory Compliance","Expansion and/or Level of Service
Community Engagement - Replace building at popular attraction in park that has 500,000 visitors each year.
Health in all policies - Provide covered seating space for socialization and restrooms for easier accessibility.
Useful LifeProject Name Centennial Lakes Park Clubhouse Replacement Category Parks
Type Replace or repair
Total Project Cost:$750,000
Total2025 2026 2027 2028 2029Expenditures 2030
750,000750,000Installation/Maintenance
750,000 750,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
750,000750,000Funding TBD
750,000 750,000Total
335
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Tiffany Bushland
2025 2030thru Department Parks: Centennial Lakes Park
Description
Replace irrigation systems throughout park that are not functioning or require extensive maintenance. Replace landscape in area of irrigation
replacement.
Project #P&R25141
Justification
Asset Functionality
Sustainability - Replace broken irrigation systems with more efficient technology.
Stewardship - Reduce maintenance costs to repair 30 year old irrigation systems.
Useful LifeProject Name CLP Irrigation and Planting Bed Replacement Category Parks
Type Replace or repair
Total Project Cost:$200,000
Total2025 2026 2027 2028 2029Expenditures 2030
200,00050,000 50,000 50,000 50,000Installation/Maintenance
50,000 50,000 50,000 50,000 200,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
200,00050,000 50,000 50,000 50,000Funding TBD
50,000 50,000 50,000 50,000 200,000Total
336
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Tiffany Bushland
2025 2030thru Department Parks: Centennial Lakes Park
Description
Repair concrete walking paths throughout the 1.4 mile loop at Centennial Lakes Park and .75 miles on Edina Promenade. Remove paver inlays
where appropriate.
Project #P&R25142
Justification
Health, Safety & Regulatory Compliance","Asset Functionality
Community Engagement - Repair damaged concrete walking paths will provide safer walking experience for 500,000 visitors
Health in all policies - Project will increase safety of walking paths, encouraging exercise and socialization
Race and equity - Removal of paver inlays will improve walking and riding experience. Increase safety at popular, diverse park.
Stewardship - 500,000 users utilize Centennial Lakes Park every year. The condition and safety of the walking paths is essential to a positive
experience. This project will enhance the public pathways and encourage people to exercise.
Useful LifeProject Name CLP Walking Path Repair Category Parks
Type Replace or repair
Total Project Cost:$600,000
Total2025 2026 2027 2028 2029Expenditures 2030
600,000100,000 100,000 100,000 100,000 100,000Installation/Maintenance 100,000
100,000 100,000 100,000 100,000 100,000 600,000Total100,000
Total2025 2026 2027 2028 2029Funding Sources 2030
600,000100,000 100,000 100,000 100,000 100,000Funding TBD 100,000
100,000 100,000 100,000 100,000 100,000 600,000Total100,000
337
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Tiffany Bushland
2025 2030thru Department Parks: Centennial Lakes Park
Description
Replace Scottish Links with seating area for park users.
Project #P&R25143
Justification
Expansion and/or Level of Service
Sustainability - "Remove bent grass that requires significant maintenance and replace with native plantings and seating areas. "
Community Engagement - Remove paying amenity with free amenity.
Health in all policies - Provide space for socialization and gathering.
Race and equity - Remove paying amenity with free amenity that promotes community.
Stewardship - Remove grass that requires a high level of resources and maintenance and replace with seating area for all park users to enjoy.
Useful LifeProject Name CLP Lawn Game Replacement/Seating Enhancement Category Parks
Type Expand or enhance
Total Project Cost:$50,000
Total2025 2026 2027 2028 2029Expenditures 2030
50,00050,000Installation/Maintenance
50,000 50,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
50,00050,000Funding TBD
50,000 50,000Total
338
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Tiffany Bushland
2025 2030thru Department Parks: Centennial Lakes Park
Description
Replace worn swinging benches, trellis, drinking fountains, and garbage cans
Project #P&R25144
Justification
Health, Safety & Regulatory Compliance","Asset Functionality
Race and Equity - Replace worn amenities at park with diverse audience.
Stewardship - Reduce maintenance costs to repair amenities.
Useful LifeProject Name Centennial Lakes Park Site Amenities Replacement Category Parks
Type Replace or repair
Total Project Cost:$80,000
Total2025 2026 2027 2028 2029Expenditures 2030
80,00040,000 40,000Installation/Maintenance
40,000 40,000 80,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
80,00040,000 40,000Funding TBD
40,000 40,000 80,000Total
339
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Tiffany Bushland
2025 2030thru Department Parks: Centennial Lakes Park
Description
A site evaluation of Centennial Lakes Park was conducted in 2021 to review all exterior hardscapes and park infrastructure. Including sidewalks,
benches and railings, irrigation systems, and site specific lighting. The report provided by Kimley-Horn & associates identified 3 priorities of
repairs throughout the parkHigh--Items in critical or near critical need for replacement $7.0MMed--Items less critical with 5-10 years of life
expectance $13.5MLow--Items deemed non-critical 10+ years of life expectance $5.5MAs these items were not previously tracked or
reported in CIP plans they lacked major funding for replacement and should be included in this and future CIP projects as deferred maintenance.
Project #P&R25146
Justification
Asset Functionality
Stewardship: By providing preventative maintenance and scheduled repairs and replacement the city is able to extend the useful life of equipment
and structures thus extending the useful life of the buildings ensuring their use by future generations. This includes minor maintenance like
cleaning carpets and painting and major maintenance such as replacement of HVAC, plumbing, and electrical service equipment.
Useful LifeProject Name Centennial Lakes Site and Hardscapes Repairs Category Parks
Type Replace or repair
Total Project Cost:$25,925,200
Total2025 2026 2027 2028 2029Expenditures 2030
25,925,2007,000,000 13,500,000Construction 5,425,200
7,000,000 13,500,000 25,925,200Total5,425,200
Total2025 2026 2027 2028 2029Funding Sources 2030
25,925,2007,000,000 13,500,000Funding TBD 5,425,200
7,000,000 13,500,000 25,925,200Total5,425,200
340
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Derik Otten
2025 2030thru Department Parks: Edinborough Park
Description
Expand loading dock area for additional trash enclosure space. Includes repairs to loading dock surfaces. Repairs to exterior lighting at
South entrance- $50,000
Project #P&R25150
Justification
Asset Functionality
Sustainability: By providing preventative maintenance and scheduled repairs and replacement the city is able to extend the useful life of equipment
and structures thus eliminating items from the waste stream. This includes minor maintenance like cleaning carpets and painting and major
maintenance such as replacement of HVAC, plumbing, and electrical service equipment.
Stewardship: By providing preventative maintenance and scheduled repairs and replacement the city is able to extend the useful life of equipment
and structures thus extending the useful life of the buildings ensuring their use by future generations. This includes minor maintenance like
cleaning carpets and painting and major maintenance such as replacement of HVAC, plumbing, and electrical service equipment
Useful LifeProject Name Edinborough Park Loading Dock Category Parks
Type Expand or enhance
Total Project Cost:$125,000
Total2025 2026 2027 2028 2029Expenditures 2030
125,00050,000 75,000Construction
50,000 75,000 125,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
50,00050,000Edinborough Fund
75,00075,000Funding TBD
50,000 75,000 125,000Total
341
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Patty McGrath
2025 2030thru Department Parks: Edinborough Park
Description
Upgrade the locker rooms to become ADA compliant.
Project #P&R25158
Justification
Health, Safety & Regulatory Compliance, Expansion and/or Level of Service
Health in All Policies: The existing locker rooms (toilets, showers and sinks) do not meet ADA requirements and limits access for some patrons.
Useful LifeProject Name Edinborough Park Locker Room Upgrade Category Parks
Type Expand or enhance
Total Project Cost:$300,000
Total2025 2026 2027 2028 2029Expenditures 2030
300,000300,000Construction
300,000 300,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
300,000300,000Funding TBD
300,000 300,000Total
342
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Derik Otten
2025 2030thru Department Parks: Edinborough Park
Description
Enhance dated and damaged areas of East drive up entrance at Edinborough Park. Area will require new concrete sidewalks, pedestrian lighting
and landscaping. Existing entrance was constructed in 1990's and components are failing.Strong Foundation: Maintain Physical Assets and
InfrastructureReliable Service: Maintain service levels and best meet the community needs. to optimize long-term financial resources and meet
sustainability goals. Continued reinvestment into the building portfolio ensures their use by current and future generations.
Project #P&R25159
Justification
Asset Functionality
Stewardship: By providing preventative maintenance and scheduled repairs and replacement the city is able to extend the useful life of equipment
and structures thus extending the useful life of the buildings ensuring their use by future generations. This includes minor maintenance like
cleaning carpets and painting and major maintenance such as replacement of HVAC, plumbing, and electrical service equipment.
Useful LifeProject Name Edinborough Park Entrance & Visitor 1st Experience Category Parks
Type Replace or repair
Total Project Cost:$600,000
Total2025 2026 2027 2028 2029Expenditures 2030
600,000100,000 500,000Construction
100,000 500,000 600,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
600,000100,000 500,000Funding TBD
100,000 500,000 600,000Total
343
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Joe Abood
2025 2030thru Department Parks: Golf Course
Description
Remove temporary/portable restroom on Academy 9 Golf Course and replace with permanent structure.
Project #P&R25161
Justification
Expansion and/or Level of Service
Sustainability: Braemar Golf Course is recognized for its Environmental Excellence as a “Certified Audubon Cooperative Sanctuary” through the
Audubon Cooperative Sanctuary Program for Golf Courses, an Audubon International program.
Braemar is one of 900 courses in the world to receive this honor for maintaining a high degree of environmental quality and natural resources in
areas including wildlife and habitat management, chemical use reduction and safety, water quality management and environmental planning.
Braemar was first certified in 2005 and has been able to retain the honor every three years during the recertification process.
Braemar’s Championship 18 opened in May 2019 after being transformed into a 6,884-yard regulation18-hole golf course. The redesign included a
significant environmental statement by restoring 4.37 acres of wetlands and enhancing a bit over a half-acre of additional wetlands, creating 32.11
acres of wetland buffer and introducing 33.85 acres of Oak Savanna throughout the course.
Community Engagement: At the heart of Braemar Golf Course lies a sense of camaraderie and social interaction. Braemar brings people together,
providing a platform for its patrons to connect, bond, and forge friendships. Braemar becomes a place where golfers of all skill levels, ages and
abilities can come together, share experiences, and create a welcoming atmosphere that extends beyond the fairways. It's this sense of belonging
that enhances the overall golfing experience and makes it truly special.
Health in All Policies: Golf is a great way to enjoy regular exercise, develop social connections, and manage stress.
Race & Equity: Braemar Golf Course is committed to being welcoming and inclusive to all who patronize the facility. To support and foster
inclusivity, Braemar staff members are dedicated to acknowledging, seeking out and celebrating the diversity of its customers and proactively
working together to eliminate systemic and institutional barriers to ensure all people have the opportunity to participate in golf at its facilities.
Stewardship: Braemar Golf Course is committed to maintaining the golf course to the highest standard while preserving and enhancing the
surrounding wildlife environment. Braemar demonstrates a high degree of environmental quality in a number of areas including environmental
planning, wildlife & habitat management, outreach & education, integrated pest management, water conservation, and water quality management.
Useful LifeProject Name Permanent Restroom Academy 9 Category Parks
Type New
Total Project Cost:$400,000
Total2025 2026 2027 2028 2029Expenditures 2030
400,000400,000Construction
400,000 400,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
400,000400,000Funding TBD
400,000 400,000Total
344
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Joe Abood
2025 2030thru Department Parks: Golf Course
Description
This was included in the building study plan. At this time, we have a “closet” for chemical storage and how we fill our sprayer is not up to OSHA
standards. A separate building for chemical storage and proper loading and mixing with proper containment is proposed. A recycled wash pad is
also being proposed.
Project #P&R25173
Justification
Health, Safety & Regulatory Compliance
Sustainability: Braemar Golf Course is recognized for its Environmental Excellence as a “Certified Audubon Cooperative Sanctuary” through the
Audubon Cooperative Sanctuary Program for Golf Courses, an Audubon International program.
Braemar is one of 900 courses in the world to receive this honor for maintaining a high degree of environmental quality and natural resources in
areas including wildlife and habitat management, chemical use reduction and safety, water quality management and environmental planning.
Braemar was first certified in 2005 and has been able to retain the honor every three years during the recertification process.
Braemar’s Championship 18 opened in May 2019 after being transformed into a 6,884-yard regulation18-hole golf course. The redesign included a
significant environmental statement by restoring 4.37 acres of wetlands and enhancing a bit over a half-acre of additional wetlands, creating 32.11
acres of wetland buffer and introducing 33.85 acres of Oak Savanna throughout the course.
Community Engagement: At the heart of Braemar Golf Course lies a sense of camaraderie and social interaction. Braemar brings people together,
providing a platform for its patrons to connect, bond, and forge friendships. Braemar becomes a place where golfers of all skill levels, ages and
abilities can come together, share experiences, and create a welcoming atmosphere that extends beyond the fairways. It's this sense of belonging
that enhances the overall golfing experience and makes it truly special.
Health in All Policies: Golf is a great way to enjoy regular exercise, develop social connections, and manage stress.
Race & Equity: Braemar Golf Course is committed to being welcoming and inclusive to all who patronize the facility. To support and foster
inclusivity, Braemar staff members are dedicated to acknowledging, seeking out and celebrating the diversity of its customers and proactively
working together to eliminate systemic and institutional barriers to ensure all people have the opportunity to participate in golf at its facilities.
Stewardship: Braemar Golf Course is committed to maintaining the golf course to the highest standard while preserving and enhancing the
surrounding wildlife environment. Braemar demonstrates a high degree of environmental quality in a number of areas including environmental
planning, wildlife & habitat management, outreach & education, integrated pest management, water conservation, and water quality management.
Useful LifeProject Name Golf Chemical Fill Station Building/ Wash Pad Category Parks
Type Expand or enhance
Total Project Cost:$300,000
Total2025 2026 2027 2028 2029Expenditures 2030
300,000300,000Construction
300,000 300,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
300,000300,000Funding TBD
300,000 300,000Total
345
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Joe Abood
2025 2030thru Department Parks: Golf Course
Description
Additions/Upgrades to Breakroom, add an Office and expand Main Shop. Current space is inadequate for growth of facility.
Project #P&R25179
Justification
Expansion and/or Level of Service
Sustainability: Braemar Golf Course is recognized for its Environmental Excellence as a “Certified Audubon Cooperative Sanctuary” through the
Audubon Cooperative Sanctuary Program for Golf Courses, an Audubon International program.
Braemar is one of 900 courses in the world to receive this honor for maintaining a high degree of environmental quality and natural resources in
areas including wildlife and habitat management, chemical use reduction and safety, water quality management and environmental planning.
Braemar was first certified in 2005 and has been able to retain the honor every three years during the recertification process.
Braemar’s Championship 18 opened in May 2019 after being transformed into a 6,884-yard regulation18-hole golf course. The redesign included a
significant environmental statement by restoring 4.37 acres of wetlands and enhancing a bit over a half-acre of additional wetlands, creating 32.11
acres of wetland buffer and introducing 33.85 acres of Oak Savanna throughout the course.
Community Engagement: At the heart of Braemar Golf Course lies a sense of camaraderie and social interaction. Braemar brings people together,
providing a platform for its patrons to connect, bond, and forge friendships. Braemar becomes a place where golfers of all skill levels, ages and
abilities can come together, share experiences, and create a welcoming atmosphere that extends beyond the fairways. It's this sense of belonging
that enhances the overall golfing experience and makes it truly special.
Health in All Policies: Golf is a great way to enjoy regular exercise, develop social connections, and manage stress.
Race & Equity: Braemar Golf Course is committed to being welcoming and inclusive to all who patronize the facility. To support and foster
inclusivity, Braemar staff members are dedicated to acknowledging, seeking out and celebrating the diversity of its customers and proactively
working together to eliminate systemic and institutional barriers to ensure all people have the opportunity to participate in golf at its facilities.
Stewardship: Braemar Golf Course is committed to maintaining the golf course to the highest standard while preserving and enhancing the
surrounding wildlife environment. Braemar demonstrates a high degree of environmental quality in a number of areas including environmental
planning, wildlife & habitat management, outreach & education, integrated pest management, water conservation, and water quality management.
Useful LifeProject Name Golf Course Maintenance Building Additions/Upgrade Category Buildings
Type Expand or enhance
Total Project Cost:$300,000
Total2025 2026 2027 2028 2029Expenditures 2030
300,000300,000Construction
300,000 300,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
300,000300,000Funding TBD
300,000 300,000Total
346
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Aaron White
2025 2030thru Department Police
Description
This will add a unmarked detective car to the police fleet. A new Detective position was authorized in the 2024 budget with a total of six new
positions in 2024-25. Detectives are assigned an unmarked police vehicle to carry out their job duties. Open positions in the department have
allowed us to defer this addition until 2025. The cost includes the vehicle, emergency equipment, and upfitting costs. Costs are higher for the
initial build of this police vehicle due to systems that are typically purchased for the entire fleet under other projects. This build includes a mobile
radio, first aid/AED equipment, and a patrol rifle. ***May be eligible for Public Safety Grant Funding***
Project #POL25102
Justification
Expansion and/or Level of Service
Sustainability: The Police Department continues to incorporate fully electric (EV) and hybrid vehicles into our fleet. Typically we utilize hybrid
vehicles for unmarked Detective cars. Vehicle procurement has become very difficult in recent years and the final selection will be based on
vehicle availability.
Community Engagement: Police vehicles are essential for officers to carry out their job duties.
Health in All Policies: An adequate and reliable fleet of emergency response vehicles is essential for our police officers to carry out their job duties.
Race & Equity: Promotes accessibility of police services to all members of the community
Stewardship: The police department continues to responsibly manage our fleet to maximize efficiency and minimize cost while prioritizing public
safety and employee safety.
Useful LifeProject Name Detective Vehicle Addition Category Equipment and Vehicles
Type New
Total Project Cost:$55,000
Total2025 2026 2027 2028 2029Expenditures 2030
55,00055,000Vehicles and Equipment
55,000 55,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
55,00055,000Funding TBD
55,000 55,000Total
347
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Aaron White
2025 2030thru Department Police
Description
Replace (15) SWAT team radio headsets. Radio headsets allow SWAT team operators and paramedics to communicate effectively during special
operations. Existing headsets are over 10 years old, are no longer serviceable, and require replacement. This is essential safety equipment required
for SWAT operations. This items should be added to the Equipment Replacement Schedule. ***May be eligible for Public Safety Grant
Funding***
Project #POL25104
Justification
Health, Safety & Regulatory Compliance, Asset Functionality
Sustainability: Existing equipment will be properly recycled.
Community Engagement: Properly equipping our SWAT team assures effective and efficient police response to any situation in the community.
Health in All Policies: We have an obligation to our employees to provide the equipment necessary to keep them safe. Technology, tactics, and
threats rapidly evolve and this investment is critical to keep our SWAT team properly equipped.
Race & Equity: Promotes accessibility of police services to all members of the community.
Stewardship: The SWAT team has extended the life of existing equipment to over 10 years through proper maintenance and repair. Replacing the
equipment now is essential for officer safety and effective SWAT operations.
Useful LifeProject Name Special Operations Radio Headsets Category Equipment and Vehicles
Type Replace or repair
Total Project Cost:$20,000
Total2025 2026 2027 2028 2029Expenditures 2030
20,00020,000Vehicles and Equipment
20,000 20,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
20,00020,000Funding TBD
20,000 20,000Total
348
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Aaron White
2025 2030thru Department Police
Description
Replace (11) night vision units, IR aiming, and mounting hardware for SWAT team. Night vision equipment is used in SWAT Special Operations
when operating in dark conditions indoors or out. The current SWAT night vision equipment is 20 years old and was acquired at the time through
a donation. This equipment is long past its useful service life and requires replacement. This item should be added to the equipment replacement
schedule. ***May be eligible for Public Safety Grant Funding***
Project #POL25105
Justification
Health, Safety & Regulatory Compliance, Asset Functionality
Sustainability: Existing equipment will be recycled properly.
Community Engagement: Properly equipping our SWAT team assures effective and efficient police response to any situation in the community.
Health in All Policies: We have an obligation to our employees to provide the equipment necessary to keep them safe. Technology, tactics, and
threats rapidly evolve and this investment is critical to keep our SWAT team properly equipped.
Race & Equity: Promotes accessibility of police services to all members of the community.
Stewardship: The SWAT team has extended the life of existing equipment for 20 years through proper maintenance and repair. Replacing the
equipment now is essential for officer safety and effective SWAT operations.
Useful LifeProject Name Special Operations Night Vision Equipment Category Equipment and Vehicles
Type Replace or repair
Total Project Cost:$80,000
Total2025 2026 2027 2028 2029Expenditures 2030
80,00080,000Vehicles and Equipment
80,000 80,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
80,00080,000Funding TBD
80,000 80,000Total
349
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Aaron White
2025 2030thru Department Police
Description
Replace preliminary breath test (PBT) devices used in the field for a preliminary measurement of blood alcohol concentration. These devices are
used in the enforcement of DWI and other alcohol related offenses. They are also used in medical situations to assess cases of extreme intoxication
or unknown substance influence. PBT units are in all patrol squads and assigned to SROs in the schools. The existing units are more than 15 years
old and have reached the end of their useful life.
Project #POL25106
Justification
Health, Safety & Regulatory Compliance, Asset Functionality
Sustainability: Existing equipment will be recycled properly. Consideration will be given to products that minimize waste.
Community Engagement: Equipment allows officers to efficiently carry out their duties in traffic enforcement and provide more effective medical
care.
Health in All Policies: This equipment is necessary to assist police in addressing alcohol related issues in the community including the threats to
public safety from intoxicated drivers.
Race & Equity: Promotes accessibility of police services to all members of the community.
Stewardship: The department has long extended the life of existing equipment through proper maintenance and repair. Product selection will give
consideration to reliability and serviceability to again minimize future replacement.
Useful LifeProject Name Preliminary Alcohol Breath Test Devices Category Equipment and Vehicles
Type Replace or repair
Total Project Cost:$20,000
Total2025 2026 2027 2028 2029Expenditures 2030
20,00020,000Vehicles and Equipment
20,000 20,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
20,00020,000Funding TBD
20,000 20,000Total
350
Capital Improvement Plan - UNFUNDED
City of Edina, Minnesota Contact Aaron White
2025 2030thru Department Police
Description
Replace ballistic helmets for SWAT officers and paramedics. This is a required replacement of existing personal safety equipment. Costs have
increased over the years bringing this to the level of CIP, it should be added to the equipment replacement schedule moving forward.
Project #POL25108
Justification
Health, Safety & Regulatory Compliance, Asset Functionality
Sustainability: Existing equipment will be recycled properly. Consideration will be given to products that minimize waste.
Community Engagement: Properly equipping our SWAT team assures effective and efficient police response to any situation in the community.
Health in All Policies: This is essential personal safety equipment necessary to operate a SWAT team.
Race & Equity: Promotes accessibility of police services to all members of the community.
Stewardship: The SWAT team repairs and maintains all equipment to maximize effective service life. Replacing the equipment is essential for
officer safety and effective SWAT operations.
Useful LifeProject Name Special Operations Ballistic Helmet Replacement Category Equipment and Vehicles
Type Replace or repair
Total Project Cost:$21,000
Total2025 2026 2027 2028 2029Expenditures 2030
21,00021,000Vehicles and Equipment
21,000 21,000Total
Total2025 2026 2027 2028 2029Funding Sources 2030
21,00021,000Funding TBD
21,000 21,000Total
351